skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

MILNOR CONSTRUCTION CORP., 1988-DBA-12 (ALJ Apr. 30, 1991)


CCASE: MILNOR CONSTRUCTION CORP. DDATE: 19910430 TTEXT: ~1 [1] [91-21 ATTACHMENT] U.S. Department of Labor Office of Administrative Law Judges 1111 20th Street, N.W. Washington, D.C. 20036 In the Matter of Disputes concerning the payment of prevailing wage rates and overtime by MILNOR CONSTRUCTION CORP., Prime Contractor and DIAL ELECTRIC CONTRACTING CO., INC. Subcontractor and Case No. 88-DBA-12 Proposed Debarment on account of Labor Standards Violations by DECISION AND ORDER DIAL ELECTRIC CONTRACTING CO., INC. and HERMAN ROSENBLATT, Its President With respect to laborers and mechanics employed by the Subcontractor under U. S. Department of Housing and Urban Development Contract No. NY36-P005-292 (Lenox Road - Rockaway Parkway Rehabilitation, Brooklyn, New York) Sheldon Feinstein, Esquire Bayside, New York For the Contractor No Appearance for the Subcontractor Louis DeBernardo, Esquire Office of the Regional Solicitor United States Department of Labor New York, New York For the Complainant Before: Aaron Silverman Administrative Law Judge [1] ~2 [2] DECISION AND ORDER I. Introduction and Issues This case, arising under the United States Housing Act of 1937, as amended (42 U. S. C 1437j) and the Davis-Bacon Act (40 U. S. C. 276a et seq.), came on for hearing in New York City on May 17-18 and July 19 in 1989. It is to be decided under the procedures prescribed in the Act, Reorganization Plan No. 14 of 1950 (64 Stat. 1267), and the applicable regulations (Part 5 of Title 29, Code of Federal Regulations, particularly its sections 5.11(b) and 5.12(b)). /FN1/ The parties here agree that the work in question was covered by the Act, but the Department contends that there was an underpayment of wages that were due to nine certain workers on the project, and it seeks also to debar from future contracts with the Federal Government the Subcontractor, Dial Electric Contracting Co., Inc. and its president, Herman Rosenblatt. The Department appeared in this proceeding and actively presented its case. So also did the Prime Contractor, Milnor Construction Corp., which acknowledges its obligation to pay the amount of any such wage deficiency as is alleged, but which vigorously contests the amount claimed for it by the Department. Neither Dial nor its president appeared in the action. We are presented, therefore, with two issues for decision, as follows 1. Was there any deficiency, in wages paid under this contract to each of nine certain workers, and if there was how much was it for each one? 2. Should Subcontractor Dial and its president, Herman Rosenblatt, or either-of them, be debarred under the Act from contracting with the Federal Government? [2] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ The following abbreviations may be used in this Decision and Order: The Act, to refer to the Davis-Bacon Act; The Department, to refer to the United States Department of Labor; Milnor or the contractor to refer to Milnor Construction Co.; Dial or the subcontractor, to refer to Dial Electric Contracting Co.; The Lenox site or the project, to refer to the Lenox Road Rockaway Parkway Rehabilitation Project; Tr., with a page reference, to refer to pages of the transcript of hearing; and Exh. P- and Exh. R-, with a number, to refer to Exhibits of the Department of Labor (P-) or the Contractor R-) in the record of this proceeding. [2] ~3 [3] For reasons which are fully discussed below, I have concluded that there were deficiencies in wages paid, in amounts that I have computed for each of the nine named workers, that Milnor and Dial are jointly and severally liable for the payment of those deficiencies, and that both Dial and Mr. Rosenblatt should be debarred. II. The Davis-Bacon Act A. The Act and Its Implementing Regulations The Davis-Bacon Act, 40 U. S. C. 276a et seq., requires that contractors on Federally funded construction projects pay not less than prevailing wages, as determined by the Secretary of Labor, to all persons who perform the duties of "laborers or mechanics" on such projects. The Act by its own terms applies to every contract in excess of $2,000 to which the United States or the District of Columbia is a party, for "construction, alteration, and/or repair, . . . and which requires the employment of mechanics and/or laborers.... The Act provides in substance that all mechanics and laborers employed directly upon the site of the work . . . [shall be paid not less than prevailing wage rates in the area as determined and announced by the Secretary of Labor,] regardless of any contractual relationship which may be alleged to exist between the contractor or subcontractor and such laborers and mechanics. Failing such payment, the Act authorizes the Government contracting officer to withhold from the contractor such amounts as he deems necessary "to pay to laborers and mechanics employed by the contractor or any subcontractor on the work" the difference between those required rates of pay and the rates actually received by the workmen. Section 5.2(o) of Title 29, Code of Federal Regulations reads as follows: Every person performing the duties of a laborer or mechanic in the construction, prosecution, completion, or repair of a public building or public work, . . . is "employed" regardless of any contractual relationship [3] ~4 [4] alleged to exist between the contractor and such person. The terms "laborer" and "mechanic" have repeatedly been construed under the Act to include all workers working on the project, including common labor, clean-up workers, skilled and semi-skilled and unskilled labor, and the trades, among others. There is no doubt, and none of the parties disputes, that the term includes workers doing the work that the workers in question performed here. B. Interpretations of the Davis-Bacon