Hanford Site
Tri-Party Agreement Change Requests
1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
|
|
REQUEST |
APPROVAL DATE |
CHANGE REQUEST TITLE |
M-45-04-05 |
01/10/2005 |
Extension of due dates for Hanford Federal Facility Agreement and Consent Order (HFFACO) Milestones M-45-03C and M-45-05A to June 30, 2005, M-45-13 and M-45-15 to March 31, 2006, and M-45-13-T01 and M-45-15-T01 to March 31, 2007 |
M-16-05-01 |
03/15/2005 |
Modify the description for TPA Interim Milestone M-016-68 (300-FF-5 OU) |
M-62-04-01 |
03/21/2005 |
Extension of due dates for Hanford Federal Facility Agreement and Consent Order (HFFACO) milestones M-62-08 AND M-62-11 to allow for collection of sufficient waste form performance data from the Demonstration Bulk Vtrification System to support completion of the Hanford Tank Waste Supplemental Treatment Technologies Report and Draft Hanford Tank Wasate Treatment Baseline. |
M-16-04-09 |
04/01/2005 |
Establish Tri-Party Agreement Interim Milestones for sampling to support 100/300 Area Component of River Corridor Baseline Rsk Assessment. |
M-45-04-04 |
04/14/2005 |
Extention of due date for Hanford Federal Facility Agreement and Consent Order milestone M-045-00C to initiate negotiation of SST waste retrieval and closure activities and associated schedules no later than September 30, 2006. |
M-92-05-01 |
05/31/2005 |
Hanford Site sodium disposition evaluation report interim milestone M-92-10 due date modification. |
M-81-05-01 |
06/06/2005 |
Hanford Site final sodium disposition evaluation report target date M-81-10-T01 due date modification. |
M-48-05-01 |
06/15/2005 |
Modify Hanford Federal Facility Agreement And Consent Order (HFFACO) Milestone M-48-14 by deleting paragraph (e)(3) which requires examination of tank bottoms via accessible air slots. This change also provides clarification of DST Ultrasonic Weld Inspection Methods and Terminology required by the M-48 Milestone Series. |
M-24-05-01 |
06/28/2005 |
Groundwater Protection, Monitoring and Remediation Well Installation Priority List for CY 2005 - CY 2008 and Modify Tri-Party Agreement Interim Milestone M-024-57. |
M-45-05-02 |
06/29/2005 |
Modification of Hanford Federal Facility Agreement and Consent Order (HFFACO) Milestones M-45-05A and M-45-05N-T01. |
M-48-05-02 |
06/29/2005 |
Modify Hanford Federal Facility Agreement and Consent Order Milestone series M-48 by adding a new interim milestone M-48-07A to complete construction of the condensate and pit upgrades. |
M-20-05-01 |
07/26/2005 |
Delay Hanford Federal Facility Agreement and Consent Order (Agreement) Interim Milestones M-020-33 and M-020-39 in conjunction with Agreement Change Request M-15-05-02. |
M-15-05-02 |
07/26/2005 |
Delay Hanford Federal Facility Agreement and Consent Order (Agreement) M-015 Interim Milestones. |
M-45-05-01 |
08/01/2005 |
Modification of Hanford Federal Facility Agreement and consent Order (HFFACO) Milestones M-45-05A, M-45-15, and (M-45-13); and deletion of M-45-13-T01, M-45-15-T01, and M-45-05N-T01. |
M-45-05-03 |
12/14/2005 |
Change C-103 Waste Retrieval Start Date |
|