skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

Gananda Development Corp., WAB Nos. 73-13 and 74-01 (WAB Jan. 18, 1974)


CCASE: GANANDA DEVELOPMENT CORPORATION DDATE: 19740514 TTEXT: ~1 [1] UNITED STATES OF AMERICA UNITED STATES DEPARTMENT OF LABOR WAGE APPEALS BOARD WASHINGTON, D. C. IN THE MATTER OF Prevailing Wage Rates Applicable to the WAGE APPEALS BOARD Construction of Sewage Treatment Plants, Water Facilities, Highways, Heavy Case Nos. 73-13 Construction and Utilities, Wayne County, New York; Federal Agency Involved, and 74-01 Department of Housing and Urban Development; Wage Determination in Issue Dated: January 18, 1974 73 N.Y. 272 of August 23, 1973. Gananda Development Corporation Petitioner (WAB Case No. 74-13) Allied Building Trades Council, Rochester, New York Petitioner (WAB Case No. 74-01) APPEARANCES: John Titus, Esquire Johnson, Reif and Mullan, P.C. Rochester, New York for Gananda Development Corporation Bernard T. King, Esquire Blitman and King Attorneys for Allied Building Trades Council, Rochester, New York [1] ~2 [2] Thomas X. Dunn, Esquire Associate General Counsel for the Building & Construction Trades Department, AFL-CIO and for the International Brotherhood of Electrical Workers, Washington, D. C. George E. Rivers, Esquire Counsel for Construction Wage Standards Office of the Solicitor and Counsel for the Assistant Administrator, W&H United States Department of Labor BEFORE: Oscar S. Smith, Chairman, Wage Appeals Board; and Stuart Rothman, and Clarence D. Barker, Members DECISION AND ORDER This matter is before the Wage Appeals Board on a petition by Gananda Development Corporation, WAB Case No. 73-13 and a cross petition by Allied Building Trades Council, Rochester, New York, WAB Case No. 74-01, which have been consolidated. This case may be cited as Gananda Development Corporation, Wayne County, New York, WAB 73-13 and 74-01. Petitioner Gananda seeks the cancellation of Employment Standards Administration (ESA) Wage Schedule No. 73-NY-272 (dated August 23, 1973) on the ground that the determination [2] ~3 [3] was faulty in that it was predicated upon a special Department of Labor (ESA) survey that did not take into account a sufficient range of representative projects spread over an appropriate time span. The cross-petitioner Allied Building Trades Council, Rochester, New York, supports the scope of the projects and time span utilized in the ESA survey, but contends ESA only took into account payroll evidence. In doing so it neglected to include certain escrowed wage payments pending reconsideration by the Construction Industry Stabilization Committee of a part of a negotiated wage increase under then existing wage stabilization law. These wage payments were ultimately restored to the employees. The Allied Building Trades Council also raised questions concerning the accuracy of some individual craft rates. While this briefly is the object of the petition and the cross-petition, the events leading to their filing are more complex and will be discussed herein. Gananda Development Corporation is engaged under the Urban Growth and New Community Development Act of 1970 /FN1/ in [3] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ See P.L. 91-609, 42 U.S.C.A. 4529. [3] ~4 [4] the construction of a new planned community ("Gananda Project") in Wayne County, New York, consisting of sewage treatment plants, water facilities, highways, heavy construction and utilities including a community center. Wayne County, a heretofore relatively rural area, is adjacent to the City of Rochester, New York. This planned community development is a large one, consisting of several thousand acres. Up to this time Gananda has utilized two contractors, Empire Pipeline Corporation of Liverpool, New York and Eddy Development Corporation of Pittsford, New York. /FN2/ To meet Davis-Bacon Act requirements for these two contracts, Gananda adopted a set of wage rates from a project in Onandaga County near Syracuse called the "Lysander Project." When, how, why, and with whose permission or authority, Gananda adopted these Lysander rates and whether it was justified in doing so, is what this case is about. /FN3/ [4] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN2/ The Eddy Development Corporation apparently suspended operations approximately 2 months after starting work. /FN3/ This appeal involves a request to review a wage determination issued pursuant to the Urban Growth and New Community Development Act of 1970, the prevailing wage provisions of which require such determination to be made by [4][FN3 CONTINUED ON PAGE 5][5] the Secretary of Labor in accordance with the Davis-Bacon Act. The pertinent provisions of these statutes read as follows: Sec. 727(f). Labor Standards All laborers and mechanics employed by contractors or subcontractors in land development assisted under this part shall be paid wages at rates not less than those prevailing on similar construction in the locality as determined by Secretary of Labor in accordance with the Davis-Bacon Act, as amended (40 U.S.C. 276a-5). No assistance shall be extended under this part for any land development without first obtaining adequate assurance that these labor standards will be maintained upon the construction work involved in such program. The Secretary of Labor shall have, with respect to the labor standards specified in this section, the authority