Act The Davis-Bacon Act, 46 Stat. 1949, P.L. 74-403, 4[0] U.S.C. 276a-276a-7, as amended, was enacted in 1931. It has been interpreted often and consistently enough with respect to several common or recurring fact situations that we can accept certain principles relating to it as well settled. It is remedial legislation, and it was enacted for the benefit of workers, and not for the benefit of contractors or subcontractors. Universities Research Ass'n., Inc. v. Coutu, 450 U.S. 754 (1981); United States v. Binghamton Construction Co., 347 U.S. 171 (1954); North Georgia Bldg. and Constr. Trades Comn. v. Goldschmidt, 621 F.2d 697 (5th Cir. 1980). Workers cannot waive, release, or in any manner contract or sign away their rights to the correct wages under the Act. Brooklyn Savings Bank v. O'Neil, 324 U.S. 697 (1945); U.S. ex rel. Maude A. Johnson v. Morley Construction Co., et al., 98 F.2d 781 (2nd Cir. 1938); In the Matter of Jack Picoult, WAB Case No. 68-9 (Dec. 9, 1968), p. 13. A prime contractor is responsible for the back wages due employees of its subcontractor. 29 C.F.R. secs. 5.2(o), 5.2(i), 5.5(a)(2), 5.5(a)(6); All Phase Electric Co., WAB Case No. 85-18 (June 18, 1986); A. D. Roe, Inc., WAB Case No. 84-11 (December 18, 1985); In re Simpson Construction Co., 24 WH 484 (1979); ln re J.B.L. Construction Co., 23 WH 1064, 1071 (1978). In fact, a prime contractor has the responsibility to insure that all persons engaged in performing the duties of a laborer or mechanic on the construction site receive the appropriate prevailing wage rate, irrespective of any contractual relationship alleged to exist or not to exist between the contractor and such persons. 40 U.S.C. sec. 276a; In re Simpson Construction Co., 24 WH 484 (19[79]); In re J.B.L. Construction Co., supra. No employment relationship with the prime contractor -- Milnor, here -- need be shown, for Milnor to be responsible under the Act for compliance with its terms. 29 C.F.R. secs. 5.2(o), 5.5(a)(1)(ii)(D); In re Joseph Morton, 26 WH 1450, 1451 (1984). III. The Undisputed Facts The parties agree that the following statements are true: 1. Or May 1, 1984 the New York City Housing Authority entered into a contract with the Rocky Hill Building Corporation, on a turnkey construction [4] ~5 [5] operation, under which Rocky Hill agreed to renovate, according to plans and specifications furnished it by the City, three abandoned buildings, which together made up the Housing Authority's Lenox Road Rockaway Parkway Rehabilitation Project No. NY36-P005-292, and then to sell the renovated project back to the Housing Authority, all œor $ 4,350,000. The funds involved were furnished entirely by the [] United States Department of Housing and Urban Development, and the contract contained the prevailing wage schedule applicable under the Act. It also contained the prevailing wage rates applicable under the New York State Prevailing Wage Act (sec. 220 of the State Labor Law). This project is referred to hereinafter as "the Lenox" job site or project. Exh. R-1 Tr 101, 434, 456-7, 594. 2. On May 15, 1984, Rocky Hill contracted with Milnor Construction Corporation for Milnor to be the prime contractor of the Lenox project. Exh. P-31. 3. The two corporations, Rocky Hill and Milnor, were under a common ownership and control. President of both was Milton Novie; he alone owned all the shares of stock in Rocky Hill, and with his wife he owned all the shares in Milnor. Tr. 593, 607, 625. 4. On July 2, 1984, Milnor as prime contractor on the Lenox project contracted with Subcontractor Dial Electric Contracting Co., Inc., for Dial to perform all the electrical work on the project, for the total amount oœ $199,800. Exh. P-3. 5. The Lenox project consisted of three buildings, known respectively as No. 1 (1142 Lenox Road), No. 2 (1144 Lenox Road), and No. 3 (1145 Lenox Road). Thus the Government contract with Rocky Hill was signed on May 1, 1984, Rocky Hill's with Milnor on May 15, 1984, and Milnor's with Dial on July 2, 1984. The exact dates when work began and was completed on the project are not agreed on, but certain relevant dates in 1985 do appear in the record for Buildings 2, 3, and 1 respectively: Certificates of occupancy were granted by the city on February 15, March 13, and April 8 (Exhs. R-3, R-4, R-5); Board of Fire Underwriters' certificates were issued February 12, February 12, and April 2 (Exhs. R-12, R-13, R-14); and the deeds transferring title to the City were executed February 25, March 22, and May 1 (Exhs. R-9, R-10, R-11). Even after the work was formally completed, however, the Contractor and Subcontractors were responsible to return to the project to repair deficiencies and take care of incomplete work noted on a "punch card list." See. Tr. 81-2; Exh. R-2, 6/3/85. 6. While Dial was performing the electrical work under this contract, it was also performing electrical work under an unrelated contract on an unrelated but nearby job, referred to as the Park Rock project. Park Rock is not directly involved in this case. It is relevant, however, that Dial, for its own administrative convenience and advantage, shifted its men about between the [5] ~6 [6] two jobs even during parts of the same day, and it apparently maintained no records that showed how any employee's hours were divided as between the two projects. Tr. 445. 7. During the period of its performance of the work on the Lenox project, Dial employed among others nine workers whose allegedly inadequate wages constitute the basis for the Department's Order of Reference in this case. These workers were Rosario ("Teto") Fernandez, Winston Foy, Solomon Glantz, Ilya Illish, Antonio ("Tony") Irizarry, Patrick Lopez, Michael Reale, Joseph Solla, and Herme Valle. All of these, except Patrick Lopez, testified at the hearing. All but Irizarry and Valle had earlier filed written statements with the Department. 