skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

Brown's Mill Road Bus Facilities, WAB No. 1975-11 (WAB Apr. 19, 1976)


CCASE: BROWN'S MILL ROAD BUS DDATE: 19760419 TTEXT: ~1 [1] UNITED STATES OF AMERICA DEPARTMENT OF LABOR DECISIONS AND ORDERS OF THE WAGE APPEALS BOARD IN THE MATTER OF The Prevailing Wage Rates WAB Applicable to the Metropolitan CASE NO. 75-11 Atlanta Rapid Transit Authority's Contract GN-01, Site Clearance, Dated: April 19, 1976 Grading, Paving and Related Work for the Brown's Mill Road Bus Facilities, Atlanta, Georgia DECISION AND ORDER APPEARANCES: Ronald S. Cooper, Esq., Steptoe & Johnson for Petitioners George E. Rivers, Esq., Counsel for Construction Wage Standards, for U.S. Department of Labor Joseph Jacobs, Esq., Jacobs, Jacobs and Davis for North Georgia Building and Construction Trades Council BEFORE: Oscar S. Smith, Chairman, and Clarence D. Barker, Member and Stuart Rothman, Member. [1] ~2 [2] THE PETITION This matter is before the Board on a petition of the Metropolitan Atlanta Rapid Transit Authority (herein MARTA) dated September 3, 1975, seeking reversal of a decision made by the Assistant Administrator, Wage and Hour Division, United States Department of Labor (herein ESA) pursuant to section 13 of the Urban Mass Transportation Act of 1964, as amended, 49 U.S.C. [sec] 1609. On May 15, 1975, ESA advised the Regional Engineer of the Urban Mass Transportation Administration, Department of Transportation (herein UMTA) that the inclusion of the "highway" wage rate schedule in the advertised specifications for Contract GN-01 on the Brown's Mill Road Bus Facilities (herein "the project" or "Brown's Mill project" was incorrect. UMTA was advised that the building wage rate schedule published in the Federal Register /FN1/ should be included in the invitations for bid. On July 18, 1975, MARTA requested reconsideration of ESA's determination. ESA affirmed its decision on August 4, 1975. Following numerous postponements prompted in part by priority interests of the parties on other MARTA matters before the Board /FN2/ and concurrent litigation instituted [2] ?????????????????????????????? /FN1/ 40 FR 6020, February 7, 1975, modified by 40 FR 16478, April 11, 1975. /FN2/ WAB Decision No. 75-05, August 25, 1975, supplemented on October 15 and 30, 1975. ~3 [3] by the North Georgia Building and Construction Trades Council (herein North Georgia) to enjoin MARTA from awarding a contract which included the highway wage rate schedule, a hearing was held before the Board on December 16, 1975. Sometime prior to the hearing, MARTA awarded Contract GN-01 to Blount Construction Company (herein Blount) incorporating the highway wage rate schedule. THE BROWN'S MILL ROAD BUS FACILITIES PROJECT OF WHICH CONTRACT GN-01 IS A PART The project is a facility utilizing approximately seventeen acres in southeast Atlanta and includes (1) off-schedule parking spaces for 227 buses, (2) an operating garage (34,359 square feet) for minor repairs and routine service and maintenance such as lubrication and oil changes, (3) between 175 to 200 parking spaces for private cars of bus drivers and employees of the operating garage, (4) a "heavy maintenance" garage (113,380 square feet) for major repairs and maintenance of the MARTA fleet and (5) an additional 250 to 300 parking spaces for employees, vendors and others with business associated with the heavy maintenance garage including spaces for use in scheduling business in and out of the garage. For the Brown's Mill Project, MARTA served as its own general contractor using a "contract administrator," J. A. Jones Construction Company, to coordinate the work of the separately awarded contract "packages of work [,]" [3] ~4 [4] sub-items "Description and Scope of the Work," "Work by Others," "Time of Completion," "Coordination with other Contractors," and "Delays Caused by Other Contracts," as follows: Description and Scope of Work: Perform all Site Work shown on the-drawings and/or described in the specifications. For the convenience of the Contractor, such work includes, but is not limited to, the following: A. In Phase I of the site work, complete the following items of work. 1. Extend and hook-up temporary utilities to Construction Manager's trailers, including water, sewer, and power. 2. Furnish access and parking area for Construction Manager's trailers. Provide the storage areas, as designated on the drawings, graded and with stone base and binder course in place for use of other contractor's trailers, and material storage. 3. Furnish and install temporary fencing and gates. 4. Complete all clearing, grubbing and removal of debris. 5. Complete all site excavation, fill, rough grading work, and compaction, including the building areas to floor slab subgrade (+0.10 feet). 6. Complete the storm water retention structure including compact fill, concrete spillways, associated piping, and permanent fencing. 7. Complete all storm drainage, beginning 5 feet outside the buildings, including catchbasins, manholes, headwalls, ditchpaving, etc. Adjust tops of existing manholes and catchbasins to final grade. 8. Excavate, construct and backfill all site retaining walls except the East wall of the Heavy Maintenance Building and its extensions North and South of the Building. The excavation [4] ~5 [5] for the retaining wall at the East side of the Heavy Maintenance Building shall be performed in this contract under Phase I. The machine backfill to the subgrade of the Parking lot on the East side of the retaining wall will be done in this contract. The actual construction of this wall will be done by others. 9. Excavate, furnish, install, test and backfill water lines and fire lines from the meter or property line to within 5 feet of the buildings at locations as shown on the drawings. Furnish and install concrete encased ducts for electrical primary power feeds and phone lines from the property line to within 5 feet of the building at locations shown on the drawings. 