ADVANTAGES
OF THE SPLIT INTERSECTION
by Joe G. Bared and Evangelos I. Kaisar
This article is adapted
from a paper presented by the authors at the 79th Annual Meeting of the Transportation
Research Board in January 2000 in Washington, D.C.
As urban and suburban intersections
become more congested, a possible remedy to the recurring traffic jam is to
separate the grades of the intersecting roads in the form of a diamond interchanges.
A more economical intersection treatment is the split intersection. This treatment
requires that the major road be separated into two one-way roads comparable
to an at-grade diamond junction. The split intersection facilitates smoother
traffic flows with less delay, and safety should be improved by reducing congestion
and separating the opposing directions of traffic.
Background and Application
Intersections, by their nature, easily become traffic bottlenecks and conflict
areas, but the capacity of an interchange with full access control is more than
twice that of an at-grade intersection.
For some conditions in the United States, the level of service at intersections
can be improved by applying a split intersection. It is applicable as a permanent
treatment or as a transitional phase before the construction of a grade-separated
diamond interchange, when required by heavy traffic.
The split intersection is currently an uncommon solution to a busy intersection.
It separates traffic flow on the mainline into offset one-way roads. (See figures
1 and 2.) This layout is comparable to a diamond at-grade interchange without
the bypassing through traffic.
|
Figure
2 - Typical split intersection (with possible median U-turn). |
By separating the mainline
traffic flow, substantial delays are reduced, and a few potential conflicts
are eliminated. When the two signals are timed correctly (preferably by a single
controller), the separation facilitates smoother and less interrupted flows
at higher volumes. Most of the reduction in delay is derived from eliminating
one of the four traffic-signal phases of the single intersection. Effectively,
this adds more "green time" to the cycle for left-turning vehicles
by reducing initial perception reaction time, startup time, and all "red
time."
The three major disadvantages of a split intersection, as cited by Hakkert and
Ben Yakov and by Polus and Cohen, are the high initial cost of construction
and of right-of-way purchases, the likelihood of stopping at two intersections
instead of one when the two signals are not well-coordinated, and the possible
wrong-way movements by unfamiliar drivers.1,2
Polus and Cohen document the advantages of split intersections, showing an increase
in capacity and a reduction in delay. Figure 3 illustrates a constant increase
in through capacity for the split when left-turning volumes rise because the
increasing left-turning volume requires more green time. For a cycle length
of 120 seconds and at the highest level of turning volume, capacity is about
35 percent higher than for a single intersection.
Figure 4 seems to show an excessively high reduction in delay as a function
of the through volume. Although a savings of 700 seconds per vehicle of stop
delay seems to be unreasonably high, the assumptions used are not completely
stated to evaluate the validity of these results.
A split intersection separates potential conflict points and slightly reduces
their locations compared with the traditional four-legged intersection.3 (See
figure 5.) Hakkert and Mahalel derived a regression equation relating accidents
to conflict points. The equation explains 60 percent of the variation, which
is more than most accident prediction models that relate accidents to highway
factors.
It is possible that the separation of conflicts combined with a reduction in
the number of signal phases will have a positive safety effect. At every transition
between phases, drivers are more likely to violate the traffic signal than they
would during a steady stream of trafffic when the light is green. More research
is necessary in this area or in the area of surrogate or exposure safety measures
in traffic microsimulation.
The split intersection is primarily considered in an isolated and congested
suburban intersection expected to experience traffic growth with particularly
high left-turning volumes. It could be considered as a transition to a grade-separated
diamond interchange with a bridge on the through roadway.1 Access management
may be reduced within the wider boundaries of this special treatment.
Further treatment is possible by providing U-turns for the left-turning vehicles
to reduce the number of signal phases to two. This treatment will eliminate
the need for storage on the cross-street. Nevertheless, high left-turning traffic
will face other conflicts when crossing through lanes on the major highway.
|
Figure 3 - Increase
in capacity of through movement after split. (Polus) |
A busy suburban intersection
in Tel Aviv, Israel, was converted to a split intersection in 1975. According
to Hakkert and Ben Yakov, the economic benefits have been proven by the reduction
of delay and the postponement of the construction of a complete grade-separated
interchange.1 Delay calculations showed noticeable savings for the split intersection
compared to the single intersection. (See table 1.) According to anecdotal accounts,
other split intersections were constructed in Israel and were since converted
to diamond grade-separated interchanges.