8. The Department claims that these men were underpaid wages, in violation of the Davis Bacon Act, in a total sum for all of them of $119,154.14. Milnor acknowledges that the men were underpaid by Dial, but contends that the total sum of those underpayments is no greater than $9,529.56. The case of each man will be discussed separately below. IV. Debarment of Dial and Rosenblatt The Department asks in this proceeding that Dial Electric and its president personally be barred, as provided in the Act, from further contracting with the Federal Government. A three-year debarment is provided, under the provisions of 29 C.F.R. sec. 5.12(a)(1), against a contractor or subcontractor whose violations under the Davis Bacon Act are determined to be "aggravated or willful." Reason tells us, and the Wage Appeals Board has consistently held, that failure to pay prevailing wages, accompanied by the submission of payrolls falsified to show that the required amounts were paid, are sufficiently aggravated and willful to constitute grounds for debarment, under this provision. Camilo A. Padre[d]a General Contractors, Inc., WAB Case No. 87-1 (August 3, 1987); Morris Excavating Co., Inc, WAB Case No. 86-27 (February 4, 1987); Wilfred G. Gooden Construction Corp., WAB Case No. 86-3 (October 1, 1986); McAndrews Co. and Robert McAndrews, WAB Case No. 86-22 (March 26, 1986); Warren C. Manter Co., WAB Case No. 84-20 (June 21, 1985). If this mere falsification of those records were not enough, there is more: the record shows clearly that Dial maintained two sets of books on payroll, a false set to show payments in the required Davis-Bacon amounts (Exh. P-4), and a presumably truer set reflecting different amounts paid, for use by Dial management in-house (Exh. P- 5). These practices of Dial's demonstrate beyond any reasonable doubt that Dial Electric and Herman Rosenblatt deliberately filed fraudulent payrolls that simulated compliance with the requirements of the Act, by showing false wage rates paid and inaccurate counting of hours worked, omission of the names of [6] ~7 [7] employees who were actually working, and failing to include all employees under their proper wage classification. This conclusion is further supported by the uncontradicted testimony of Rosario Fernandez, that when he called Rosenblatt's attention to the fact that Fernandez was not receiving the prevailing wage rate as required under the Davis-Bacon Act, Rosenblatt responded simply that "If you don't like it then you can leave" (Tr. 391, 393). See Exh. P-4, and testimony of the respective workers, Tr. passim; cf. wages and hours worked for Ilya Illish and Michael Reale in Exhs. P-5, P-16, and P-18. Dial did not deny, in response to a Request for Admissions served by the Department, the Department's contentions with respect to the number of men working on the Lenox job, the number of hours that each one worked there, and that the men involved were electricians. Exh. P-29; 29 C.F.R 18.20(b). The record thus demonstrates clearly that both Dial Electric and Herman Rosenblatt should be debarred as provided under the Act. V. What Rate of Pay Applies A. The Contract Provisions 1. The Davis-Bacon Act schedule. The parties disagree with respect to the rate of pay that should be employed in the computations in this proceeding. They do agree that the contract between the Housing Authority and Rocky Hill contained a provision requiring that workers on the job be paid at wage rates not less than the aggregate of the basic hourly rates and the rates of payment contributions, or costs for only fringe benefit contained in the wage determination decision of the Secretary of Labor which is attached hereto and made a part hereof, regardless of any contractual relationship which may be alleged to exist between the contractor or subcontractor and such laborers and mechanics. Exh. R-1, exh. "D" of the contract. The contract contains Department of Labor Decision No. NY 83 3032, which requires: [7] ~8 [8] Basic Hourly Wage Fringe Benefits Electricians $19.50 29.2% + a + b Jobbing, maintenance, repair work; alterations and new work up to contract price of $50,000 8.75 10% + a + b Footnotes: a. Employer contributes $4.00 per day b. Paid Holidays: A through F, Washington's Birthday, Columbus Day and Election Day Paid Holidays: A - New Year's Day, B - Memorial Day, C - Independence Day, D - Labor Day, E - Thanksgiving Day, F - Christmas Day 2. The New York State schedule. The contract also contains the prevailing rates established under the New York State Prevailing Wage Act. Exh. R-1; Tr. 456. The Contractor here points out that it too contains two rates. The first is $20.50 per hour, plus certain fringe benefits the value of which I am unable to determine from the record before me. The second is a lower rate designated as "Electrician 'M'". This rate is $10.75 per hour, likewise plus certain fringe benefits named but not evaluated. In addition, the State schedule has lower rates for "electrician trainees." The "Electrician 'M'" rate appears to be for work deemed as "jobbing, maintenance and repair work." Tr. 457. It is apparently customary to pay the higher rate on new construction, and the lower, "M," rate on alteration work. Tr. 602. In order to start work on the buildings, Milnor was required to obtain a building permit. It appears that there are three types of building permits issued. One is for a small alteration, for which a "BM" number is issued. The second is for a large alteration; for this, the contractor receives an alteration number. The third is for a new building, for which the contractor receives an "NB" number. Tr. 604. For the Lenox project, Milnor received a building permit bearing an alteration number. Exh. R-8; Tr. 604. It is conceded by the Department that the work to be done here was the rehabilitation and repair of existing buildings. Tr. 459. [8] ~9 [9] B. What