10. Furnish and install temporary power located as shown on the drawings and specified in S.C. 1.14. 11. Extend the sanitary sewer lines from 5 feet of the building to tie into the existing sanitary sewers as shown on the drawings, including manholes and drop manholes as shown. 12. The gas lines will be run to the buildings by the utility companies before the paving base course is started. 13. Install, cap and test water lines from 5 feet of the building for the future bus wash area and lawn sprinklering systems as shown on the drawings. 14. Install temporary drain lines so that the building site area will be able to be drained of water during construction. 15. Furnish and install site lighting, including foundations, poles, lights, underground conduits from 5 feet of building (capped at this point). Wiring between poles and poles themselves shall be under this contract. Wiring of home runs shall be done by others. 16. On the bank slopes indicated on the drawings, plant ground cover LO control the erosion of the slopes. This should be done as soon after the bank slopes are completed as possible. [5] ~6 [6] 17. Provide curb and gutter work as shown on the drawings. 18. Provide base course for concrete and asphaltic paving. Hold the base back from the buildings and underground tanks twenty (20) feet during Phase I. 19. Provide the binder course for the asphaltic concrete paving. 20. Provide all engineering layout work as required to complete your work. 21. Safety barricades, trench bracing, warning lights, etc. B. In Phase II of the site work, complete the following items of work: 1. Complete base course work around buildings and over the underground tanks. Dress up the remainder base course as required. 2. Provide the wearing course on the asphaltic concrete, as indicated in the drawings. 3. Provide the concrete paving as shown on the drawings. 4. Provide painting, striping and marking of parking areas, drives, ramps, etc., as shown on the drawings. 5. Provide precast concrete bumpers as shown for the parking areas. 6. Excavate, form, pour, finish, and backfill exterior steps and sidewalks; furnish and install rails for the steps, as shown on the drawings. 7. Remove temporary fencing and gates. Provide the permanent security fencing gates, and guard rails as shown on the drawings. 8. Furnish and install the flag pole(s) as shown on the drawings. 9. Complete the corrective work as listed on the Punch-List. 10. Furnish As-Built Drawings as follows: [6] ~7 [7] Underground Power Distribution - Electrical * Water * Storm & Sanitary Sewer System * Fire Lines * Gas * Telephone 1.02 Work by Others: The work described below, which precedes, relates to or follows the work in Article 1.01 above, will be accomplished by others: Concrete work inside the building lines, footing excavations for building footings, pits, etc. The retaining walls at the East side of the Heavy Maintenance Building. Water, sewer, storm drainage, underground piping, and conduits all within the foot print of the buildings and 5 feet outside the building lines. Underground tanks, their excavation, installation and backfill. Masonry work in the buildings, roofing, doors, windows, partitions, painting, fixed equipment, tools, and furnishings. The application fees and monthly charges for temporary utilities for the Construction Manager's trailer and building sites. Gas piping on site, primary electrical feeds on site, and telephone cables. Preparation of approved re-inforcing steel shop drawings and bar list for retaining walls. 1.03 Time of Completion: The work as described in Article 1.01 above shall be completed within three hundred seventy eight (378) days after the effective date of the Notice to Proceed. In addition to meeting the final completion date, portions of the work which affect the work of other contractors shall be completed as follows (coordination dates): Portion of the Work [:] Within Number of Days From NTP [:] Temporary Fence and Gates 20 Building Areas Grading Complete 75 Storage Areas Ready for Use 82 Temporary Power and Water at Buildings 82 Start Backfill behind Heavy Maintenance Retaining Wall 146 Complete Base Course and Binder Course and Phase I Operations 174 Begin Final Operations, Phase II 319 Complete Contract 378 [7] ~8 [8] 1.04 Coordination with other Contractors. This project will be constructed using phased construction involving approximately 10 packages of work, each awarded to the low, responsible bidder. The work will be scheduled and coordinated by MARTA's Construction Manager, J. A. Jones Construction Company. Cooperation and coordination with other contractors will be required. 1.05 Delays Caused by Other Contractors: The completion of certain work-described in Article 1.02 above may in some cases determine the date upon which a portion of your work can commence. While every effort will be made to stay on or ahead of schedule, it is possible that some such work will, under extenuating circumstances, be delayed. Therefore, each contractor should plan on adjusting the coordination dates above by up to 30 days. If you are delayed in starting any portion of your work, you will of course be eligible for a corresponding extension of time on that portion and any other portions affected by the delay. 