skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

USDOL v. RUST CONSTRUCTION CO. INC., 1985-DBA-23 (ALJ Feb. 18, 1987)


CCASE: DOL V. RUST CONSTRUCTION CO. DDATE: 19870218 TTEXT: ~1 [1] [87-15.WAB ATTACHMENT] U. S. Department of Labor Office of Administrative Law Judges 304A U.S. Post Office and Courthouse Cincinnati, Ohio 45202 (513) 684-3252 DATE: February 18, 1987 CASE NO. 85-DBA-23 IN THE MATTER OF Proposed debarment for labor standards violations by: UNITED STATES DEPARTMENT OF LABOR, Complainant, v. RUST CONSTRUCTION CO., INC. Contractor JERRY RUST, President, SANDRA RUST, Vice-President, Respondents. With respect to laborers and mechanics employed by the contractor under Environmental Protection Agency Contract No. C290835, Sewer System Construction, Dixon, Missouri APPEARANCES: Robert S. Bass, Esquire, Eliehue Brunson, Esquire For the complainant Ross A. Friedman, Esquire For the respondents BEFORE: Donald W. Mosser Administrative Law Judge DECISION AND ORDER This proceeding arises pursuant to an Order of Reference filed by the Administrator, Wage and Hour Division, Employment Standards Administration, alleging the respondents violated the [1] ~2 [2] Federal Water Pollution Control Act, [hereinafter FWPCA], 33 U.S.C. Section 1372, by failing to pay the prevailing wage to its employees at the time the wages were due, failing to maintain required payroll records, and submitting inaccurate certified payrolls. The prevailing wage is mandated by the Davis-Bacon Act, 40 U.S.C. Section 276, and applied to other labor statutes through Reorganization Plan No. 14 of 1950, 5 U.S.C. Section 903 and 29 C.F.R. Section 5.1. The Order further alleges a violation of the Contract Work Hours and Safety Standards Act [hereinafter CWHSSA], 40 U.S.C. Section 327 et seq., which sets standards for payment for overtime work on federal contracts. The Order of Reference indicates that these violations of the Rust Construction Company are "aggravated and willful" within the meaning of 29 C.F.R Section 5.12 [hereinafter cited by Section number only] and therefore the Rust Construction Company and Gerard Rust and Sandra Rust, its president and vice-president, respectively, and owners, should be debarred from bidding on government or government-sponsored contracts. By certified mail dated April 12, 1984, the respondents were advised by the Administrator, Wage and Hour Division, of the findings of the specific violations and the conclusion that the violations were aggravated and willful within the meaning of Section 5.12(a)(1) of the regulations. Respondents were further advised of their right to request a hearing within 30 days. Respondents, by letter dated May 11, 1984, requested a hearing and asserted that there were mitigating circumstances that would make debarment inequitable. As noted above, the Order of Reference was then filed on September 27, 1984, and this case was transferred to the Office of Administrative Law Judges for a formal hearing. A hearing was held on June 11, 1986, in St. Louis, Missouri, at which time the parties were given full opportunity to present evidence. Both parties also submitted post-hearing briefs. ISSUE Whether Rust Construction Company, its president, Gerard Rust, and its vice-president, Sandra Rust, should be placed on the ineligible list for receiving federal government contracts for a period not exceeding three years because of willful and aggravated violations of the Davis-Bacon and related Acts. FINDINGS OF FACT The following facts essentially are not in dispute: 1. Rust Construction Company, Inc. [hereinafter Rust] is a small family contracting business located in Warrenton, Missouri. [2] ~3 [3] It principally specialized in the construction of residential homes, sewers and water lines. Rust's principal stockholders and executive officers during the times pertinent to this case were Gerard Rust, its president, and vice-president, Sandra Rust. 2. On May 5, 1982, Rust entered into Contract No. C290835 with the City of Dixon, Missouri. The contract provided for payment of the $170,649.66 to Rust for the construction of a new scepter sewer and water main to Dixon's new treatment plant. The contract was subject to the Davis-Bacon Act and the other federal statutes hereinafter referred to. It also was subject to a so-called "wage decision" which was incorporated into the contract and which had been published in a 1981 volume of the Federal Register. 3. Rust's work on the contract began around August of 1982 and was completed in the following summer. All of the work was performed in Pulaski County, Missouri, which is approximately 100 miles from Rust's office in Warrenton, Missouri. 4. After the project had been completed, a compliance officer of the Wage and Hour Division of the United States Department of Labor conducted a labor standards investigation of Rust's performance under its contract with Dixon. The compliance officer concluded from his investigation that Rust had committed certain violations of the labor standard provisions of the Federal Water Pollution Control Act, the Contract Work Hours and Safety Standards Act, and the regulations found in 29 C.F.R. Part 5. These violations included Rust's failure to pay its employees the applicable prevailing wage rates in accordance with the wage decision of the contract, as well as the required rates for overtime. The compliance officer also determined the corporation had committed violations by submitting unsigned certified payrolls which contained inaccurate and incomplete information and that these records also failed to list payroll information regarding two of Rust's employees. Rust also failed to retain all of the payroll records that are required by the pertinent regulations. 