Was The Workers' Proper Job Classification? Milnor does not seem to contest that the workers must be regarded as electricians, but it does disagree with the Department with reference to the applicable rate of pay. It is well settled that under the Davis-Bacon Act worker classification is determined on one basis only, that of actual work done, irrespective of worker qualification or degree of skill or experience. The record contains no contradiction of the testimony, given by all the eight workers who testified, and in the written statement of the ninth, that all of them used the tools customarily used by electricians and performed work customarily performed by electricians. Having done that, they must be paid as electricians, under the Act. The lack of experience or other qualifications, relied on by Milnor as supporting a lower rate, is altogether irrelevant under the Act. If a contractor or subcontractor chooses to have apprentices do the work of journeymen or masters, he must pay them as such. The choice as to assignment belongs to the employer, under the Act, but the choice as to pay, once the assignment is made, belongs to the Secretary. It may well be, as the Contractor here contends, that these employees were "M" workers, and even that some of them were no better than helpers. If so, they should have been assigned work commensurate with their ability. But if an employer, on a Davis-Bacon job, wants to have a young man still in high school do electrician's work for him, that employer exposes himself to the risk among other risks that the Department of Labor will agree with the employer about the worker's classification, and require that the employer pay that worker electricians' wages. Framlau Corp. WAB Case No. 70-5 (April 19, 1971), cited in FSG Contracting Co., 76-DB-110 (June 22, 1976); Lee Roy Corley, 77-DB-114 (March 21, 1978), aff'd, Decision of Administrator (October 6, 1978); Titan Atlantic Constr./Quality Electric Contractors, 78-DB- 125 (August 23, 1978). C. What Is The Workers' Applicable Rate of Pay? Milnor contends that the applicable base wage rate is $8.75, because the work involved was "alteration" work under New York State law. It contends that this rate is further supported because it corresponds most nearly to the New York State "M" rate, which the claimant workers' here acknowledge is all they are paid on private jobs. Nevertheless, this is not an argument that need detain us long, in view of the restriction of this rate in the schedule to contracts of $50,000 or less; both Milnor's contract and Dial's involve prices of much more than that. In any event, New York State law, though as a matter of Department policy its wage rates might be accepted as a floor for Federally funded projects, would surely not take precedence over the rates established pursuant to a United States statute! We see no other hourly wage rate here than the Davis-Bacon base for "Electricians" of $19.50, which with the addition of 29.2% ($5.69) and the $4.00 daily in footnote "a" ($.5714 per hour for a [9] ~10 [10] seven-hour day and $.50 per hour on the basis of eight) amounts to a rate of $ 25.76 or $25.69 per hour, for a seven-hour and an eight hour day, respectively. Milnor advances two other arguments on this point. Both are futile. One is that (1) New York State recognizes the "M" rate, for electricians having more than apprentice skill and experience, but less than that of journeymen, (2) the State "M" rate ($10.75 per hour plus fringe benefits) is what these men were customarily paid on jobs not federally funded, (3) the $8.75 rate set forth in the Act (as shown above) is substantially equivalent to the State "M" rate, so that (4) that lower Davis-Bacon rate is the one that should be applied here. The short answer to this argument is that, while the contract does not allow the contractor or its Subcontractors to pay less than the State-determined "M" rate, the Davis-Bacon Act makes no exception to its own rates in favor of the State rate; the Davis-Bacon provision fixing the rate of $8.75 states clearly what work it applies to, and that is not the work being performed here. Milnor's other contention is that the provision in the Act regarding the lower rate is ambiguous, as to whether the cap of $50,000 applies only to "new work," or to "alterations" (which they contend the work under this contract is) as well, that because of this ambiguity the Government as drafting party should be subject to the principle of contra proferent[u]m and have the ambiguity resolved against it, with the result that the rate of $8.75 would apply. This argument, too, fails; I find the provision entirely unambiguous as applying the $50,000 cap for the rate of $ 8.75 to both alteration work and new work. I conclude, accordingly, that the wage rate to be applied in this case is the $19.50 base, increased by the adjustments described above. VI. For How Many Hours Were The Workmen Underpaid? A. Introductory Statement There are many, and conflicting, bases in the record for computing how many hours each man here involved worked under this contract. I found all the testimony, on both sides, credible, as being what the witness now recalled, with perhaps one exception. Witness Ilya Illish's explicit and detailed recall of his own data, and even that of other workers, with respect to this one job they had worked on five years before, coupled with the contrasting vagueness of his recall about jobs preceding and following this one, renders his testimony in my judgment significantly less credible than that of the other witnesses. Obviously all the witnesses, other than DOL Investigator Irv Miljoner and City Housing Authority representatives Alvin Reinstein and Joseph Nanartowich (and the Authority's Superintendent on the job, Colville D. Holt, who signed its daily construction log, Exh. R-2, and is [10] ~11 [11] now retired, Tr. 81), had