1.06 Liquidated Damages, specified in Article GC8.9, shall be in the amount of $500.00 per day. * * * Contract GN-01 is one of approximately fifteen separate contracts to be advertised for the construction of the Brown's Mill facility. More specifically, Contract GN-01 and the nine other contracts awarded prior to t-he December 16, 1976 hearing and their status [DO NOT] follow: [8] ~9 [PAGES 9, 10, AND 11 ARE THREE PAGES OF HORIZONTAL CHARTS WITH THE FOLLOWING INFORMATION PERTAINING TO NINE MARTA CONTRACTS: CONTRACT NUMBER, PRIME CONTRACTOR, ORIGINAL CONTRACT DOLLAR AMOUNT, WAGE SCHEDULE TYPE, NOTICE TO PROCEED DATE, DESCRIPTION OF CONTRACT WORK, AND CURRENT STATUS; THE CHARTS ARE AVAILABLE UPON REQUEST FROM THE BOARD'S OFFICES] [9][10][11] ~12 [12] THE BACKGROUND OF THE DISPUTE BETWEEN MARTA AND ESA AS TO WHETHER CONTRACT GN-01 SHOULD INCLUDE THE BUILDING WAGE RATE SCHEDULE OR THE HIGHWAY RATE SCHEDULE On April 11, 1975, MARTA solicited bids for construction of the Brown's Mill Road Bus Facilities. The bid specifications included a highway wage rate schedule published in the Federal Register./FN3/ On the date of bid opening the Assistant Administrator advised MARTA by telegram that the building construction wage rates schedule for the Atlanta area are the proper rates for the contract. On the same day and without responding to the telegram, MARTA opened the bids. Blount Construction Company was the apparent low bidder. On May 22, 1975, the North Georgia Building Construction Trades Council filed its action in United States District Court seeking to enjoin the award of the contract with the highway wages in it. In its decision and order granting the injunction, the District Court deferred to the Department of Labor. /FN4/ The Court enjoined the award of GN-01 pending a final ruling on the applicable wage scale by the Wage Appeals Board unless such contract contains a clause providing that the wage scales in it are subject to adjustment on order of the Secretary of Labor or the Wage Appeals Board. ???????????????????????????????? /FN3/ 39 F.R. 34984, September 2,, 1974. /FN4/ North Georgia Building Construction Trades Council v. U. S. Department of Transportation, et al., 399 F. Supp. 58 (N.D. Ga. 1975). [12] ~13 [13] THE APPLICABLE DAVIS-BACON ACT PROVISIONS The construction of the Brown's Mill Road Bus Facility will be financed, in part, by a grant under the Urban Mass Transportation Act of 1964 (49 U.S.C. [sec] 1601, et seq.). Accordingly, it is subject to the Labor Standards Section of that Act, 49 U.S.C. [sec] 1609, as follows: (a) The Secretary [of Transportation] shall take such action as may be necessary to insure that all laborers and mechanics employed by contractors or subcontractors in the performance of construction work financed with the assistance of loans or grants under section 1602 of this title shall be paid wages at rates not less than those prevailing on similar construction in the locality as determined by the Secretary of Labor in accordance with the Davis-Bacon Act, as amended. The Secretary shall not approve any such loan or grant without first obtaining adequate assurance that required labor standards will be maintained upon the construction work. (b) The Secretary of Labor shall have, with respect to the labor standards specified in subsection (a) of this section, the authority and functions set forth in Reorganization Plan Numbered 14 of 1950 (15 F.R. 3176; 64 Stat. 1267), and section 276c of Title 40. MARTA'S BASIC CONTENTIONS THAT APPROPRIATE WAGE CLASSIFICATIONS AND WAGE RATES FOR THE WORK IN QUESTION ARE THE SAME AS THE WAGE RATES AND CLASSIFICATIONS THAT ARE USED FOR HIGHWAY CONSTRUCTION MARTA contends that the construction work required for Contract GN-01 is more nearly similar to highway work than building work. MARTA relies upon the conclusion of UMTA that (a) the work involved is properly classified as highway work and (b) the "prevailing practice" for building projects in the metropolitan Atlanta area similar to the Brown's Mill Road Bus Facility is to award the site preparation and paving [13] ~14 [14] work as separate contracts to be performed at lower rates than those commonly paid for on the "actual" building construction. In support, MARTA points to its own recent construction project in which it did this without enforcement proceedings against it. MARTA further contends that ESA's determination that Contract GN-01 must use the building construction wage schedule because: a. The decision was based on the Brown's Mill project as a whole, rather than on the nature of the work involved in Contract GN-01 only; b. The work in Contract GN-01 is "indisputably more similar" to highway work than building work; c. ESA ignored its prior administrative practice and prior Board decisions permitting a separate rate schedule for site work for a building construction project when consistent with area practice; d. ESA ignored an alleged "predominant" local practice for large building construction projects of a character similar to the Brown's Mill project to award separate contracts at less than the building rates for clearing, grading, paving and other site preparation work; e. ESA erred in failing to give appropriate weight to MARTA's decision to use the highway rates. THE ISSUES TO BE CONSIDERED BY THE BOARD The Board must consider three questions in order to dispose of this case. ~15 1. Whether the building or the highway wage rate schedule is the most appropriate under the Davis-Bacon Act requirements for the work performed under Contract GN-01. 2. Did MARTA meet Davis-Bacon Act requirements when it awarded Contract GN-01 to Blount on the contingency that the wage scales included therein are subject to adjustment if MARTA is unable to reverse ESA's decision. 