Another application of the split intersection is possible in urban areas where
two-way streets can be converted to one-way streets if the offset between the
two streets is adequate.
The authors of this article conducted a delay comparison between single and
split intersections using a traffic microsimulation model - CORSIM (CORridor
SIMulation) - to provide insight into the benefits of conversion.
Analysis Methodology
Single and split intersections are modeled in CORSIM Version 4.3 with identical
geometric dimensions for the length of the approaches and turning lanes (right
and left turns) and the same number of through lanes.
CORSIM provides comprehensive capabilities, including traffic operational analysis,
geometric design/traffic operational evaluation, and assessment of mitigation
strategies under congested conditions. PASSER II-90 is a program developed by
the Texas Transportation Institute (TTI) to evaluate and determine optimal signalization
strategies for an arterial signal system to reduce delays, stops, and fuel consumption.
It is equally capable of analyzing single, isolated intersections. PASSER III-90
is also a program developed by TTI to evaluate existing or proposed signalization
strategies for diamond interchanges and to determine strategies that minimize
the average delay per vehicle.
The first simulated case is for a four-lane major highway (north-south) with
a 40-mile per hour (64-kilometer per hour) posted speed intersecting a four-lane
highway with a 45-mi/h (72-km/h) posted speed. A constant left-turning percentage
of 15 percent is assumed on all four approaches. The split intersection has
an offset of 200 feet (61 meters) between the two separated intersections. The
researchers selected various scenarios of entering volumes on all approaches
to cover many possible flow conditions (e.g., equal flows on all approaches
and some imbalanced flows). More scenarios with imbalanced flows might necessitate
a longer offset than the modeled distances of 200 feet (61 meters) and 300 feet
(91 meters). At each approach, the length of the left-turn lane is 350 feet
(107 meters).
The second simulated case is similar to the first, but it assumes a 30-percent
left-turning volume on all four approaches and the split intersection is offset
by 300 feet (91 meters). For the second case, each approach is designed with
dual left-turn lanes that are 450 feet (137 meters) long. Both cases are assigned
10-percent right-turning traffic with 250-foot (76-meter) right-turn lanes.
Moreover, both cases are modeled with 5-percent truck traffic on all approaches.
Although signal timing (cycle length and phase split) is not the objective of
this research, it is necessary to determine an optimal signal plan to evaluate
the effectiveness of the intersection configuration. For a single intersection,
PASSER II is used to help determine the best signal timing for cycle lengths
ranging from 60 to 120 seconds with 10-second increments. When undersaturated
conditions are analyzed, the run with the smallest delay is selected for cycle
length and phase timing. In saturated/oversaturated conditions, PASSER II does
not compute accurate delays.4 Nevertheless, phase timing is still reliable.
When various cycle lengths are applied in CORSIM for saturated/oversaturated
conditions, longer cycle durations yield a lower delay for single intersections.
The four-phase arrangement used in modeling is shown in figure 6 with exclusive
left turns and no overlap.
For the split intersection, PASSER III is used to help determine cycle length
(ranging from 60 to 120 seconds), optimum phase timing, and time offset between
the two signals. PASSER III minimizes intersection delay for undersaturated
conditions only, similar to PASSER II. Nevertheless, phase timing and offset
are reliable in saturated/oversaturated conditions. Conversely, for saturated/oversaturated
conditions, shorter cycle lengths provided shorter delays according to CORSIM.
The split intersection is controlled by three-phase signals that are coordinated
according to five sequences. A best left-turn sequence or phase order is provided
by PASSER III in conjunction with the interval offset. Both programs use deterministic
approaches in analyzing and optimizing signal timing without accounting accurately
for individual vehicle performance (e.g., acceleration/deceleration, lane changing).
Therefore, the desired signal timing could possibly be slightly improved.5
Then, for each traffic flow scenario, pertinent data from the two PASSER programs
are separately input into CORSIM to model the single and split intersections
for 15 minutes. Results are verified and recorded for each scenario using various
cycle lengths.