a pecuniary interest in the outcome of the case, and the recollections of all were being given at a distance of five years from the actual events, but I do not find that these facts diminished the credibility of the testimony as being truthfully what the witness now recalled. Nevertheless, these credible witnesses in several respects contradicted each other. B. The Number Of Hours In the Working Day One such respect relevant here is the length of the working day on the project. All the workers who testified (except for Solla, who worked only half-days), and Lopez in his statement, said that they worked each day for eight hours, from 7:30 a.m. to 4:00 p.m. (after an initial period when both times were half-an-hour earlier), with a half-hour for lunch, and that they worked those hours regularly five days a week, for a total of forty hours. Solla's testimony, regarding his half-day work, was consistent with this, and so were the written statements given by several of the workmen at earlier times nearer to the actual events. Dial's "in house" accounts (Exh. P-5) also show forty-hour weeks, and the pay stubs that are in the record reflect the same thing. Exhs. P-7, P-16, P-18, P-21, P-23, P-30. On the other hand, Dial's false certified accounts, Exh. P-4, submitted for the purpose of satisfying the requirements of the Act, show a 35-hour work week. Both the owner of Milnor, Milton Novie, who visited the site occasionally, and his foreman, Joe Carbonara, who made an inspection trip there every day precisely to see what manning the trades had and to check on the progress of the work, and to note his observations down in a daily report (Tr. 640; Exh. R-7), were very definite in their testimony that Lenox was a seven-hour day (7:30 a.m. to 3:00 p.m.), 35-hour-per-week job. Both said that the premises were secured at the end of seven hours, that no trade was allowed to work beyond that time without requesting and obtaining permission from Milnor, and that no such permission had been requested or given. The persuasive weight that I can attach to Milnor's evidence, however, is diminished by the fact that they declined the Department's request to produce their own daily reports. Tr. 437-8, 479-80. I find that the men worked five eight-hour days for a forty-hour week. I accept the Milnor testimony as fully credible, but that testimony also suggests that neither of its two witnesses ever actually inspected the site during non-working hours and that the "security" after working hours really was not for the purpose of monitoring the trades. I simply have no basis to conclude that [11] ~12 [12] there was some sort of a conspiracy among the men, or somehow that they all suffered by chance from the same misapprehension, extending back to the time they made their respective written statements. The conformity of Dial's "Davis-Bacon" books with the Milnor witnesses' testimony suggests that what they say is correct as to how things should have been, but the more reliable character of Dial's "in-house" books and the weight I accord the unanimous testimony of the workmen makes me find as a fact that the men did work on the Lenox project a forty-hour week made up of five eight-hour days. C. The Comparative Reliability Of Records There are several sources of information in the record as to the periods of time during which each of the nine claimants here was employed on the Lenox project. First is the testimony of the men themselves, buttressed by the statements most of them gave at a time closer to the events and by the recollections of each one with respect to the presence of the others on the job. Another is Dial's payroll records, particularly the inherently more trustworthy "in-house" edition, Exh. P-5. Milnor's job superintendent, Joseph Carbonara, who inspected the site and the work every day, made a daily record of what work each trade was doing and how many foremen and crew were on the site doing it. Exh. P-7. Colville D. Holt, Superintendent of the project for the New York City Housing Authority, also inspected the site daily for the same purpose, and made the same sort of record, Exh. R-2; however, half of his records (February - June 1985) were reported missing, so that we do not have them all. Nor, as I have already observed, do we have Milnor's own daily payroll records. The record, needless to say, does not present a clear picture. The testimony and earlier statements of the respective claimant witnesses are generally consistent with each other and, as I have already stated, I find them credible. Moreover, although it is conceded that Dial had a second, apparently private, project nearby, just across the street or down the block, and readily transferred men back and forth between the two projects, none of the pay or other records reflect which of the two projects any of the men was working on at any time, so that the workers' testimony and statements themselves are the only basis I have to determine which specific individuals were working on the Lenox site at any given time. As for Dial's records, even if they did indicate what project a man was working on during any day or part of a day, I would take for granted that the data was artificial, to attribute more or fewer men to the Government job for whatever advantage one or the other course might give Dial. However, I accept their "in-house" records, Exh. P-5, as being generally credible with respect to total hours of work and rates of pay for each man. Carbonara's and Holt's respective records seem to me trustworthy enough, in that they were being made for dealing with actual operations, subject to a recognition of their limitations. Neither of them shows names; both follow a form, as for example "1/5," that would show the presence of a single foreman and five men working [12] ~13 [13] on the trade. These two records unfortunately do not agree, either with each