3. If there has been a violation of Davis-Bacon Act requirements in question 1 or 2, or both, what is the appropriate remedial action required under the circumstances. THE APPROPRIATE WAGE SCHEDULE MARTA does not contend that the Contract GN-01 is work on a highway project. MARTA urges, however, that (1) the Blount contract calls for large amounts of paving, preparation of site for paving and other site preparation and improvements which is the kind of work usually performed upon highways. If GN-01 is considered a separate undertaking the site preparation work as described in Exhibit No. 1, SITE-SPECIAL CONDITIONS is indisputably more similar to highway work than building work. MARTA also contends that since the principal purpose of the Brown's Mill Road project is to decrease operating expenses and to increase efficiency of its bus services by providing overnight parking Contract GN-01 does not require building construction wage rates even if other parts of the project require such rates. In support of this contention, MARTA argues that the site preparation work, for buildings executed in close development sequence with the buildings, has [15] ~16 [16] always been considered by ESA as building construction. The Board has carefully examined the entire record and all documents submitted including prehearing and post-hearing statements and matters considered at the oral hearing of December 16, 1975. The Board does not agree that any of the conclusions advanced by the petitioner are substantiated under Davis-Bacon Act practice or principle. The Board does not agree that decisions cited by MARTA support the contention that the work specified in Contract GN-01 is the kind which when separately awarded, can be undertaken at wage rates lower than those specified for the nine other building construction contracts on the site. The Board does not accept MARTA's contention that site preparation work for buildings in the Atlanta area is "predominantly" performed at highway construction wage rates. MARTA's reliance upon a conclusionary statement by UMTA's regional representative and on a few other conclusionary letters is misplaced. Under long established Davis-Bacon Act practice, a project can not be broken down into "packages of work." This smacks strongly of little more than an effort to break a project down into items of work for which the claim can be made that the "nature" of each item is indisputably more similar to a project of some other nature. The nature of the Brown's Mill Bus Facility and Contract GN-01 must be examined together. The situation in this case is in no way comparable to the separate contracts awarded by MARTA in Contracts 330 and 540 [16] ~17 [17] for entire segments of the new subway and rapid rail construction. A bus facility with two large garages cannot be broken into layers each a separate project. Similarly, each of the other 8 construction contracts awarded prior to December 16, 1975 are not separate projects. The decisions of this Board dealing with local paving contracts, or with contracts akin to local public utility contracts in a new political subdivision are not decisions under which MARTA's claims can be subsumed. The Board does not view the construction of the two buildings in the project with the insignificance that MARTA would attach to them. An examination of the "Site-Special Conditions" requires the conclusion that Contract GN-01, as one of the nine packages into which the Brown's Mill project has been separated, cannot be considered separately from the total project development for wage comparability purposes. Even if it were to be so considered, the work required by Contract GN-01 includes work which is considered building construction when done on any self-contained project which includes the erection of buildings. Although MARTA would contend that such work is an incidental part of Contract GN-01 as a contract for general site preparation, it embraces part of the construction of a large maintenance garage and an operating garage combined with an off-schedule employees' parking lot. MARTA cites the Board's decision In the Matter of Bell Helicopter, WAB Case No. 66-04 (December 28, 1966), as precedent for severing a project into separate contracts for wage determination purposes. However, [17] ~18 [18] in Bell Helicopter, the parties stipulated that all that was under consideration was a specific local paving contract. If MARTA had wished to write a contract limited to such a local area practice, it could have done so. It did not attempt to do so in this case. /FN5/ Other decisions of the Board which MARTA referred in support of its decisions to go ahead despite a clear determination of the Labor Department not to use them are not helpful. Airport construction and similar construction encompassing many square miles within the contract lines and meeting different scheduling requirements do not establish the general protective umbrella MARTA claims for its decision to split the Brown's Mill project site into at least nine packages of related work, each package dependent upon the other. Nor are situations involved in laying out new political subdivisions by local utility contractors or similar utility work in public streets apropos. The Board has considered whether the construction industry in a locality has recognized a carving out of such local paving work or [18] ?????????????????????????????? /FN5/ In its supplemental brief, MARTA places considerable reliance on its own construction at three Park & Ride facilities and at its Brady Avenue Bus Parking Facility. The Board understands that there are neither operating nor heavy maintenance garages at the Park & Ride facilities and that there is no heavy maintenance garage at the Brady Avenue facility. It seems improbable that the Park & Ride construction involved building construction in the way that Contract GN-01 does. While the Brady Avenue project is not before the Board, questions have been raised in respect to it sufficient to persuade the Board that it cannot, without more facts, accept MARTA's handling of this project as evidence or an appropriate application of the Davis-Bacon Act in the Atlanta area. [18] ~19 [19] local utility work. But neither the Labor Department nor this Board has extended such limited exceptions to what MARTA calls site preparation work for buildings when the work is sequentially a closely coordinated part of the building construction. We see no justification under the circumstances to make a change in basic past interpretation. Even the rates MARTA