and functions set forth in Reorganization Plan Numbered 14 of 1950 (64 Stat. 1267), and section 2 of the Act of June 13, 1934 (40 U.S.C. 276c). (42 U.S.C.A. 4529). The wage determination provisions of the Davis-Bacon Act provide for [5][FN3 CONTINUED ON PAGE 6][6] . . .minimum wages to be paid various classes of laborers and mechanics which shall be based upon the wages that will be determined by the Secretary of Labor to be prevailing for the corresponding classes of laborers and mechanics employed on projects of a character similar to the contract work in the city, town, village or other civil subdivision of the State in which the work is performed. . . . (Section 1 of the Davis-Bacon Act. 40 U.S.C. 276a). The pertinent provisions of the Department's Regulations (See 29 CFR, Part 1 and Part 7) as they related to this matter read as follow: Sec. 1.2 Definitions (b) The term "area" in determining wage rates under the Davis-Bacon Act and the prevailing wage provisions of the other statutes listed in Appendix A shall mean the city, town, village, or other civil subdivision of the State in which the work is to be performed. . . . * * *[6] [FN3 CONTINUED ON PAGE 7][7] Sec. 1.8 Scope of consideration (a) In making a wage rate determination, projects completed more than one year prior to the date of request for the determination may, [*] but [*] need not be considered. [*](Emphasis added.)[*] (b) If there has been no similar construction within the area in the past year, wage rates paid on the nearest similar construction may be considered. Sec. 1.16 Review by Wage Appeals Board Any interested person may appeal to the Wage Appeals Board for a review of a determination of wage rates made under this part, or any findings and conclusions made on the record of any hearings held under [sec] 1.3(c). Any such appeal may, in the discretion of the Wage Appeals Board be received, accepted, and decided in accordance with the provisions of 29 CFR Part 7 and such other procedures as the Board may establish. [END FN3] [7] ~5 [5] The Board was advised at the oral hearing that Empire Pipeline commenced construction by September 1, 1973, Gananda's prehearing statement fixes the date as August 27th, Eddy Development Corporation, commenced construction on or about September 1st. [5] ~6 [6] The immediate responsibility for the administration and enforcement of Federal labor protective standards for this project is under the jurisdiction of the Department of Housing [6] ~7 [7] and Urban Development through its Buffalo, New York Area Office. As far back as February 1973 Petitioner Gananda asked HUD for a prevailing wage determination for the Gananda development recognizing that the project was in a non-urban county and was "highway and heavy" non-residential work. In turn, but not until May 24, 1973, HUD requested the Department of Labor to conduct a survey and to issue a predetermination for this project. The Employment Standards Administration issued its decision 73-NY-272, dated August 23, 1973. This document, [7] ~8 [8] according to an exhibit attached to Gananda's prehearing statement, came into the hands of the director of the Buffalo Area Office of HUD by August 27, 1973. This was the piece of paper Gananda had requested in February 1973. What did the Buffalo area director do with it when he received it? Accepting his August 27, 1973 letter on its face, he sent it to the Assistant Secretary of Labor Relations of HUD in Washington. It was not received by Gananda until September 10th. Although all parties knew that this wage predetermination, 73-NY-272, not some other, was a prerequisite to going ahead with construction work under the Urban Growth and New Community Development Act of 1970, /FN4/ Gananda went ahead before it was received. In June 1973, Gananda had invited bids on certain of the work and on August 7, 1973, "initial bids were let," i.e., accepted. In the absence of the requested schedule, Petitioner [8] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN4/ The Urban Growth and New Community Development Act of 1970 does not contain an exception found in certain other housing acts that permits a developer to proceed notwithstanding failure to incorporate in the bid documents the appropriate wage predeterminations as issued by the ESA for the project. See for example the National Housing Act, Section 212(a) and 29 CFR 1.7. The record contains no explanation of why the August 23rd wage determination did not reach Petitioner Gananda until September 10th since the HUD Buffalo Area Office, [8][FN4 CONTINUED ON PAGE 9] based on general experience with the Davis-Bacon Act, would know that the appropriate wage schedule of August 23, 1973, must be applied to the project from the commencement of construction and could not be modified thereafter. It is clear that this schedule was in the hands of the Buffalo Area Office on August 27th the date upon which Gananda's petition states that construction was commenced. [END FN4] [9] ~9 [9] Gananda states that it secured a wage scale from "other projects similar to this project and in particular a project known as the "Lysander Project" near Syracuse, New York, also in a rural county of upstate New York. This project is a new community project under the auspices of the Department of Housing and Urban Development." Petitioner was vague as to what other Davis-Bacon wage schedules it examined