Appendix 1: PDUFA 3 Meeting Performance Goals
Meeting Type |
Target Date |
Type A |
Should occur within 30 calendar days of receipt of request |
Type B |
Should occur within 60 calendar days of receipt of request |
Type C |
Should occur within 75 calendar days of receipt of request |