skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

STANFORD LINEAR ACCELERATOR CENTER, WAB No. 65-02 (WAB Apr. 12, 1965)


CCASE: STANFORD LINEAR ACCELERATOR CENTER V. SOL DDATE: 19650412 TTEXT: ~1 UNITED STATES OF AMERICA DEPARTMENT OF LABOR DECISIONS AND ORDERS OF THE WAGE APPEALS BOARD In the Matter of: THE DETERMINATION OF COVERAGE UNDER DAVIS-BACON ACT OF CERTAIN WAB Case WORK IN ASSEMBLING 40-FOOT MODULES No. 65-02 AT STANFORD LINEAR ACCELERATOR CENTER, PALO ALTO, CALIFORNIA DATED: April 12, 1965 Messrs. Hudson B. Ragan of U.S. Atomic Energy Commission, and Daryl Craig Dawson of Stanford University for petitioners. Mr. Paul A. Tenney, for Solicitor of Labor. Messrs. Thomas X. Dunn and William J. McSorley, for Building & Construction Trades Council, AFL-CIO. Messrs. Patrick C. O'Donoghue and Eugene W. Bradshaw, for United Association of Journeymen and Apprentices of the Plumbing and Pipefitting Industry. Messrs. Thomas X. Dunn and O. A. Rieman, for International Brotherhood of Electrical Workers. Before BARKER and ROTHMAN, Members. [1] ~2 DECISION STATEMENT OF CASE This is a proceeding under Order No. 32-63 of the Secretary of Labor, as amended, following a petition for review filed jointly on February 23, 1965, by Leland Stanford Junior University and the U.S. Atomic Energy Commission, hereinafter called the petitioners, pursuant to the Wage Appeals Board Rules of Procedure, Part 7, (29 CFR, Subtitle A). The petition requests review of an opinion dated January 13, 1064, by the Solicitor of Labor, U.S. Department of Labor, that certain work being performed by the University under contract No. AT(04-3)-400 for the Atomic Energy Commission, issued pursuant to the Davis-Bacon Act, (40 U.S.C. 276a et. seq.) and Department of Labor Regulations, Part 5 (29 CFR, Subtitle A). The January 13 opinion of the Solicitor applies to the assembly or fabrication of four 10-foot waveguide sections into a single 40-foot section or module at Building No. 5, Central Laboratories at Stanford, which is subsequently transported to the housing, a concrete tunnel below ground and a gallery above ground and installed as a part of the overall two-mile linear accelerator project. All known interested parties were notified that the petition had been filed and were requested to submit written statements by March 17, 1965. By virtue of the highly technical and complex methods employed ln the construction of the linear accelerator the Board announced that it would make a visitation to the Stanford Linear Accelerator Center, hereafter called SLAC. Representatives of the Solicitor had previously visited the site of the work. All interested [2] ~3 [3] parties were advised March 12 of the proposed visit to the Stanford installation and were invited to accompany the Board on its tour. The Office of the Solicitor was requested to send a representative of its Wage Determinations Division to participate in the visitation. The purpose of the visit, as stated by the Board in its invitation, was to prepare the Board to properly understand subsequent argument and statements concerning the issues in dispute. Listed below are those persons in attendance, along with the name of the organization which they represented: Messrs: Affiliation Barker Rothman Rivers Wage Appeals Board Tenney Office of the Solicitor of Labor Bradshaw Spalding Abruscato UA Simonds San Mateo County BTC Mohr Ragan Hiestand AEC Grant Aetron-Blume-Atkinson Panofsky Dawson Field Stanford Thomas IBEW The announcement stated that in the absence of an all-party agreement to hold the hearing at Stanford, an oral hearing would be held in Washington at a date subsequently to be announced. Upon the conclusion of the Board's tour of the site on March 24, it announced to all parties present that a hearing would be held at 2:00 p.m. on [3] ~4 [4] Friday April 2, 1985, in Conference Room 102, Main Labor Building, U.S. Department of Labor, Washington, D. C. Subsequently, written, notices of the hearing were mailed to all interested parties. The following organizations, although notified that the petition had been filed did not submit statements in this case: Associated General Contractors of America Building and Construction Trades Department, AFL-CIO Building and Construction Trades Council of San Mateo County, California National Constructors Association The International Brotherhood of Electrical Workers, the United Association of Journeymen and Apprentices or the Plumbing and Pipefitting Industry, Stanford University, and the U.S. Atomic Energy Commission filed written statements in advance of the hearing, as did the Solicitor of Labor. The petitioners and the Solicitor through respective counsel, presented argument at an oral hearing pursuant to the agreed notice on April 2, 1965. The Building and Construction Trades