skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

LANCE LOVE, INC., WAB Case No. 88-32 (Mar. 28, 1991)


CCASE: LANCE LOVE, INC. DDATE: 19910328 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of: LANCE LOVE, INC., WAB Case No. 88-32 Prime Contractor and LANCE LOVE, President BEFORE: Charles E. Shearer, Jr., Chairman Ruth E. Peters, Member Patrick J. O'Brien, Member DATED: March 28, 1991 DECISION OF THE WAGE APPEALS BOARD This matter is before the Wage Appeals Board on the petition of Lance Love, Inc. and Mr. Lance Love (hereinafter, "Love" or "Petitioner"), seeking partial reversal of the erudite Decision and Order of Administrative Law Judge ("ALJ") Rudolf L. Jansen dated May 11, 1988. That Decision and Order found Love in violation of the Davis-Bacon Act, 40 U.S.C. 276a et seq. and the Contract Work Hours and Safety Standards Act ("CWHSSA"), 40 U.S.C. 327 [1] ~2 [2] et seq. The petition questions ALJ Jansen's Decision and Order only with respect to back wages owed five employees and does not contest Love's debarment or other findings and conclusions. The Board regards as abandoned all remaining wage violation and debarment issues. For the reasons contained herein, the Wage Appeals Board affirms the attached Decision and Order in its entirety. I. BACKGROUND Lance Love, Inc. of Indianapolis, Indiana, was engaged in the sale and installation of floor coverings. On June 4, 1982, Love entered into a contract to replace and/or install floor covering at Fort Benjamin Harrison. The contract contained the standard Davis-Bacon, CWHSSA, and Copeland Act provisions. For reasons not apparent from the record, Love bid and received the contract for $47,179.00 despite a government estimate of nearly twice that amount. Furthermore, the contract was open-ended, and delivery orders against it eventually totalled in excess of $250,000. On April 21, 1982, the government sent a "possible mistake-in-bid" notice to Love which called their attention to the contract's wage rate requirements. Love's contract sales manager responded by stating that their bid was firm and had contemplated the prevailing wage requirements. A subsequent Wage and Hour investigation found that employees had been paid a piece-rate for their efforts, that fifteen employees had been underpaid by some $31,000, and that Love had falsified payrolls. Love challenges ALJ Jansen's Decision and Order only with respect to five employees: two are alleged to be a subcontracting partnership; two are contested because of ex-post calculations regarding relationships between the required wage rate and hypothetical projections based on the piece-rate actually employed; and the fifth is contested because he testified that he felt he was paid the required rate. None of these contentions has any merit. II. DISCUSSION Petitioner contends that Albert Weir and Harry K. Phillips were not "laborers" or "mechanics" within the meaning of the Davis-Bacon Act. Love contends that these two were an entity, not employees. It is, however, undisputed the two worked on the project by removing old floorings and installing new ones. Section 1(a) of the Davis-Bacon Act applies a functional rather than a formalistic test to determine coverage: if someone works on a project covered by the Act and performs tasks contemplated by the Act, that person is covered by the Act, regardless of any label or lack thereof. See N.B.A. Enterprises, Ltd., WAB Case No. 88-16 (February 22, 1991). A review of the record and [2] ~3 [3] applicable law leads to the inescapable conclusion that Messrs. Weir and Phillips were functional employees, and that ALJ Jansen correctly determined back wages with regard to them. Love further contends that ALJ Jansen erred with regard to back wage computations for Ron Adams and Larry Johnson, and offers an extrapolation based upon a piece rate. Furthermore, Love concedes that it falsified its payroll. Our review of the record finds ALJ Jansen's application of the principles enunciated in Anderson v. Mt. Clemens Pottery Company, 328 U.S. 680 (1946) correct, fully consistent with Board precedent as discussed in Apollo Mechanical, WAB Case No. 90-42 (March 11, 1991), and based upon his personal evaluation of the credibility of the witnesses before him. In short, there is no legal or factual reason to disturb ALJ Jansen's Decision and Order in this respect. Petitioner argues that Gary Greever should not receive a back wage award because he testified that he believed he was paid the required prevailing wage. The Board is pleased to enhance Mr. Greever's contentment, as an employee cannot make an agreement in derogation of his statutory rights to the correct compensation. See Harlow Restoration Corp., WAB Case No. 81-14 (May 11, 1983). For the foregoing reasons, ALJ Jansen's Decision and Order is affirmed in its entirety. BY ORDER OF THE BOARD: Charles E. Shearer, Jr., Chairman Ruth E. Peters, Member Patrick J. O'Brien, Member _____________________________ Gerald F. Krizan, Esq. Executive Secretary [3]



Phone Numbers