Dec. 29, 2005
King County awards first Brightwater construction contract
$131 million contract includes construction of 14,000-foot-long tunnel
2005 Archived News
King County Executive Ron Sims today announced the signing of the
first construction project contract for the $1.4 billion Brightwater
wastewater treatment plant.
Kenny/Shea/Traylor, A Joint Venture of Wheeling, Ill., has been
awarded a $131 million contract to build the east segment of Brightwater
treatment plant's conveyance system -- a 14,000-foot-long tunnel
from the North Creek Business Park in Bothell to the plant site
at the intersection of State Route 9 and State Route 522 north of
Woodinville.
"Awarding the contract today is a milestone in this vital
project," Sims said. "Brightwater will protect public
health and the environment for the next generation while providing
infrastructure needed for economic growth. The new facilities will
be good neighbors during both construction and operation, and we
will ensure that Brightwater is built to strict environmental standards."
Kenny/Shea/Traylor is expected to begin construction on the conveyance
system early next spring. A special tunnel-boring machine will be
used to create a tunnel approximately 18 feet in diameter to depths
of up to 260 feet below the surface.
The scope of work also includes excavating a 74-foot-deep shaft
that will be used to launch the tunnel-boring machine, installing
four pipes in the tunnel ranging from 27 inches to 84 inches in
diameter, and installing three fiber-optic cables to monitor Brightwater
facilities. The tunnel will be backfilled filled with concrete after
the pipes and cables are installed.
The contractor will also dig a smaller, 2,400-foot-long microtunnel
from the North Creek tunnel shaft to the existing North Creek Pump
Station, and excavate an 83-foot-deep double shaft for a new Brightwater
system pump station that will be built under a separate contract.
The work is part of the $1.4 billion Brightwater project to build
a treatment plant, 13-mile conveyance pipeline, and a marine outfall
north of Seattle by 2010. King County will advertise two more tunneling
contracts in 2006. Total construction cost for the wastewater conveyance
system is an estimated $705 million.
This contract was advertised in July 2005 under a competitive
procurement process conducted by King County. Kenny/Shea/Traylor
was the low bidder among six firms that submitted bids in October.
Bid results are posted on the Web at www.metrokc.gov/procurement/rfp_rfq_itb/awarded.aspx
A bid evaluation team comprised of representatives from the design
team, the construction management team, and the project manager,
conducted a thorough review of Kenny/Shea/Traylor's qualifications
before awarding the contract. The County has already selected Jacobs
Civil to provide construction management services for the conveyance
facilities. MWH/Jacobs Associates is designing the system as a joint
venture.
Kenny/Shea/Traylor, A Joint Venture has extensive experience on
tunnel and underground construction projects, most recently the
North Outfall Sewer and the East Central Interceptor Sewer for the
City of Los Angeles.
Formerly known as Metro, the wastewater-treatment utility now
operated by King County has been preventing water pollution for
40 years. The regional clean-water agency serves 17 cities, 17 local
sewer utilities and more than 1.4 million residents in King, Snohomish
and Pierce counties.