other or with the claimants' evidence, in that both generally show fewer electricians than are claimed to be present and Milnor's record generally shows fewer than Holt's. In addition, of course, half the Holt records could not be found. Once again, I must allow the most weight to the testimony and statements of the claimants. Their knowledge of their own activities was, necessarily, complete, at least as of the time the events took place. But both Carbonara and Holt were not normally on the job site the whole day; they came and went, so that their records are a snapshot taken at a given time during the day. This would still be the case, even though they did rely on information they obtained from the various foremen on the job, as well as on their own observations. The fact that both would be interested in obtaining an accurate count, and yet that they often disagree, at least indicates some inaccuracy in their reports. It may also be -- the record does not show -- that their count of "electricians" was limited to qualified tradesmen, and did not include those of the claimants who clearly do not purport to be qualified electricians but who must be considered so under the facts of this case for Davis-Bacon Act purposes. If that were the case, they would inevitably record fewer than the Act includes, on the basis of its criteria based strictly on what work the worker was performing, irrespective of his qualifications or lack of qualification to perform it properly. In any event, Milnor's refusal to furnish its own reports necessarily gives rise to a diminution of confidence in its allegations. Thus I credit most heavily in this record the testimony and statements of the claimants, as reflecting most accurately what each of them did and when he did it. Precise computation for each claimant appears below. D. At What Rate Were The Claimants Actually Paid? There is no dispute with respect to the respective rates of pay the various claimants actually received. This data will be discussed as part of the computation of the basic pay due each worker, below. VII.Computation Of The Amount Due Each Claimant A. The Method Of Computation In view of the fraud and inaccuracy inherent in the pay records obtained from Dial, and the refusal by Milnor to produce its own pay records, we are left to compute claimants' back wages without those documents. Under these circumstances, Milnor's contention that the Secretary has failed to prove the amounts due by a preponderance of the evidence and that the Secretary's demands constitute only a "guesstimate" (Tr. 648-651) must be recognized as being [13] ~14 [14] without merit. Where a contractor's records are inaccurate and unreliable, as Dial's are, or unavailable, as Milnor's are, the Supreme Court has held that an employee has carried out his burden if he proves that he has in fact performed work for which he was improperly compensated and if he produces sufficient evidence to show the amount and extent of that work as a matter of just and reasonable inference. The burden then shifts to the employer to come forward with evidence of the precise amount of work performed or with evidence to negative the reasonableness of the inference to be drawn from the employee's evidence. If the employer fails to produce such evidence, the court may then award damages to the employee, even though the result be only approximate. Anderson v. Mt. Clemens Pottery Co., 328 U.S. 680, 66 S.Ct. 1192 (1946). In Structural Services, WAB Case No. 82-13 June 22, 1983), the Wage Appeals Board explicitly reminded contractors of their obligation: The Board warns contractors and subcontractors who take on government contracts covered by Davis-Bacon and related acts that they should be aware that they must keep accurate records of wages, overtime and fringe benefits payments to their employees. Failure to keep such records will be at the contractor's or subcontractor's peril. Recordkeeping is the only method to substantiate the actual wages and fringe benefits paid laborers and mechanics. Without proper payroll records, the Wage and Hour compliance officers are compelled to invoke the criteria set forth in the Mt. Clemens case . . . . Id., slip op. at 8. This is similar to the rule followed in cases arising under the Fair Labor Standards Act. See Brock v. Norman Country Market, Inc., 835 F.2d 823, 828 (11th Cir. 1988); Brock v. Seto, 790 F.2d 1446, 1449 (9th Cir. 1986); Hodgson v. American Concrete Construction Co., Inc., 471 F.2d 1183, 1186 (6th Cir. 1973); Hodgson v. Humphries, 454 F.2d 1279, 1282, 1283 (10th Cir. 1972). Accordingly, in the absence of the true and accurate payroll records that it was the obligation of the contractor and subcontractor to furnish, I shall accept the reconstruction by the Department, using whatever evidence appears to be reliable toward that end, to the extent that it is reasonable. [14] ~15 [15] The period and hours during which the respective claimants are credited with working at the Lenox job site is derived from the claimants' testimony, confirmed to the extent possible by recourse to Dial's records and, further, by the recollection of at least two of the other workers that the claimant did work there. I find that this method the Department has used to calculate each claimant's hours is reasonable, under the circumstances of this case, and therefore I accept it. The mathematical formula for the computation in the case of each claimant will simply be (1) to determine, by deducting the rate actually paid from the rate that should have been paid, the rate of back wages due per hour he worked on the Lenox job, and (2) to determine the total amount due by multiplying the basic wages due per hour by the number of hours worked (plus creditable holidays not received). The rate that should have been paid is that fixed by the Wage Decision cited above: $19.50 (the basic hourly rate) + $5.69 (29.2% of $19.50) + $.50 ($4.00 / the 8 hours of a working day) = $25.69. B. Rosario Fernandez Rosario Fernandez worked for Dial at Lenox from the third week of August to the first week of October, in 1984, a period of 7 weeks. Tr. 385. He then worked at Park Rock, but he returned to Lenox the first week of December and worked there for 10 weeks until his departure in February of 1985. Ibid.; Exh. P-23. His total time worked at Lenox was thus 17 40-hour weeks, or 680 hours. Tr. 383-385. His hourly pay was $7.50, and he received no fringe benefits or paid holidays. Tr. 386, 388; Exhs. P-26, P-5. The hourly underpayment in his case was $18.19 ($25.69 - $ 7.50) and the total underpayment for the whole 680 hours was $12,369.20. In addition he was entitled to pay for four holidays, that he did not receive, for an additional deficit of $822.08 ($25.69 x 8 x 4). Exh. P-26. The total due Rosario Fernandez is thus $13,191.28. C. Winston Foy Winston Foy appeared on the Dial payroll from February 18 through May 31 in 1985, a total of 15 weeks. The Dial record shows that he worked 540 hours during that time, and was paid at the rate of $10.75 an hour. Exh. P-5; Tr. 15, 20-1. Foy's testimony and statement support this figure, and are uncontradicted that he was employed on the Lenox project. He was also due two holidays, for which in fact he was not paid, during that period. Accordingly, Foy is due a differential per hour of $14.94 ($25.69 - $10.75), and therefore a total of $8,067.60 for the 540 hours. The two unpaid [15] ~16 [16] holidays increase this amount by $411.04 ($25.69 x 8 x 2), to make a total sum due Winston Foy of $8,478.64. D. Solomon Glantz Solomon Glantz worked at Lenox from February 15 to May 31 in 1985, a total of 16 weeks. He worked for 15 weeks at 40 hours and one week at 32 hours, a total of 632 hours. He was paid at the rate of $8.00 per hour. Tr. 236; Exhs. P-7, P-5. Thus the total amount of underpayment due him for the days he worked amounts to $11,180.08 ($17.69 [$ 25.69 - $ 8.00] x 632). In addition, Glantz did not receive two paid holidays that were due him, for which we must add $411.04 ($25.69 x 8 x 2), for a total due Solomon Glantz of $11,591.12. E. Ilya Illish Illish was the Dial foreman at Lenox Road. He worked on that project from June 7, 1984 until June 14, 1985. Tr. 115, 148. He was paid $11.00 an hour until August 31, 1984, then $11.50 until October 12, and then $12.50 until the end of his tenure. Tr. 116; Exhs. P-16, P-5. Of this total of 55 weeks, he was assigned to the Park Rock project for the 13 weeks from November 2, 1984 through January of 1985, a period not involved here. See Exh. P-20. I therefore credit Illish with 42 work weeks at 40 hours a week, making a total of 1,680 hours. The Department has reasonably taken this claimant's pay to have been an average of $11.50 per hour, making a difference from the $25.69 Davis-Bacon requirement of $14.19, which for the whole 1,680 hours makes a total underpayment of $23,839.20. The compliance officer properly credited him with a credit of $540.15 for fringe benefits actually received, so that the total basic pay due Ilya Illish amounts to $23,299.05. Exh. P-26. F. Antonio Irizarry Antonio Irizarry worked on the Lenox project from "February" to mid-May of 1985. Tr. 210. I credit him from the middle of February, the 15th, to May 17th, a total of 13 weeks. He was paid at the rate of $8.25 per hour, and received no fringe benefits. Tr. 207-10; Exhs. P-21, P-5. His 13 weeks of work make a total of 520 hours. The underpayment in his case being $17.44 ($25.69 - $8.25), the total back wages due him for these 520 hours is $9,068.80. Exh. P-26. G. Patrick Lopez Respondent Milnor has moved (Tr. 512) that Lopez' entire claim be disallowed, because he himself did not appear to testify at the hearing, and the only evidence in the record with respect to his alleged underpayment is a statement taken by an employee of the Department of Labor who also did not testify. Exh. P-25; Tr. 448. Thus Milnor had no opportunity for cross-examination. [16] ~17 [17] This argument overlooks the fact that the reason why this lack of better documentation exists is the Contractor's failure to enforce and the Subcontractor's failure to obtain the accurate books and records required by law and by this contract. For this reason I am authorized to accept the Department's reasonable reconstruction of the amount due Lopez as back wages, even though it be entirely based on out-of-court statements. See Structural Services, supra, and Glen Electric Co., Inc., WAB Case No. 79-2 (1983). Milnor's motion is therefore denied. Lopez worked at Lenox from the middle of August in 1984 to the end of February in 1985, a total of 28 workweeks or 1,120 hours. He was paid $11.00 an hour, with no fringe benefits. Exh. P-25, P-5. The hourly underpayment in his case was $14.69 ($25.69 - $11.00), so that his accumulated back pay adds up to $16,452.80 ($14.69 x 1,120). In addition, Dial failed to pay him for five paid holidays, which results in an additional underpayment of $1,027.60 ($25.69 x 8 x 5). Thus the total amount of back wages due Patrick Lopez is $17,480.40. H. Michael Reale Michael Reale kept a calendar record of his work, and that calendar, Exh. P-19, is probably the most accurate and reliable record in this case (once one realizes that the October and December sheets have exchanged places). Reale worked at Lenox from August 15, 1984 to January 26, 1985, a total of 23.5 weeks. Tr. 172-173; Exhs. P-18, P-19. Of these weeks, he was paid during 11.5 (430.5 hours) at $7.00 an hour and during 12 (450.5 hours) at $8.00. Thus he suffered an underpayment of $18.69 ($25.69 - $7.00) per hour for 430.5 hours, a total of $7,615.55, and an underpayment of $17.69 ($25.69 - $8.00) per hour for 450.5 hours, totalling $7,969.35, the sum of the two amounting to $15,584.90. In addition, Reale