5. The respondents cooperated during the compliance officer's investigation and did not dispute his findings. As agreed with the U.S. Department of Labor, Rust paid back wages and overtime as computed by the compliance officer totalling $11,865.06 and $3,127.03, respectively. 6. The Order of Reference involved in this case was issued to the respondents on September 27, 1984. The complainant charged in this document that the above described violations of the respondents were aggravated and willful, and that the respondents should be placed on the ineligible bidders list and debarred from doing business with the federal government as a contractor for a period not to exceed three years. [3] ~4 [4] At the hearing before me, Jerry Rust credibly testified, and I so find, that during the time pertinent to this case he was responsible for determining which of the prevailing wage figures in the contract were to apply to Rust's employees; that the wrong wage classifications were used in computing Rust's employees' wages because he used the wrong page of the wage decision in the contract; that he computed overtime for Rust's employees according to a practice commonly used by contractors in that area of Missouri, rather than in accordance with the contract that his wife was responsible for the preparation of the certified weekly payrolls under the contract; and, that he did not know that he was supposed to sign the payrolls. Sandra Rust credibly testified at the hearing, and I so find, that during the time pertinent to this case she was responsible for managing Rust's office and preparing its payrolls with the assistance of a part-time employee; that she obtained the hours used in computing the weekly payrolls by telephone from one of the workers at the construction site; that she obtained the applicable wage rates and overtime computation from Mr. Rust; that she usually prepared the certified weekly payrolls to be submitted under the contract to the City of Dixon, although she did not fully understand how to accurately complete all of the information required on the payrolls; that she was advised by personnel of the City of Dixon to just complete those portions of the certified weekly payrolls that she understood; that she did not know that the certified weekly payrolls had to be signed; and that she did not realize there were any problems with respect to those weekly certified payrolls until the compliance officer commenced his investigation. Rust's contract with the City of Dixon apparently was the respondents['] first experience with a construction project related to a federal contract. Rust's only other experience with a government contract was investigated by the state of Missouri and no problems were reported concerning Rust's handling of that project. Conclusions of Law The Department of Labor Regulations at 29 C.F.R. Section 5.6(b)(1) provide: Whenever any contractor or subcontractor is found by the Secretary of Labor ... to be in aggravated or willful violation of the labor standards provisions of any of the applicable statutes ... such contractor or subcontractor or any firm, corporation, partnership or association in which such contractor or subcontractor has a substantial interest shall be ineligible for a period not to exceed 3 [4] ~5 [5] years ... to receive any contracts or subcontracts subject to any of the statutes listed in (Section) 5.1. Since respondent, Rust Construction, has conceded that statutory violations exist, the only question remaining is whether the violations were "aggravated and willful", thereby making debarment an appropriate penalty. The complainant argues the officers of Rust Construction knew when they signed the contract involved in this case that they were required to follow the labor standards contained in the contract. Since they failed to do so, their actions are argued to be "aggravated and willful." Complainant contends that intent can be inferred from actions and that falsified payrolls, omission of employees from payroll records, failure to keep accurate records, and failure to pay correct prevailing wages and overtime in effect speak for themselves. Complainant cites several Wage Appeals Board cases in support of its position. These cases, however, are distinguishable from the facts of this case since in each of them the actions of the contractor indicated an intent to defraud its employees for the company's personal gain. Such violations go to the heart of the Davis-Bacon legislation. See Matter of Marvin Hirchert, [1978-1981 Transfer Binder] Lab. L. Rep. (CCH) [par] 31,353 (Wage Appeals Bd., Oct. 16, 1978); Matter of Ace Contracting, [1978-1981 Transfer Binder] Lab. L. Rep. (CCH) [par] 31,357 (Wage Appeals Bd., May 30, 1980); and Thomas Moore, [1978-1981 Transfer Binder] Lab. L. Rep. (CCH) [par] 31,351 (Wage Appeals Bd., Nov. 28, 1979). Moreover, in all of the cases, the contractors were precluded from relying on an unfamiliarity with the regulations because of a long history of work on federal contracts. In the Hirchert case, the company had previous violations and in Moore, the contractor actually falsified employee statements to indicate the employees had been paid the correct wages. One of the