selected, the highway rate schedule which was at hand, has not been shown to be the rates in fact paid when certain work in connection with building construction has been done at less than building rates. Under Davis-Bacon Act principles, site preparation work in Contract GN-01 is simply not of the nature of a highway project. If this were so, than all such work including the building construction rates when used and paid for all building site preparation work would be included by ESA in the determination of highway wage rates. The Board in this case will not go into the background and the history of the federal aid highway program under which highway rates are determined in cooperation with state highway departments. But avoidance of this background and history, which parties before this Board seek to obliterate, has resulted in a highly erroneous and mischievous situation in which, in this case, MARTA has deliberately decided to place itself. The Board concludes that the nine contracts, including GN-01, already awarded for the construction of the Brown's Mill Road project, contemplates a total development to be [19] ~20 [20] simultaneously undertaken. Close and overall coordination and cooperation between the nine construction contractors, including Blount, in the execution of the work, is required. /FN6/ The Board further concludes that, since the work specified in Contract GN-01 is not highway work and not work of a nature similar to highway work under long-established and basic Davis-Bacon Act principles, highway rates should not have been selected as the appropriate rates for the work in question. THE AWARD OF THE BLOUNT CONTRACT SUBSEQUENT TO THE COURT DECISIONS IN NORTH GEORGIA BUILDING AND CONSTRUCTION TRADES COUNCIL V. U.S. DEPARTMENT OF TRANSPORTATION, USDC, NORTHERN DISTRICT OF GEORGIA, ATLANTA DIVISION, CIVIL ACTION NO. C75-955A Apprehensive that MARTA would proceed with an award of the work on the basis of highway construction rates despite ESA's decision of May 15, 1975, North Georgia sought injunctive relief. A local United States Attorney first "aligned the executive branch with the defend[a]nts" as the court said. The court wisely ordered the Department of Labor joined as a party. Two Assistant United States Attorneys filed briefs. One presented the views of the Department of Transportation; the other, the Department of Labor's. The court noted: Finally, by letter dated June 10, 1975, the court was informed that this intra-executive squabble had been resolved and the entire executive branch should now be regarded as supporting the plaintiff's position. The [20] ???????????????????????????????????? /FN6/ There is no evidence in this case that J. A. Jones, the contract coordinator, is responsible for MARTA's policy decision to proceed to award contract GN-01 at highway wage rates. [20] ~21 [21] letter also requested permission to withdraw the brief filed on behalf of DOT. This development both clarifies and muddies the waters of this case. On the one hand it brings the federal defendants into a harmonious posture, albeit on the side of the plaintiff. On the other hand it casts some doubt on the wisdom of the remaining defendants' tactical decision to heavily rely on DOT having positioned itself as their ally. As for UMTA, the governmental agency subject to and operating under Reorganization Plan 14, it should have known better than to have sanctioned or condoned MARTA's action after the Court's order in this matter. All it had to do, was to do what the Labor Department told it to do. The court recognized that questions of Davis-Bacon Act policy and administration were novel to the court. While it listened to MARTA's "suggestions" on basic law it did not accept such "suggestions" as established policy, administration or law. More must be said concerning the order of the court in connection with the appropriate relief required as the result of this proceeding. The court took jurisdiction under Title 28, Section 1361 U.S.C. insofar as plaintiffs sought to compel a federal agency to perform its duty. The court concluded that plaintiffs had standing to bring this suit under section 702, Title 5 U.S.C., citing International Union of Operating Engineers v. Arthurs, 355 F. Supp. 7, 14 (W.D. O[kl]a.) aff'd 280 F.2d 603 (1Oth Cir. 1973). The court noted however: The Court'[s] role in this controversy, however, is not to decide the entire controversy but rather is limited to entering an order which will '(1) compel [21] ~22 [22] agency action unlawfully withheld or unreasonably delayed; and (2) hold unlawful and set aside agency action, findings, and conclusions found to be -- (A) arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law; [or] -- (D) without observance of procedure required by law.' 5 U.S.C. [sec] 706. The role of this court does not include a determination de novo of the appropriate wage scale to be applied to this contract. That determination is committed to the agency proceedings provided by the statute and regulations and this court will therefore express no opinion whatsoever on that aspect of this controversy. What this court can undertake to do is to compel agency compliance with lawful procedures. The agency referred to was DOT for not doing what the Labor Department said, not to the Department of Labor. Inasmuch as the Department of Labor came into this action to ensure that MARTA and DOT did what ESA said they were required to do under the Davis-Bacon Act, this Board has no quarrel with the District Court's position. This is because the court made clear that it believed judicial intervention was necessary to assure, under the peculiar circumstances of this case, that DOT and MARTA, not the Labor Department, observed the Labor Department's directions. The Board seriously questions, however, whether a court can order the Department of Labor to do this or that with respect to any practice