before selecting Lysander, although administrative notice is taken that there were Davis-Bacon schedules previously issued for Wayne County. According to Petitioner's explanation which the Board accepts, an understanding then developed after September 10, 1973 between the appropriate office of HUD and Petitioner Gananda that it would be permissible for Gananda to continue to use the set of wage rates it had adopted when soliciting bids and to substitute these for the Wayne County determination expressly made by the Secretary of Labor by reason of [9] ~10 [10] Petitioner's request. Gananda agreed with HUD, we are told, that it would challenge the determination of the Department of Labor and if the challenge should go for naught, it would pay the prevailing rate of wages as determined by the Secretary of Labor to the employees affected. Petitioner Gananda said that it had "escrowed" the funds, but no accounts were set up for individual employees and the necessary funds have not been duly sequestered. In the meantime mechanics and employees entitled to the protection of the Davis-Bacon and related Acts have not been paid as the Copeland Act requires. /FN5/ Although Petitioner states that no one told it to use the rates from an Onandago County project near Syracuse instead of the specific rates found by the Labor Department to prevail for a Wayne County project near Rochester, the Board concludes that Petitioner's gambit on its own could not have started or continued without the knowledge and consent of the appropriate office of HUD.[10] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN5/ 40 U.S.C. 276c. [10] ~11 [11] Petitioner Gananda initially requested this Board to review Wage Schedule No. 73-NY-272 on November 21, 1973. This Board referred the matter to the Employment Standards Administration for reconsideration. The ESA on February 11, 1974 denied Petitioner's reconsideration as untimely, i.e., after the "award and/or the beginning of construction". Gananda has argued that its petition is timely because it was made within a reasonable time after receipt of the predetermination. This argument could have merit only if bids had not been awarded and construction commenced in advance of the predetermination. Gananda also seeks by continuation of its petition, guidance as to the adequacy of ESA methods and procedures for arriving at wage determinations for future contracts on the Gananda project. But as Petitioner has also rejected out of hand the wage schedule ESA said must be paid on the two contracts awarded on August 7, 1973, the Board's more immediate and demanding concern is what to do about the blithe adoption of, and HUD's concurrence in, a bogus set of wage rates.[11] ~12 [12] The Department of Housing and Urban Development which could have enlightened the Board made no appearance and has offered no explanation of how the mismanagement in this case arose. For purposes of what it has to say in this decision, the Board will assume that the administering agency failed to act out of some kind of error or misunderstanding, notwithstanding the fact that any area office of HUD would be familiar with the operation of the Davis-Bacon Act and related acts under other housing acts. * * * Among other purposes, the Wage Appeals Board was established more than ten years ago to meet a need for an impartial review board as Secretary of Labor Wirtz said, to be "as independent as it can be made by the Secretary", to consider and grant relief where justified in a case of alleged misfunction of administration or error of interpretation under the Davis-Bacon Act. In this capacity, the Board on a case-by-case basis, has protected many parties -- labor organizations, individuals, sponsoring agencies and contractors, -- from misfunction or misinterpretation of the Act by administering agencies. [12] ~13 [13] The Board on a case-by-case basis has "adjudicated" respective claims of contracting agencies, employers, labor organizations and individuals and has sought through clarification and guiding principles to bring about an harmonious and coordinated administration of the Davis-Bacon Act and related Acts. Seldom have we had a case that has called more for some guiding statement of administration than the facts underlying this petition as we are told those facts to be. 29 CFR 1.7(a) and 1.7(b) provide: [Sec] 1.7 Use and effectiveness of wage determinations (a)(1) Project wage determinations initially issued shall be effective for 120 calendar days from the date of such determinations. If such a wage determination is not used in the period of its effectiveness it is void. If it appears that a wage determination may expire between bid opening and award, the agency should request a new wage determination sufficiently in advance of the bid opening to assure receipt prior thereto. However, when due to unavoidable circumstances a determination expires before award and after bid opening, the Administrator upon a written finding to that effect by the head of the Federal agency in individual cases may extend the expiration date of a determination whenever he finds it necessary and proper in the public interest to prevent injustice or undue hardship or to avoid serious impairment in the conduct of Government business. /FN6/ * * *[13] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN6/ 29 CFR 1.7(a). [13] ~14 [14] (b)(l) All actions modifying