Department, AFL-CIO the International Brotherhood of Electrical Workers, and the United Association of Journeymen and Apprentices of the Plumbing and Pipefitting Industry, through respective counsel, also participated in the oral argument. FINDINGS OF FACT THE PROJECT The overall SLAC project involves expenditures in excess of $130,000,000 and may be divided roughly into three phases: (1) the construction of the office building and shops necessary to fabricate [4] ~5 [5] component parts and to assemble the component parts of the accelerator, (2) the actual installation of the two-mile accelerator, and (3) the construction of the housing for the accelerator on a two-mile strip and the construction of a target building. A linear accelerator is more popularly known as an atom smasher. This particular version is a further development of the prototype linear accelerators devised during the last decade by Stanford University, and is a contrast to the circular accelerators now in use at the Brookhaven National Laboratory in New York, the Argonne National Laboratory near Chicago, CERN Laboratory at Geneva, and in other parts of the world. The earlier linear prototypes developed by Stanford were designed, the parts manufactured and the accelerator fabricated in the existing shops and offices of the University proper. The techniques used in the development of the prototype became the basis for the subsequent manufacture and fabrication of the complex two-mile long accelerator now being constructed. Basically there are two purposes for high energy accelerators: (1) To enable the physicist to see the objects he is studying -- the protons, neutrons, and the many other kinds of particles that are the elementary constituents of all matter. Accelerators in this sense are like microscopes enabling the physicist to study particles a billion times smaller than the smallest object that can be seen with an optical microscope. (2) The accelerator is used to create new particles. Given enough energy, the Board is informed that all the thirty different kinds of elementary particles now known can be created by processes in which energy is converted into mass. [5] ~6 [6] The Stanford accelerator is suited to ,both of these basic purposes. For "seeing" the structural details of subnuclear particles, it will have no equal. Also, the combination of high energy and high intensity will make the machine an abundant source of all known elementary particles. The heart of this unique and complex instrument is a two-mile-long disc-loaded waveguide consisting principally of a series of the 40-foot modules the fabrication of which is at issue in this proceeding. At one end of the waveguide an electron gun injects short bursts of electrons 360 times a second. The electrons are driven forward by traveling waves of radio energy from klystron tubes injected into the waveguide at certain intervals. The klystron tubes and much other equipment is housed in the gallery above the tunnel. The electrons strike a target and observations are made of the resulting deflection patterns. Knowledge thus gained will lead to a better understanding of the mysteries of the subnuclear universe. In greater detail, the accelerator's purpose is to propel electrons to high velocities and energy levels for use in particle physics research. The electrons speed down the linear accelerator, propelled by radio waves from klystron tubes which are spread at ten-foot intervals. The accelerated electrons strike a target and observations and analyses are made from the deflection patterns and the resulting creation of new particles. The part which actually accelerates the electrons is an accurately fabricated tube made of copper disks and rings machined [6] ~7 [7] to very close tolerances. This is the "disk-loaded waveguide". The disk-loaded waveguide assembly is fabricated in 40-foot modular lengths and placed end-to-end to form the two-mile long accelerator. The accelerator is described by the AEC as essentially a precision instrument. A 40-foot disc-loaded waveguide cannot be made in one piece at this time. The longest piece of the disc-loaded waveguide that can be feasibly made in one piece is 10 feet. Each 10-foot piece is formed of 85 "disks" and two end plates, all 4" in outside diameter. The spaces are 1.147-inch pieces of copper pipe; the disks are 0.230 of an inch thick; and the two end plates are 0.7629 of an inch thick. The 86 spaces each have a different inside diameter; one differs from the next by about 3/4 of a thousandth of an inch. Likewise, each of the 85 disks has a different aperture size, ranging from 1.0323 inches to 0.7517 of an inch over the 10-foot piece. Each ten-foot section is brazed together in a special furnace. Four ten-foot lengths and such other equipment and paraphernalia are then joined