or procedure in making a wage predetermination. The Board believes it is established law that a court cannot. There are other ways than judicial intervention for the departments and agencies of the federal establishment to resolve their problems. The decisions of the Secretary of Labor under Reorganization Plan 14 are preeminent within [22] ~23 [23] the federal administration. They are not subject, in the view of the Board, to further judicial review. Only in the last dozen years has an appellate review procedure under Regs. Part [] 7 of the U. S. Department of Labor, been provided through this Board. This procedure is an appellate procedure to be taken only from a final decision of the Assistant Administrator of the Wage & Hour Administration. The decision of ESA is a final decision which must be observed unless stayed administratively. As the court noted it cannot determine the minimum wage schedules at which the work shall be performed. The Board believes that the courts will not be taken in by tactics alleging procedural improprieties in the discharging of Davis-Bacon Act responsibilities. Such tactical delays can be the equivalent of victory in efforts to frustrate needed public works and other development programs. With respect to the court's view of North Georgia's request for an injunction and the qualifications the court placed upon granting one, it is important that the order of the court be set out in this decision. The plaintiff has also requested that this court enjoin execution of the contract on the basis of the bids opened on May 5, 1975 and require that it be readvertised. The court declines to go so far. The plaintiff was found to have standing in order to protect the rights conferred by the Davis-Bacon Act on laborers in general and plaintiff's members in particular. Its only interest is to insure that the appropriate wages under the Act are paid to all laborers hired under the contract. Accordingly, the court ENJOINS the defendants from executing any contract for the Brown's Mill project until such time as a final ruling has been made on the appropriate [23] ~24 [24] applicable wage scale to be included therein unless such contract contains a clause providing that the wage scales in it are subject to adjustment on order of the Secretary of Labor or of the Wage Appeals Board. That injunction having been entered, there remains the question what action should be taken on the Brown's Mill project. Three possibilities suggest themselves (1) All action on the project can be deferred until there is a final ruling on the appropriate wage scale. (2) The contract can be executed as bid with a clause providing for a later retroactive adjustment of the wage scale if necessary. (3) The contract can be withdrawn and resolicited with an adjustment provision. [*] Which of these possibilities is legally appropriate has not vet been adequately briefed by the parties and the court is not entirely convinced it is even appropriately before this court. Hence the court expresses no opinion on this issue at this time and will leave its determination to the defendants. [*] [*] (Underlining supplied.) [*] It is the opinion of this Board that MARTA was without color of any claim to "suggest" to the court that the disputed contract could be executed on the basis of the highway wage scales with a clause providing for a later adjustment in minimum wage. /FN7/ The Board concludes that such a suggestion to the court flies in the face of the cardinal principle of the Davis-Bacon Act, "that the advertised specifications for every contract . . . and which requires or involves the employment of mechanics and/or laborers shall contain a provision [*] stating the minimum wages to be paid various classes of laborers and mechanics which shall be based upon the wage that will be determined by the Secretary of Labor [*] to be [24] ?????????????????????????????? /FN7/ The court said, "Defendant MARTA has suggested that this is possible under the contract as bid." [24] ~25 [25] prevailing for the corresponding classes of laborers and mechanics employed on projects of a character similar to the contract work . . ." [*] (Underlining supplied.) [*] The Act further provides that every Davis-Bacon contract [*] shall contain a stipulation [*] that the contractor and his subcontractor shall pay the full amounts accrued at the time of payment computed at wage rates not less than those [*] stated in the advertised specifications [*] regardless of any contractual relationship which may be alleged to exist between the contractor or subcontractor and such laborers and mechanics. [Emphases in original] The Act further goes on to provide that the scale of wages to be paid shall be posted by the contractor in a prominent and easily accessible place at the site of the work. These three requirements are written in the statute. It is not a matter of interpretation of gloss. The appropriate wage schedule must be [*] stated [*] in the contract bid documents upon which the award is made. This is the schedule which must be [*] posted [*]. [Emphases in original] When the Department of Labor directed the use of building rates for Contract GN-01, it was DOT's obligation under Reorganization Plan 14 to accept that determination and to pass it on to MARTA through control over financial assistance. The remedy in this case will have to speak to that matter. If DOT wished to use other administrative procedures than this Board, it could have entered into policy or other discussions with the Department of Labor. The one thing that UMTA could not do was to let MARTA thumb its nose at [25] ~26 [26] the Department of Labor while violating the plain language of the Act. THE APPROPRIATE REMEDY MARTA has failed to sustain its position in respect to the use of the highway schedules. The Board sustains the May 15 and August 4, 1975 decisions of ESA that the correct schedules under the circumstances are the building rate schedules. The ESA decision (and in fact the later decision of the District Court) put MARTA on notice that it would proceed only at its peril. Such advice simply cannot be flou[]ted under the circumstances of this case. In view of MARTA's course of conduct, the Board must view this case not only as an enforcement matter but one requiring special remedies in the circumstances. These remedies need to be three-pronged: 1. Before MARTA receives any further federal assistance each laborer or mechanic employed by Blount, as contemplated by CFR 29, Part 5.5(a)(1) must receive a wage rate effective as of the date of original hire at Brown's Mill Road that is not less than the rate for his classification as defined by the ESA wire of May 15, 1975. 