an original project wage determination prior to the award of the contract or contracts for which the determination was sought shall be applicable thereto, but modifications received by the Federal agency (in the case of the Federal-Aid Highway Acts as codified in 23 U.S.C. 113, the State Highway department of each State) later than 10 days before the opening of bids shall not be effective except when the Federal agency (in the case of the Federal-Aid Highway Acts as codified in 23 U.S.C. 113, the State highway department of each State) finds that there is a reasonable time in which to notify bidders of the modification. Similarly, in the case of contracts entered into pursuant to the National Housing Act, changes or modifications in the original determination shall be effective if made prior to the beginning of construction, but shall not apply after the mortgage is initially endorsed by the Federal agency. A modification in no case will continue in effect beyond the effective period of the wage determination to which it relates. /FN7/ We hold that Petitioner Gananda has presented no information of merit that would justify this Board in relieving it from compliance with Wage Determination 73-NY-272 effective at the commencement of work. To entertain this case on the contention that the Department of Labor's survey was in error, after work commenced and the contract firmly awarded would permit a construction contractor, sponsoring agency, and a [14] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN7/ 29 CFR 1.7(b). [14] ~15 [15] like-minded governmental regional underling, sua sponte, inter sese, and pendente lite to take it upon themselves to dismantle the administration of the Act whenever they are unhappy with a Department of Labor wage predetermination action. Under Regulations, 1.7(a) requests for modifications must be received and processed before work starts or award made in accordance with the terms of the regulation. Under the requirements of the Copeland Act, an employee is entitled to the amount of wages due him each week. There is nothing in the administration of the Davis-Bacon Act that warrants withholding of wages under circumstances such as present in this case. With thousands of Davis-Bacon wage predeterminations annually finding their way into bidding documents, the administration of the Act would be reduced to shambles if any regional administrator were to permit a contractor to pick and choose the rates he would apply subject to payment of the correct wages due to affected employees if at some subsequent time the Department of Labor were to catch up with the violation. The scheme of things, as the Copeland Act shows, is to the contrary. The wage predetermination schedule must be successfully challenged in a timely fashion, or it must be [15] ~16 [16] included in the bid and contract documents, and must be paid. The fundamental requirement of the Davis-Bacon Act, that the contract specifications will contain the wage predetermination of the Secretary of Labor does not permit the kind of end run attempted here. But for the participation of the regional office of HUD this would be the kind of case that would warrant consideration for recommended debarment. In view of this case the Board suggests that the respective governmental agencies directly responsible for the administration of the Davis-Bacon and related Acts re-examine their responsibilities. The Board suggests to the Department of Labor to take another look at Reorganization Plan 14 of 1950 out of precaution to avoid a recurrence of this kind of situation. Petitioner Gananda was concerned not only with the application of Wage Determination 73-NY-272 to the work in progress, but the manner and means in which the Labor Department will survey wage rates for future contracts on the Gananda project. This decision is without prejudice to Petitioner's right to seek review of a future Labor Department [16] ~17 [17] wage predetermination when timely brought. It is also without prejudice to the rights of Allied Building Trades Council to seek review in a new wage predetermination of individual craft rates or other matters. The Board prefers to deal only with the proper application of Wage Determination 73-NY-272 in this case. The cross-petitioner, Allied Building Trades Council Rochester, New York, has asked the Board to direct the ESA to add to the wage determination 73-NY-272 a part of the negotiated wage rate that was not in the employees' paycheck at the time the survey was made because it was withheld in escrow pending reconsideration by the Construction Industry Stabilization Committee of the total amount of the negotiated increase. There are reasons in favor of this proposition. However, considering the overall mechanics of Davis-Bacon administration and the ephemeral nature of wage controls when viewed in perspective, the Wage Appeals Board will not disturb the practice of the ESA. Based upon limited information available in this case, the establishment of such a practice would appear to create more difficult problems in Davis-Bacon administration than it would solve. [17] ~18 [18] ORDER: The Petition of Gananda Development Corporation is denied. The Petition of Allied Building Trades Council, Rochester, New York, is denied. SO ORDERED: (s) Oscar S. Smith, Chairman (s) Stuart Rothman, Member (s) Clarence D. Barker, Member [18]



Phone Numbers