Tennessee NPL/NPL Caliber Cleanup Site Summaries
U.S. DOE Oak Ridge ReservationEPA ID: TN1890090003
Location: Oak Ridge, Anderson County, Tennessee
Congressional District: 03
NPL Status: Proposed: 07/14/89; Final 11/21/89
Project Manager
Documents:
- Site Profile
- Additional Site Documents including Five Year Reviews, Records of Decisions (ROD) and Explanation of Significant Differences (ESD).
- For documents not available on the website, please contact the Region 4 Freedom of Information Office (http://www.epa.gov/region4/foiapgs/submit.htm).
Site Background:
The Oak Ridge Reservation site, a U.S. Department of Energy (DOE) facility,
covers 37,000 acres and includes 294 on-site contaminated areas and off-site
surface waters including Poplar Creek, the Clinch River and lower Watts
Bar Reservoir of the Tennessee River. The site consists of three large
industrial facilities: the Oak Ridge National Laboratory or X-10, a research
facility that includes nuclear reactors and ongoing energy, chemical,
and biological programs; the former K-25 Site, now known as the East
Tennessee Technology Park (ETTP), a former production facility that enriched
uranium-235 by gaseous diffusion; and the Y-12 Plant, a production facility
that formerly enriched uranium-235 by an electromagnetic process, and
currently disassembles nuclear weapon components, processes nuclear materials,
and performs other functions that relate to energy and national defense
programs. Site operations generated a variety of radioactive, non-radioactive,
and mixed (radioactive and non-radioactive) hazardous wastes, most of
which were containerized and buried below ground or stored in buildings
on site. Leakage from buried waste areas and former-processing facilities
has contaminated on-site and off-site soils, surface water, sediments,
and groundwater. Site related contaminants above levels of concern could
be found in sediment, water, and biota of Popular Creek. The State has
advised against consuming fish and coming into contact with water from
Poplar Creek, which flows to the Clinch River and ultimately to the Tennessee
River. An estimated 43,200 people obtain water from surface water intakes
on the Tennessee River along a 118-mile stretch downstream from the site.
Cleanup Progress: Construction Underway and Completed
Cleanup Progress: DOE commenced initial cleanup activities under a RCRA permit
in 1986. The facility was later listed on the NPL, and DOE, EPA, and State of
Tennessee enter a Federal Facility Agreement (FFA). Since that time, DOE has
initiated approximately 50 response actions under the FFA that address contamination
and disposal issues.
1. Lower East Fork Poplar Creek - A remedial action was conducted to remove mercury-contaminated
sediments in the flood plains area. Physical work was completed in November 1997.
The remedial action report was issued and approved in 1998.
2. United Nuclear Corporation Landfill - In 1995, remedial action to construct
a multi-layer cap and institute monitoring was completed.
3. Mercury Sumps - In 1994, remedial action was completed to remove mercury (Hg)
contaminated materials to prevent transport to the surface water system.
4. K-1407-B and K-1407-C Ponds - A RCRA action was conducted to remove and stabilize
contaminated sediments. A cap was later installed as part of a remedial action
to address residual radioactive contaminants. The action was completed in 1995.
5. Drum Storage Yard - In 1995 a RCRA action/remedial action was completed to
stabilize, repackage, and off-site disposal of sediments from the B&C Ponds
project.
6. White Wing Scrap Yard - A remedial action was completed in 1994 to remove
and dispose of contaminated scrap material to prevent further contamination of
soils and allow for future subsurface investigations.
7. Cesium Plots Research Facility - A remedial action was completed in 1994 to
remove and dispose of cesium-137 contaminated soils from a research area adjacent
to the Clinch River.
8. K-1070 SW-31 - A remedial action was completed in 1994 to intercept and treat
groundwater contaminated with VOCs prior to discharge to the surface water system. The
system is expected to be terminated in 2007 because due to a decrease of contaminant
levels in the discharge.
9. Clinch River and Poplar Creek - A remedial action imposed institutional controls
that restrict dredging of creek sediments and consumption of fish and turtles
contaminated with Hg and PCBs. The remedial action report was approved in November
1997.
10. Lower Watts Bar Reservoir - A remedial action was completed in August 1997
to impose institutional controls that restrict dredging of creek sediments and
the consumption of fish and turtles contaminated with mercury and PCBs.
11. South Campus Facility - A remedial action was completed in 1996 to impose
a deed notification for shallow groundwater contamination and periodic monitoring.
No other actions were required.