2. Action should be taken by ESA pursuant to 29 CFR Part 5.6(2)(c) and examination made of possible debarment of MARTA from further Federal assistance. [26] ~27 [27] 3. Action should be taken to ensure that DOT employees, if any, that may have aided and abetted MARTA in its Contract GN-01 course of action are shown the error of their ways to prevent a recurrence of inexcusable conduct. With respect to these three remedial items, Item 1 above should present no problem as MARTA assured the Board that it has some contractual arrangement with Blount to accomplish this. It should be done with ESA assistance and subject to its approval. With respect to Item 2 above, if it is not feasible to debar MARTA from further financial assistance, it may be not unfeasible to remove from MARTA those staff employees who are responsible for flaunting the ESA decisions by proceeding with the award of Contract GN-01 at the improper rates. In lieu of blacklisting MARTA, the ESA should sit down with MARTA and obtain such assurances as will satisfy it that henceforth those employees responsible for the policy decisions to proceed with the GN-01 award will not participate in Davis-Bacon Act matters. MARTA should make a recommendation to ESA [as] to the steps it will take to avoid this situation in the future to avoid being considered for the ineligible list. MARTA must give to ESA true assurances that its staff employees who do participate in contract award and administration are conversant with the requirements of the Davis-Bacon Act and that MARTA will abide by the ESA requirements. [27] ~28 [28] In respect to Item 3 above, the Department of Labor should sit down with the Department of Transportation and request DOT to undertake a training and educational program. Any employee that aided, abetted or condoned MARTA's conduct should be considerately dealt with. DOT should make a recommendation to the Labor Department as to what it wants to do with respect to such employees. The matter must be straightened out to the satisfaction of the Labor Department as a matter within the federal establishment. It is not feasible to declare another government agency ineligible to use federal financial assistance because of its disregard of required labor protection standards. [28] ~29 [29] Barker: Concurring. I am in agreement with the majority decision and the three points of the Board's order in all respects. I add this concurring opinion for the purposes of pointing out that in those cases in which there is an established local practice for certain types of specialty work to be performed by identified segments of the construction industry in the locality such as the existence of contractors who specialize in local paving and similar work, or local street and utility work, it would be possible for a contracting agency to segregate project work into categories of work which would utilize this distinction. If such local practices exist in Atlanta, Marta could have awarded parts of the Blount award on such a separate basis. But, the work involved in site preparation for this kind of a project cannot be characterized as a local paving contract or a local public utility contract, nor is Blount such a local and specialized construction contractor. It is far too late, after Marta went ahead as it did here to lump building construction work in with work which possibly might have been separated, for the claim to be made that the building work was just an incidental part of the other work. That is not the test in determining projects of a character similar to the questioned work being tested, nor is the building work required for site preparation for buildings in this case "insignificant", nor it did not take place as an "incidental" matter. [29] ~30 [30] ROTHMAN: Concurring in part and dissenting in part: I am in agreement with the Board majority decision except Item 1 of the order; what to do with the extra money MARTA arranged to pay Blount under an arrangement never fully disclosed to the Board. This is a case of extraordinary circumstances and warrants consideration of extraordinary relief. The Board having the matter before it must look at the total situation because, although the award has been made and the work far along to completion, it is a situation that could occur again without presentation and concomitant proper remedy. I see no obligation or at best no purpose here under the Davis-Bacon Act for MARTA to pay extra compensation to Blount under the extraordinary factual situation. I see no obligation by Blount to pay to its employees more than the wage rates required to be "stated" in the bid documents under these extraordinary facts. The serious violation of the Act stems from MARTA's deliberate insertion of the wrong schedule in the agreement, not in what Blount did. The question is how should MARTA be held to a responsible standard of accountability. Blount has paid its employees not less than the wage rates "stated" in the contract it executed with MARTA as the contracting agency as well as its own general contractor. [30] ~31 [31] Blount is not required to do