cases cited by the complainant involved a contractor that made repeated errors even after the violations were called to its attention . In Re Bone, 23 Wage & Hour Cas. (BNA) 896 (Wage Appeals Bd., June 7, 1978). In another, the contractor refused to make restitution after the violations had been established. General Comptroller's Decision, [2 Wages-Hours] Lab. L. Rep. (CCH) [par] 31,365 (Wage Appeals Bd., March 25, 1981). Rust Construction argues that the decisions in two analogous Service Contract Act cases should be followed. Federal Food Service v. Donovan, 658 F.2d 830 (D.C. Cir. 1981); Mastercraft Flooring v. Donovan, 589 F. Supp. 258 (D.D.C. 1984). In both of these cases, the Courts applied the following multi-part test to determine whether a contractor found to be in violation of Department of Labor regulations should be debarred: [5] ~6 [6] 1. whether contractor had a prior history of violations; 2. whether current violations were serious or extensive; 3. whether the violations were willful or the circumstances showed there was culpable neglect to ascertain whether certain practices were in compliance; 4. whether the respondent's liability turned on bona fide legal issues of doubtful certainty; 5. whether the contractor cooperated with the investigation; and, 6. whether the contractor paid all amounts due to the employees promptly. These criteria indicate that an analysis of whether debarment is appropriate concerns the extent to which the contractor manifested a subjective intent to defraud employees of wage rights that the statutes were designed to protect. Decisions under Davis-Bacon related statutes have provided conclusions similar to the conclusions of these Service Contract Act decisions. In Tilo Company, Inc., [1973-1978 Transfer Binder] Lab. L. Rep. (CCH) [par] 31,114 (Wage Appeals Bd., June 6, 1971), debarment was not imposed where the government inexcusably delayed informing Tilo that there was reasonable cause for debarment, where the company reorganized its procedures for handling government contracts and where subsequent compliance was evident. In Steingass Mechanical Contracting, 83 DBA 47 (June 28, 1985), a plumbing company was found to be in violation of regulations when it improperly classified the temporary summer help and incorrectly calculated payment for overtime work. The judge found in deciding that case that debarment was inappropriate where: ... the Respondent had no prior Government contracting experience; there was complete cooperation with the investigating officials at all times; the Respondent undertook to ensure compliance with the regulations after being made aware of the violations; an agreement to pay back wages was promptly entered into and paid in accordance with the payment schedule worked out between the parties; and the Respondent had entered into substantial Government contracting in the five years subsequent to [these] projects with no other violations. . . . See also Paul Vitale Excavating, 83-DBA-61 (April 30, 1986); Morris Excavating Company, 85-DBA-58 (August 29, 1986); McAndrews Company, 86-DBA-44 (October 3, 1986). [6] ~7 [7] The factual pattern in the instant case is closer to the Mastercraft and Steingass cases than to the cases cited by the Department of Labor. It is clear from the record that Rust Construction had no prior history of Davis-Bacon or CWHSSA violations. The officers cooperated fully in the investigation and promptly paid the sums which were found owing to Rust's employees. There is no evidence of a purposeful intent to profit under this contract at the expense of the employees' wage rights, nor is there evidence that the Rusts intentionally failed to ascertain whether their practices were in compliance with the regulations. The purpose of the Davis-Bacon legislation is to make sure that government funds are not spent on projects where workers would be exploited by being deprived of a fair wage for their work. Perkins v. Lukens Steel Co., 310 U.S. 113, 128 (1940); Endicott Johnson Corporation v. Perkins, 317 U.S. 501, 507 (1943) and S. Rep. No. 798, 89th Cong., 1st Sess. reprinted in 1965 U.S. Code Cong. and Adm. News, 1965, pp. 3737-3739. As in the Steingass case, I find that Rust's statutory violations clearly were due to inexperience and "not out of a pre-conceived intent to defraud." Mr. and Mrs. Rust apparently were overwhelmed with the complexity of the contract that they had signed on behalf of Rust and were incapable at that time of meeting its requirements. To debar under the facts of this case, I find, would serve no constructive purpose. In conclusion, I find the complainant has failed to demonstrate that the violations of Gerard Rust, Sandra Rust or Rust Construction Company were either willful or aggravated. Moreover, I find there existed circumstances mitigating the seriousness of their violations of the Davis-Bacon and related acts. I therefore reject the complainant's prayer for debarment. ORDER IT IS HEREBY ORDERED that the complainant's request to place Rust Construction Company, Inc., and its officers, Jerry Rust and Sandra Rust, on the ineligible bidders list from doing business with federal government as a contractor or sub-contractor for a period not to exceed three years is denied on the grounds the evidence in this case fails to support the allegations that their violations of the Davis-Bacon and related acts were aggravated or willful. DONALD W. MOSSER, ADMINISTRATIVE LAW JUDGE [7]



Phone Numbers