12. Union Valley Groundwater - An interim remedial action was completed in July
1997 that imposed institutional controls that restrict groundwater use. The remedy
also provided for license agreements with private property owners to allow for
continued access for future investigations or actions.
13. Filled Coal Ash Pond, McCoy Bridge - A remedial action was conducted to stabilize
the dam holding contaminated pond sediments in place. A wetland, removed during
stabilization activities, was re-constructed as part of the remedial action.
Physical work was completed in March 1997. The remedial action report was approved
in May 1997.
14. Bear Creek Rust Spoil Area - A remedial action was completed in January 1997
that imposed institutional controls to maintain existing soil cover and prevent
waste intrusion.
15. Nitric Acid Pipeline - A No Action Record of Decision (ROD) was issued in
1994.
16. Plating Shop Container Area - A No Action ROD was issued in 1992.
17. Kerr Hollow Quarry - A No Further Action ROD was issued for this former hazardous
waste treatment area in 1995.
18. White Oak Creek Embayment - A removal action was completed in 1992 to install
a sediment retention structure to preclude the migration of contaminated sediments
from the White Oak Creek system into the Clinch River.
19. Solid Waste Storage Area (SWSA) 4 - A removal action was completed in January
1997 to solidify trenches, through low pressure grouting, releasing high levels
of strontium (Sr-90) into the White Oak Creek system.
20. Molten Salt Reactor Experiment Facility - A removal action was completed
in August 1997 to remove the build-up of reactive and uranium gases from the
facility’s piping system. Actions were also taken to minimize the possibility
of a criticality event.
21. Molten Salt Reactor Experiment Facility - A removal action was completed
in 2002 to remove a significant deposit of fissile uranium from an auxiliary
charcoal filter outside of the facility’s primary containment boundary.
A remedial action to remove the fuel and flush salts is currently underway. Because
of technical and budgetary issues, a fixed completion date is currently unavailable.
22. ORNL Corehole 8 - A removal action was completed in 1995 to intercept and
treat groundwater contaminated with Sr-90 prior to discharge into the White Oak
Creek system.
23. ORNL Corehole 8 - A removal action was completed in 2001 to remediate the
source of the Sr-90 contamination to the Corehole 8 groundwater plume. However,
Trans-Uranic (TRU) waste was discovered during the removal. Because the cost
of handling and disposing of TRU waste is significantly higher than that of the
material that was expected during this project, the contractor performing the
removal was unable to address the TRU waste and had to leave it in place. The
TRU waste will be addressed in a later action.
24. SWSA 5 - A removal action was completed in 1995 to intercept and treat two
of the most significant sources of Sr-90 into the White Oak Creek system.
25. Alpha 4 Building - A removal action was completed in December 1997 that removed
inactive outdoor piping systems contaminated with mercury. Approximately 2,300
lbs. of elemental Hg was recovered for recycling purposes.
26. K-1401 and K-1420 Sumps - A removal action was completed in 1998 to collect
and treat shallow groundwater contaminated with VOCs.
27. K-1070 C/D Mitchell Branch - A removal action was completed in 1998 to collect
and treat shallow groundwater contaminated with VOCs. Although a collection and
treatment system was installed, the system did not perform at optimum levels.
DOE terminated the ineffective removal action and is deferring further response
on groundwater to the final remedial action decision scheduled for 2007.
28. K-901-A and K1007-P1 Ponds - A removal action was undertaken in 1999 to stabilize
ponds contaminated primarily with PCBs. A non-time critical removal action
has been accepted as the remedial alternative for the K-1007-P1 Holding Pond. DOE
is intending to implement an ecological enhancement innovative technology to
remove PCB contamination from fish receptors. This action should eventually
eliminate all risk from PCB’s to the pond ecosystem. The Action Memorandum
was approved March 20, 2007.
29. Firing Range Soils - A removal action was completed in 1999 to remove sediments
contaminated with lead.
30. Old Hydrofracture Tanks - A removal action was completed in 2001 to remove
sludge contaminated with approximately 30,000 curies of fission products and
transuranics and transfer the materials to an active doubly contained storage
facility for further treatment.
31. Waste Evaporator Facility - A removal action was completed in December 1996
to demolish this inactive contaminated facility.
32. Building 3001 Canal - A removal action was completed in September 1997 to
eliminate the source of on-going releases of radionuclides to the groundwater
system.
33. Buildings K-29, 31&33 - A removal action was initiated November
1997 to recycle uranium and other metals from the building’s uranium enrichment
process equipment, remove contaminated equipment and decontaminate building surfaces
at these three large buildings located at the East Tennessee Technology Park.