was entitled to three paid holidays, that he did not receive, a deficit of $616.56 ($25.69 x 8 x 3). Exh. P-26. Michael Reale is, accordingly, entitled to a total back pay of $16,201.45. I. Joseph Solla Joseph Solla was a high-school senior who worked for Dial at Lenox on a half-day (four hours) basis from October 12, 1984 through February 22, 1985, five days a week during the 1984 months and two to four days in 1985. Tr. 356, 363; Exh. P-5. While he testified that he often arrived a half-hour early and worked through without taking any time for lunch, he could not say how often this occurred and acknowledged that he had been hired to work four hours and he was paid for four. Tr. 356, 363. Therefore I credit him with 13 twenty-hour [17] ~18 [18] work weeks from October through December 22 in 1984, a total of 260 hours. Taking two and a half days (10 hours) as his average work week at Lenox during the eight weeks he worked in 1985, I credit him with 80 additional hours, for a total of 340. Solla did perform other work for Dial than that of an electrician. He performed such services as driving a truck and delivering materials, as well as working on the job itself. See Addendum of February 28, 1986 to written statement of Rosario Fernandez, Exh. P-24, p. 2. He failed to mention that fact, and the record does not disclose what proportion of his time was spent in these other duties, but half seems to me a fair and reasonable proportion in the case of a high school senior on an electrical job. Solla received $4.00 an hour, and no fringe benefits, for his work (Tr. 355; Exh. P-5), and I will apply the deficit of $21.69 ($25.69 - $4.00) to 170 hours as being for his work as an electrician. This calculates to an underpayment of $3,687.30. In addition, he should have received three paid holidays (12 hours), one-half of which consists of 6 hours, for which he is entitled to an additional $154.14 ($25.69 x 6). Thus I find that Joseph Solla is entitled ta payment now of $3,841.44. J. Herme Valle Herme Valle worked for Dial during the period from December 1984 into March 1985. Tr. 529-30. There being no way to fix specific dates for the beginning and ending of his work at Lenox, I credit him with half each of the first and last months (i. e., from December 16,1984 to March 15,1985, a total of 13 weeks). Valle did not work only at Lenox, however, but divided his time between that project and the Park Rock job nearby. Valle estimated that he worked at Lenox an average of 25 hours a week -- four to eight hours on three or four days a week. Tr. 532. In the absence of the more exact data that we should have from the contractor's side, there is no reason for me not to accept the claimant's estimate. Valle received pay at the rate of $5.00 per hour on the Lenox site (Exh. P-30), making an underpayment for Davis-Bacon purposes of $20.69 ($25.69 - $5.00). Working 13 weeks at an average of 25 hours each, he has a total of 325 hours, for which the underpayment comes to $6,724.25 ($20.69 x 325). Adding in one unpaid holiday for which he was entitled to be paid, we apply the 25/40 proportion of the holiday (5 hours) for which he is reasonably entitled to Davis-Bacon pay under his working arrangement at Lenox, to credit him with an additional $128.45 ($25.69 x 5). I therefore find that Herme Valle is entitled to payment of $6,852.70. [18] ~19 [19] ORDER For the reasons stated above, it is ORDERED, pursuant to the United States Housing Act of 1937, as amended, and the Davis-Bacon Act, as amended, as provided under section 5.12(b) of Title 29, Code of Federal Regulations: 1. That the following companies and individuals be, and they hereby are, debarred and ineligible to receive any contracts or subcontracts subject to any of the statutes listed in Section 5.1 of Title 29, Code of Federal Regulations, for a period of three years from the date of publication by the Comptroller General of their names on the ineligible list: Dial Electric Contracting Co., Inc. Herman Rosenblatt 2. a. That Dial Electric Contracting Co., Inc. and Milnor Construction Corp. are jointly and severally liable and shall pay the unpaid prevailing wages and fringe benefits due the following named employees in the individual amounts appearing beside their respective names and totalling $110,044.88. This total sum is to be paid to the United States Department of Labor. The respective names and amounts due are as follows: Rosario Fernandez $13,191.28 Winston Foy 8,478.64 Solomon Glantz 11,591.12 Ilya Illish 23,299.05 Antonio Irizarry 9,068.80 Patrick Lopez 17,480.40 Michael Reale 16,201.45 Joseph Solla 3,841.44 Herme Valle 6,852.70 $110,004.88 [19] ~20 [20] b. And if any of those named persons refuses to accept those funds or cannot be found, then that person's share shall be deposited into the Treasury of the United States as miscellaneous receipts. c. The New York City Housing Authority shall release, to the Wage and Hour Division of the United States Department of Labor, any funds it has withheld under Contract NO. NY36-P005-292. [3]. The balance of the monies being withheld under that contract shall be paid to the Contractor under the contract. Aaron Silverman Administrative Law Judge Dated: April 30, 1991 Washington, D. C. AS:SBG:gbs ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ NOTICE OF RIGHT TO APPEAL. Pursuant to the applicable regulations, which appear in Section 6.29 of Title 29, Code of Federal Regulations, any interested person may appeal, within 40 days after receipt of this decision, by filing exceptions thereto. The original statement of such exceptions must be filed with the Wage Appeals Board, Frances Perkins Building, 200 Constitution Avenue, N. W., Washington, D. C. 20210, and a copy must be sent to the Chief Administrative Law Judge, United States Department of Labor, 1111 20th Street, N.W., Washington, D.C. 20036. [20]



Phone Numbers