and fabricated together into the 40-foot modules. This assembly consists of a 40-foot long 24-inch diameter aluminum pipe on supports, which becomes the supporting beam. Attached to the top of the beam are adjustable supports for the waveguide (which is in 10-foot sections), waveguide connections for the klystron tube lines, vacuum lines, coolant lines, shielding and degaussing cables. Targets and sights are attached to both the interior and exterior of supporting beams for alignment and calibration. Exterior sights are used with optical equipment and interior targets are used with a laser beam under low pressure vacuum. [7] ~8 [8] The assembly of the 40-foot segments takes place in a permanent fabrication building, one of three large and permanent buildings which will service the accelerator. After the 40-foot sections are completely calibrated they are moved to the accelerator tunnel, 25 feet underground, lowered into the tunnel, and moved longitudinally into final position secured to the adjoining section, leveled and otherwise adjusted. This accomplished, proper piping and connections are made for waveguides, coolant and vacuum lines from equipment in the galleries. The labor cost of the disputed assembly work involved has been estimated to be about $84,000 to $100,000. This represents the employment of sixteen workmen over an eighteen-month period. The disputed work involves the following stages: (1) Joining of four 10-foot basic sections of the disk-loaded waveguide of the top of a 40-foot aluminum pipe supporting structure about two feet in diameter; (2) Mounting of the rectangular waveguides which feed the electrical power impulses to the disk-loaded waveguide at 10-foot intervals; (3) Installation of degaussing wires and shielding which run parallel to the disk-loaded waveguide, and which neutralize the magnetic field; (4) Installation of numerous water coolant pipes; (5) Installation of vacuum piping and fitting; and (6) Aligning of components. [8] ~9 [9] The assembly work takes place in a permanent fabrication shop. It is the same shop where the 10-foot components, which comprise the 40-foot units, are made. There are about 244 employees in this shop who are engaged in fabrication or assembly work or both. SUMMARY OF SOLICITOR'S ACTIONS On July 15, 1964, the International Representative of the International Brotherhood of Electrical Workers in San Francisco, California, wrote the Solicitor of Labor requesting a ruling on the application of the Davis-Bacon Act to certain assembly and installation work to be performed at the Stanford Linear Accelerator Center, Stanford, California. The work was to be performed under contract No. AT(04-3)-400 for the design and construction of the accelerator. This letter was in effect an appeal from a June 26 decision of the Atomic Energy Commission area manager at Palo Alto that the assembly and installation of the disc-loaded waveguide and its ancillary components was not covered by the Davis-Bacon Act. The area manager in his letter stated: It is my decision that the manufacture and assembly work of the Disk-Loaded Waveguide being performed in the Shops Complex, which results in a functionally complete 40-foot segment or structure, noncovered. The transportation of the 40-foot piece of equipment from the Shops Complex and its installation in the Accelerator Housing is considered to be covered work within the meaning of the Davis-Bacon Act. On September 17 and 18, 1974, a joint visit was made to the SLAC site by the Atomic Energy Commission and the Department of Labor. [9] ~10 [10] By letter of March 17, 1964, the United Association also urged a ruling from the Office of the Solicitor to the effect that the Davis-Bacon Act applied to the installation and assembly work involved. Subsequently, on January 13, 1965, the Solicitor of Labor advised the Atomic Energy Commission that in his opinion the Davis-Bacon Act applied to the installation and assembly work in question. Thereafter, the Atomic Energy Commission and Stanford orally requested the Solicitor to reconsider his decision. The Solicitor declined to change his decision and so notified the Atomic Energy Commission and Stanford. Whereupon the Atomic Energy Commission and Stanford petitioned the Department's Wage Appeals Board for a review of the ruling of the Solicitor in the matter. This part of the work is the only part of the work which has been directly questioned, but the Solicitor has neither questioned nor applied the Act to the other parts of the work in the Central Laboratories Building involved in preparing the 40-foot modules. From the brief and argument of the Office of the Solicitor the Atomic Energy Commission determination in this matter is viewed as correct in all respects except for the ruling with regard to the assembly of the 