more. MARTA put itself in the shoes of the Department of Labor and called the shot that the Labor Department should have called and did. In this case it should not have run to the benefit of individual employees. The supplemental arrangement that MARTA would pay Blount an amount above the minimum wage rates as "stated" in the bid documents if MARTA could not overthrow the Labor Department before this Board is not a legal Davis Bacon Act arrangement. The United States District Court did not authorize it as a decision of the Court in the injunction proceeding. Therefore, I would not honor the arrangement (even if there has been a clear one). MARTA had been cautioned when before this Board in other proceedings that it could not and should not manipulate wage rates to its own satisfaction in bid documents. But for MARTA to stay off the ineligible list, it should make amends in some other way. I do not emphasize in this dissent the correctness of ESA's decision. I emphasize the fact that MARTA used a schedule of rates ESA directed it should not use. MARTA cannot be excused for making a mistake of law, because it made none. It proceeded contrary to the direction and advices given to it by the authoritative agency, ESA in the Labor Department. [31] ~32 [32] To pay an additional sum of money to Blount would only compound the miscarriage of basic law and the injustice which took place when MARTA expediently deprived a class of contractors who would be reasonably expected to employ mechanics and laborers affiliated with the North Georgia Building and Construction Trades Council from bidding for Contract GN-01 work. It selected a contractor by a prohibited process. It then dealt with that contractor on a preferential basis. This redounded to the detriment of laborers and mechanics the Act was designed to protect. The details of the alleged arrangement to increase Blount's contract price, how it would be administered, the kind of notices that were posted pursuant to the requirement of the Act have not been explained. MARTA's use of the wage rates the Labor Department said were wrong even after it asked review of ESA's decision does relieve MARTA of the requirement that ESA determination must be attached and reversed before, not after the wrong rates are used. The Board would be justified in dismissing the petition as untimely and let the ESA decision stand for that reason alone. But this case has gone too far to be disposed of on the basis that the MARTA petition, realistically viewed, was untimely. ESA is now required to consider an enforcement position. [32] ~33 [33] It is also worth a passing glance that the work of Contract GN-01 is not part of a highway project. There has been no acceptable showing by MARTA that the wages MARTA specified for the work, even under MARTA's erroneous theory, were in fact the prevailing wage rates paid for site improvement work on this kind of project. The actual prevailing wage rates for such work when independent of building construction or when part of building construction may have been less more than highway construction. Since Davis-Bacon Act rates (when correctly used) are minimum rates only Blount may have paid over those rates to some employees and so bid the job along with correlative items, such as overhead, etc., based upon its estimates. The vice of MARTA's decision to go ahead is that it gave one class of contractors and the employees they would select an advantage over another class. Subsequent efforts to rectify the situation only points up the illegality. There is really nothing that can come later as a remedy that can fully repair the harm that has been done (a) in the administration of the Act by ESA and ([b]) to the laborers and mechanics who had a reasonable expectation to work on this project. If this were a case involving a small contractor, the likelihood is that the contractor would find himself on the ineligible list for three years. In order to avoid placing MARTA, which acted as its own contractor, on the [33] ~34 [34] ineligible list for further federal participation in Davis-Bacon Act programs, I would recommend the following procedures to the U.S. Department of Labor. 1. The Department of Labor, in addition to the relief required by the majority except for Item 1, (the payment of back wages) should under Reorganization Plan 14, and together with North Georgia, MARTA and UMTA determine upon a plan to provide that a sum of money equivalent to the amount that would be paid to Blount be paid into North Georgia jointly trusteed welfare, pension or other trust funds for the crafts employed by Blount on this job. 2. If on the advice of ESA counsel there are legal impediments to paying the moneys into such jointly trusteed trust funds for the affected crafts, an arrangement should be considered to pay the money to one or more charities designated by the North Georgia Building and Construction Trades Council. 3. If neither of the foregoing arrangements can be worked out, then and only then the fund should be distributed to Blount employees. As I see it under the circumstances as a voluntary arrangement by MARTA and not a statutory requirement. I believe my colleagues, which make up the majority on this point would find that employees of Blount must be [34] ~35 [35] paid these moneys in the first instance. If that is so, I am suggesting that MARTA be required to do so, but also make a payment to North Georgia. 4. ESA should place MARTA on the ineligible list for not more than 3 years unless MARTA voluntarily agrees that no further work will be awarded by MARTA on any project using Davis Bacon wage predeterminations until ESA has indicated in writing that it is satisfied with the solutions worked out for this case and that this situation will not occur again. SO ORDERED: (s) Oscar S. Smith, Chairman (s) Stuart Rothman, Member (s) Clarence D. Barker, Member



Phone Numbers