The DOE contractor implementing the removal action is the British Nuclear Fuels
Limited (BNFL) company. The removal action did not fully attain the cleanup
objectives in the Removal Engineering Evaluation/Cost Analysis and Action Memorandum. DOE
determined that attainment of these decontamination goals would be contingent
upon future re-use potential. DOE completed demolition of the K-29 building
in 2007 because its re-use potential was limited. DOE has deferred a final
decision on whether to further decontaminate the remaining buildings or begin
full building demolition.
34. ORNL Gunite Tanks - A remedial action was being conducted to remove water
and sludges containing over 30,000 curies of transuranic and fission product
material. That action is now complete.
35. ORNL Inactive Tanks - A removal action to remediate 10 to 12 inactive tanks
that contain radioactive waste has been completed. These tanks posed less of
a risk than the Gunite Tanks at ORNL.
36. East End Volatile Organic Plume- A removal action was approved in 1999 to
contain the existing volatile organic plume at the Y-12 fence line through pump
and treat actions. Construction on the project began in early 2000. Construction
was completed in June 2006 and the treatment remains operational.
37. Bear Creek Valley- A Record of Decision (ROD) was signed in early 2000 for
the Boneyard/Burnyard S-3 pathway 3 areas of the valley. Following are the actions
being implemented under this ROD:
a. Construction of the french drain was completed in 2000.
b. The remainder of construction on the Boneyard/Burnyard site was completed
in 2003. This action included the excavation of 57,000 cubic yards of contaminated
soil, capping of the remaining soil and site restoration activities. The contaminated
soil was disposed of at EMWMF CERCLA Waste Cell.
c. The removal and disposal of the wastes stored at the Oil Landfarm was completed
in July 2001.
d. The remaining two activities under this ROD, the S3 Pathway 3 and the DARA
pad, will be completed in the future. In the meantime, the removal action
for the S3 Pathways 1 and 2 has been terminated because it was ineffective.
38. K-1070-A Burial Ground - A one acre site that consisted of 26 unlined trenches
and 62 circular unlined pits. The Record of Decision was signed January 13, 2000
to remove the source material. Excavation was tied directly with the opening
of the on-site EMWMF CERCLA Waste Cell and began in June 2002. All remedial action
activities were completed in June 2003. Approximately 16,684 cubic yards of low-level
radioactive material was removed. A Remedial Action Report documenting the completion
of the response action was approved November 2003.
39. K-1070-C/D G-Pit and Concrete Pad - The concrete pad was covered with soil
and seeded. The contaminated soil, which contains some classified waste material,
has been excavated. The soils were treated in late 2001 using a low temperature
thermal desorption process. On-site disposal of the contaminated soils was completed;
however, some secondary waste material was disposed in the TSCA incinerator due
to radionuclide levels. A Remedial Action Report documenting the completion of
the response action was approved in October 2003.
40. Group I Buildings - Decontamination and demolition of five former process
buildings was initiated in 1997. Demolition of the K-724-Storage Building and
K-725 Beryllium Building was competed in 1998. Final disposition of all
waste was completed and the response action closed June 2006.
41. Group II Buildings/Phase I - Decontamination and demolition of seven former
process related buildings and associated structures began late fall 2000. All
buildings have been demolished. Due to the extent of fixed contamination, an
asphalt cap was placed on building K-1413 slab. A Removal Action Report documenting
the completion of the response action was approved in September 2004.
42. Group II Buildings, Phase II - Decontamination and Demolition of 18 minor
facilities began in March of 2004 as part of the K-1064 area D&D. A Removal
Action Report documenting the completion of the response action was approved
in June 2007.
43. Environmental Management Waste Management Facility (EMWMF) CERCLA Waste Cell
- On November 2, 1999, the ROD selected the preferred alternative for the disposal
of wastes that will result from future cleanups at the Oak Ridge Reservation
(ORR) under CERCLA was signed. The preferred alternative was the design, construction,
operation and closure of an onsite earthen disposal cell and supporting facilities
in East Bear Creek Valley. Two additional cells, adding 800,000 cubic yards in
capacity, have recently been completed and a third and final expansion design
has been approved.
44. Melton Valley- The ROD was signed in September 2000. This ROD selected a
number of different source control remedies for waste areas in Melton Valley.
The ultimate goals are to protect human health and to reduce the amount of contaminants
in White Oak Creek to acceptable levels. Following are the projects being implemented
under this ROD:
a. The D&D of the Old Hydrofracture Facility was completed in September 2006.
b. A number of monitor wells that are no longer in use have been plugged and
abandoned. This action was completed in July 2006.
c. The Intermediate Holding Pond (IHP) cleanup has been completed. This project
involved the excavation and removal of 14,000 cubic yards of contaminated soil.