40-foot module. ISSUES AND CONCLUSIONS Issues raised by petition include: (1) Should a decision by the Atomic Energy Commission with respect to the application of the Davis-Bacon Act under its applicable rules (41 CFR, part 9-12) be considered controlling? (2) Does the assembly of the 40-foot [10] ~11 [11] modules constitute "construction"? (3) If it is "construction", whether or not it is de minimis. At the hearing, counsel for petitioners contended pertinaciously that the decision of the Atomic Energy Commission should be accorded strong presumptive validity. We assume that the Atomic Energy Commission is urging that agency decisions should not lightly be set aside. It is always assumed that agencies are acting in good faith when they are performing their official duties. The Wage Appeals Board does not take a different view. A decision as to the Act's coverage must be set aside when the weight of the evidence demonstrates that it is not in accord with the Act and regulations issued pursuant thereto. This conclusion is supported by Reorganization Plan No. 14 of 1950 and, indeed, the Atomic Energy Commission rules contemplate a final decision by the Department Or Labor. See 41 CFR 9-12.5004-2(h)(5). The Board is called upon for the first time to determine whether or not certain work is subject to the provisions of the Davis-Bacon Act that is, whether employees engaged upon that work are entitled to the protections of the Act. Inquiry into whether certain work is "construction, alteration or repair" work for purposes of the application of the Act is by and large a matter of fact. Inquiry must begin by looking at the work itself to determine whether or not it should be subsumed under recognized categories of construction, repair or alteration of a public building or public work. When questioned work is examined for purposes of determining coverage under the Act, it must be viewed through the eyes of persons experienced in building and construction matters who have developed expertise in the application of the Act to a wide range of activities. [11] ~12 [12] Based upon the files and records made available to the Board by the Office of the Solicitor, the Statement of the Solicitor, the Briefs submitted, and arguments made by the parties and interested persons at the hearing, taken as a whole, the Board concludes that the work in question is not covered work subject to the provisions the Act. We do not think that the residing parties have spelled out any meaningful degree of functional difference and autonomy between the assembly of the 40-foot module and the other fabrication work that goes on in Building No. 5, which will support a rational differentiation of one type of work from the other. There are components housed in the klystron gallery which are fabricated as units in the central laboratory which are not covered. There is the fabrication of rectangular waveguides with brazed and assembled parts thereon done in the central laboratory which are added to the 40-foot module and which are not covered. There is the 10-foot disc-loaded waveguide itself, which concededly is not covered. If a distinction is sought to be drawn between light assembly work as not covered and heavy assembly work which is covered as was attempted in the hearing, then we do not see a sufficient degree of technological distinction in making and completing the 40-foot section from making and completing the other work to warrant placing one type of work in a separate category from the other work, all performed in the central laboratory. The Wage Appeals Board reaffirms the principle that on-site work or project work which is removed from the site for the facility or convenience of the contractor is covered work. But in this case the Board is required to reject the contention that the questioned [12] ~13 [13] work can be adequately separated from the noncovered production activities to justify separate treatment under the Davis-Bacon Act. We do not see that to do so would effectuate the purposes of the Act in any meaningful way. The primary activity at the central laboratory in producing and fabricating the 40-foot module is, for practical purposes, an integrated operation which precludes the work which takes place there from over-fragmentation for the purpose of applying the Davis-Bacon Act to some 16 employees out of about 244 employees. Despite the contention that the work is in a separate work place in the central laboratory, we cannot so find. The employees who are not covered and those in question here work in the same large room. While the area where the 40-foot module is assembled is at one end of the room, this is only a matter of convenience to have the space and to permit the 40-foot module to be moved out conveniently. Other employees working in the same room are