Although CORSIM is capable of modeling oversaturated traffic conditions, a peculiar
behavior is noted at very high flows with 30-percent left-turning traffic. At
the latter part of the simulation period, gridlock develops, preventing left-turning
traffic within the offset highway section from moving because of a spill-back
into both intersections.6 In practice, this could be prevented by stopping the
vehicles on red when the offset section is saturated and by designing a little
longer offset when growth is anticipated. The most significant variables affecting
delay are the length of the offset section, the signal coordination for the
split intersection, and the length of the left-turn lanes for both types of
intersections.
Results
The CORSIM analyses show that the split intersection accommodates higher volumes
of traffic with less delay per vehicle than the single intersection. The delay
differential between the two types of intersections increases as entering and
left-turning volumes rise. (See figures 7 and 8.) As stated earlier, the reductions
in delay are derived from eliminating one phase for the split intersection,
thus increasing the percentage of effective green time. Although at higher volumes
the optimal cycle length for the split intersection was shorter than for the
single intersection, the additional proportion of effective green time yielded
significant delay reductions when through and left-turning traffic move concurrently.
An exponential form from Microsoft Excel is selected to fit the scatter of the
CORSIM data. This displays an approximation of the model performance. No statistical
analysis was conducted to determine a best model or an evaluation of goodness-of-fit
of the data to a mathematical equation. A visual evaluation of figures 7 and
8 shows reasonable fit for most points below 7,000 vehicles per hour (vph).
Figures 7 and 8 reveal gradual, then noticeable, reductions in travel delay
for the split intersection starting at a total entering flow of 4,000 vph. Average
delays for single and split intersections are comparable between 1,600 vph (smallest
simulated flow) and 4,000 vph. In comparison to the computed delays shown in
table 1, these simulated results yield approximately a 40-percent to 50-percent
reduction in travel delay at higher volumes (5,000 to 6,000 vph total entering
flows) with 15-percent left-turning traffic. For 30-percent left-turning traffic,
the reduction in delay ranges from 50 percent to 60 percent for the same range
of total entering flows.
A simple economic analysis provides very encouraging documentation of the substantial
benefits of the split intersection. The computed results in figures 9 and 10
show the extent of savings per year in vehicle-hours and in equivalent costs
for two selected peak flows. The following assumptions were used in the computations:
- Four hours of peak periods
per day (h).
- Peak period occurs on
more than 250 working days per year.
- Nationwide average occupancy
factor of 1.6 passengers per vehicle (p).
- Recommended hourly value
of travel-time savings per person-hour of $12.70 (c).
The occupancy factor and
the hourly cost of delay are given in an FHWA memorandum (April 1997) on "Departmental
Guidance for the Valuation of Travel Time in Economic Analysis." It has
been adjusted from 1995 to 1998 dollars using the consumer price index. This
factor applies to all vehicles, including buses and vans.
Economic Benefits
A case study presents an economic analysis procedure for planning purposes.
A single intersection is converted to a split intersection to serve the traffic
demand for the next 10 years. After 10 years, a bridge will be required on the
major highway over the crossroad to meet the growing traffic volumes. The split
intersection is thus converted to a diamond interchange with the separated roadway
serving as on and off ramps from the major highway. Although the assumed costs
are reasonable, users should apply local estimates that meet their specific
project needs. Some constraints are observed because of a broad variability
and a limitation in the scope. The impact on adjacent properties is considered
to be comparable to any other necessary improvement alternative. An isolated
site does not require signal progression. Pedestrian and bicycle traffic is
very rare.
Net benefits are expressed in present worth of the yearly savings minus the
initial costs of right-of-way, construction, and signal. Estimated peak flow
over the first five years is 5,000 vph, and a flow of 6,000 vph is assumed for
the following five years. Equivalent cost-savings per year are provided in figure
10 and converted to the present with a rate of return of 0.06. Assumed costs
are as follows:
- Land cost for 15-percent
left-turning volumes (200-ft offset) ($16/ft2): $3,200,000
- Land cost for 30-percent
left-turning volumes (300-ft offset): $4,800,000
- Construction cost for
pavements and drainage: $ 583,000
- Signal cost: $ 80,000
The net present benefits
are illustrated in figure 11. For the 15-percent left-turning volumes, a net
benefit is derived after seven years. A net benefit for the 30-percent left-turning
volumes kicks in after six years.
Additional savings are derived from postponing the bridge construction over
the crossroad for several years. An estimated cost of embankment and pavement
for extending and raising the mainline to the bridge is $1,021,000. The bridge
cost is estimated at $928,000. Figure 12 displays the resulting present worth
savings that could be derived by delaying the bridge construction for five to
10 years.
