FOLK CONSTRUCTION CO., INC., WAB No. 76-02 (WAB Feb. 26, 1976)


CCASE: WAB CASE NO. 76-02 DDATE: 19760226 TTEXT: ~1 [1] [ 76-02.WAB ATTACHMENT] TELEGRAPHIC MESSAGE NAME OF AGENCY: U.S. Department of Labor Office of Labor Relations and Civil Rights ACCOUNTING CLASSIFICATION: 6165-2-2-N-500-72500-2330-000 DATE PREPARED: 2/26/76 NAME: Terry R. Yellig TO: All Interested Parties on attached sheet RE: WAB CASE NO. 76-02 TOM BIGBY WATERWAY, MS PREVAILING WAGE RATES APPLICABLE TO CONSTRUCTION OF ILLINOIS CENTRAL GULF RAILROAD RELOCATION. WAGE DECISION NO. 76-MS-41 TOM BIGBY WATERWAY MISS. THE BOARD HAS CAREFULLY AND THOROUGHLY REVIEWED THE RECORDS AND DATA SUBMITTED IN THIS CASE TOGETHER WITH THE PRE-HEARING BRIEFS AND THE ARGUMENTS AND DISCUSSIONS AT THE TWO HEARINGS FEBRUARY 13 AND FEBRUARY 25, 1976 AND IS CONVINCED THAT THE TWO PRINCIPLES AND PROCEDURES APPLIED BY THE ESA WITH RESPECT TO WAGE PREDETERMINATION NO. 76-MS-41, ISSUED FEBRUARY 23, 1976 ARE APPLICABLE AND APPROPRIATE. THE BOARD HAS ADOPTED A SHORT FORM DECISION AND ORDER IN THIS MATTER TO MEET THE REQUESTS OF ALL PARTIES FOR EXPEDITION. A SUPPLEMENTARY DECISION WILL FOLLOW. THE PETITION IS DENIED. BY CHAIRMAN OSCAR SMITH AND MEMBER STUART ROTHMAN [1]



Phone Numbers