not separated from these employees by as much as an aisle. The space arrangement simply facilitates a logical sequence of production for making the 40-foot module from raw materials and other parts fabricated in the laboratory or brought in from elsewhere. The 10-foot sections and other components placed on the 40-foot girder are located in the same large room and are brought to the girder in no particular order or sequence. The Board must reject the Solicitor's contention that the total operation is not so integrated as to preclude the establishment of Davis-Bacon wage rates for the assembly of the 40-foot girder and not for all the other work undertaken in the central laboratory pertaining to the performance of the work under the contract. [13] ~14 [14] We look at the production of the 40-foot module from the fabrication of the raw copper sheets and tubes and the work on the other component parts to the completion of the 40-foot section as a primary production operation not subject to the Davis-Bacon Act under the unique and special circumstances found in this case. Indeed, the furnace for brazing the 10-foot unit lies beyond the area where the 40-foot assembly takes place, and the employees, concededly not covered, would be moving back and forth through the area where the questioned employees would be working if they were covered. The skills, techniques, and types of equipment used for making and testing equipment other than the 40-foot module and for the 40-foot module are similar throughout the plant even though certain highly sensitive gauges and hydraulic presses are required for the 10-foot section. While the two-mile linear accelerator is a modern scientific piece of nuclear machinery for purposes of scientific experiments and when installed will be a single piece of equipment, its installation in the gallery and tunnel is, by accepted and time- tested Davis-Bacon principles, a public work of the United States and is covered. It is conceded and it is not an issue in this case that any employees who leave the area of the Central Laboratory land go on the site of the accelerator housing, that is, the gallery and the tunnel, to work there would be subject to the Act when so engaged. Central Laboratory Building No. 5, while built recently and under a contract which includes the accelerator project, is a permanent [14] ~15 [15] structure for nuclear research and as such is integrated with a complex of nuclear scientific undertakings at Stanford University. It is, and will be, devoted to these uses on a permanent basis serving on site and off site activities. Without having to decide whether building is directly upon the site of construction or not, the Board concludes that under these circumstances even if it were within the perimeter of the construction site, that factor alone cannot be controlling here. We recognize and do not reject the argument of the interested labor organizations who have appeared in this case that employees whom they usually represent have the skills and can and do perform the work in question. We also recognize, however, that such employees can and are frequently engaged in non-construction work. We look at the work involved. We reject the contention of the petitioners that any principle of de minimis could be applicable to this case. Petitioner argues that in comparison to the cost of the overall project of some $130,000,000, this is such a trivial sum as to be insignificant. The amount of work in question, approximately $84,000 to $100,000, is more than substantial to be subject to the Act if it were determined that the work is covered. In the past there have been a number of efforts to formulate expressly and by universal principles, exactly when a questionable work or activity is or may be covered work. We do not believe it will serve the purpose of an efficient and realistic administration of the Davis-Bacon Act to establish such formulas, but suggest that each case must be evaluated on the basis of its own particular facts. For the reasons noted earlier in this decision, determinations of the kind here involved are dependent on the particular facts as they relate to the inquiry in which the question is raised. This decision [15] ~16 [16] cannot form the basis for any broad predicate that work of the type here involved would or would not be subject to the coverage of the Act in a different factual context. ORDER On the basis of the findings of fact and conclusions of law and pursuant to section 7.8(a) of the Board's Rules and Regulations, the Wage Appeals Board finds that the assembly of the 40-foot module is not "construction" work covered under the Davis-Bacon Act. Dated at Washington, D. C. this 12th day of April, 1965. Stuart Rothman, Member Clarence D. Barker, Member WAGE APPEALS BOARD [16]



Phone Numbers