Conclusions and Recommendations
Split intersections are well-suited to alleviate traffic congestion of single
intersections in isolated suburban areas where the total approaching volume
is greater than 4,000 vph. They can possibly be used along an arterial with
signal progression when the arterial signal synchronization is compatible with
the optimal signal timing of the split intersection. Moreover, their application
is feasible in urban areas when streets are converted to one-way traffic with
adequate available offset.
For high peak flows and higher left-turning traffic, the economic benefits are
noticeable. These benefits can easily justify the conversion of a split intersection
over its economic life. The split intersection provides noticeable economic
benefits in postponing the construction of the bridge for a grade-separated
diamond interchange until traffic growth requires it.
The length of the split intersection offset and the number and length of left-turn
lanes in conjunction with well-coordinated signals are crucial to a smooth and
economical operation that yields the derived savings.
A well-designed and coordinated signal timing should rely on accurate estimates
and forecasts of flows on all approaches of the split intersection.
In the case of highly oversaturated conditions, the spill-back of left-turning
traffic along the east-west highway blocking the intersections could be prevented
by designing longer offsets between the two intersections and/or controlling
left-turning traffic on the crossroad.
Although this study applies only to fixed signal timing, actuated timing could
provide smooth and efficient operation for off-peak flow. More analysis is needed
to investigate actuated signal timing for various scenarios. Additional research
is also needed to evaluate the effectiveness of the split intersection along
an arterial progression.
For specific applications, it is recommended that a detailed comparison process
similar to this study be applied rather than simply relying on the derived fitted
comparison of figures 7 and 8.
Ideally, a field study is recommended to validate the simulated findings. However,
this is unlikely because (according to the literature) very few intersections
in the world have been converted to two split intersections. Besides the two
case conditions that are discussed in this article, other cases could likewise
be simulated in CORSIM with differing traffic volume and roadway cross-section
scenarios.
References
- S. Hakkert and Y. Ben
Yakov. "Single-Level Interchange or Splitting a Signalized Intersection,"
Traffic Engineering and Control, Aug./Sept. 1978.
- A. Polus and R. Cohen.
"Operational Impact of Split Intersections," Transportation Research
Record, No. 1579, Washington, D.C., 1997.
- S. Hakkert and Y. Mahalel.
"Estimating the Number of Accidents at Intersections: Single-Level Interchange
or Splitting a Signalized Intersection," Traffic Engineering and Control,
Aug./Sept. 1978.
- PASSER II-90, User's
Guide, Methodology for Optimizing Signal Timing: M|O|S|T, Volume 3, Federal
Highway Administration, Washington, D.C., 1991.
- PASSER III-90, User's
Manual and Application Guide, Texas Transportation Institute, Texas A&M
University, College Station, Texas, 1991.
- Traffic Software Integrated
System (TSIS) User's Guide, Version 4.02, Federal Highway Administration,
Washington, D.C., 1998.
- A Policy of Geometric
Design of Highways and Streets, American Association of State Highway and
Transportation Officials (AASHTO), Washington, D.C., 1994.
- Highway Capacity Manual,
Special Report 206, Transportation Research Board, Washington, D.C., 1998.
Joe G. Bared is a
highway research engineer in the Office of Research and Development, Federal
Highway Administration. He manages research contracts and conducts staff research
in the areas of safety and operational effects of design. He has a doctorate
in transportation engineering from the University of Maryland, and he is a registered
professional engineer.
Evangelos I. Kaisar
is a doctoral student at the University of Maryland. He is conducting research
in the field of operations research and its application to transportation engineering.
He is also doing research for the Federal Highway Administration in the areas
of safety and the operational effects of design. He has a bachelor's degree
and a master's degree in civil engineering from the University of Maryland,
and he has a bachelor's degree from the Technical University of Athens in Greece.
He is a registered professional engineer in Greece.
Articles & Departments The First Issue of Public Roads
IDAS Integrates ITS Into Planning Process
Turbo Architecture
Communities of Practice
Middle School Students Design Future Cities
The Partnership Initiative
An Australian Road Review
Advantages of the Split Intersection
One Mile in Five: Debunking the Myth
National Transportation Week
Annual Index
|