The soil was disposed of in the EMWMF. The capping and hydraulic isolation of
SWSA 4 has been completed.
d. The D&D of the New Hydrofracture Facility was completed in July 2006.
e. The D&D of the Small Facilities at SWSA 4 was completed in February 2003.
f. The construction for the hydraulic isolation projects for SWSA 4, SWSA 5,
SWSA 6, and the hydraulic isolation at the Pits and Trenches Area have been completed. The
completions are, respectively, September 2006, October 2006, August 2006 and
September 2006.
g. An Explanation of Significant Differences was signed by the three FFA agencies
in 2004 adding Tumulus I, Tumulus II and the Interim Waste Management Facility
to the SWSA 6 hydraulic isolation remedy.
h. The Soils and Sediment project was completed in September 2006.
i. The HRE Ancillary Facilities D&D was completed in September 2006.
j. The 22 TRU trenches project has been completed. This consisted of excavating
the buried casks containing TRU waste and transporting them to the onsite Foster
Wheeler plant for eventual disposition at WIPP. This action was authorized
under a State Consent Order, not under CERCLA.
k. A ROD amendment was signed November 2004 to change the selected remedy
for Trenches 5 and 7 (in the Seepage Pits and Trenches Area) from in-situ vitrification
to in-situ grouting.
l. An Explanation of Significant Differences was signed November 2004 to add
additional units to the remedial action approved in the Interim ROD.
m. An Explanation of Significant Difference was signed in 2005 to remove the
MSRE Ancillary Buildings from the scope of the interim ROD. Instead, these
buildings will undergo D&D at the same time as the MSRE itself.
n. An Explanation of Significant Difference was signed in 2007 to remove the
Shielded Transfer Tanks from the scope of the interim ROD. Instead, these
tanks will be addressed under NEPA.
45. Bethel Valley - The ROD was negotiated between the EPA, TDEC and DOE during
2001 and signed in May 2002. This ROD selected a number of different source control
remedies for waste areas in Bethel Valley. The major actions are the decontamination
and decommissioning of a number of buildings, capping of buried wastes, removal
of contaminated soils, addressing of contaminated tanks and pipelines, and addressing
areas of contaminated groundwater. The ultimate goals are to protect human health
and to reduce the amount of contaminants in White Oak Creek to acceptable levels.
Following are the projects being implemented under this ROD:
a. Field work has been completed in support of the Engineering Study Work Plan
for Groundwater Actions. This plan was approved in 2006. Remedial
actions will not be implemented until completion of the remaining accelerated
cleanup response actions Therefore, response actions required by the ROD will
not be implemented prior to 2009.
b. The remedial action at the T1, T2 and HFIR tanks has been completed. The
response included emptying the contents of the three tanks for offsite disposal
and grouting the tanks in place.
46. The Upper East Fork Poplar Creek (UEFPC) - The ROD was negotiated between
the EPA, TDEC and DOE during 2001 and signed in May 2002. This ROD selected a
number of different source control remedies to control the influx of mercury
from the Y-12 plant into UEFPC. The major actions are the hydraulic isolation
of contaminated soils in the West End Mercury Area (WEMA), the treatment of the
discharge of groundwater into UEFPC at Outfall 51 and the removal of contaminated
sediments from UEFPC and Lake Reality. The goal is to restore surface water in
UEFPC to human health recreational risk-based values at Station 17. Following
are the projects being implemented under this ROD:
a. The construction of the Big Springs Water Treatment Plant has been completed
and facility is operating as of August 2005.
b. The Phase 2 UEFPC Soils ROD was issued in April 2006. Remedial actions
will not be implemented until completion of the remaining accelerated cleanup
response actions. Therefore, response actions required by this ROD will
not be implemented prior to 2009.
47. K-25/K-27 Buildings - An engineering evaluation/cost analysis (EE/CA) was
prepared in 2001 for phased demolition of the buildings. Phase 1, characterization
and removal of hazardous buildings materials (primarily asbestos) began in February
2002 and the completion of this phase of the response action was documented in
an approved Phased Completion Report. Phases 2 and 3 apply to equipment
removal and building demolition, respectively, and have since been combined into
a single project. Equipment removal, disposal and demolition are currently scheduled
to be completed by 2009; however DOE has recently proposed to extend this work
to 2016. A Memorandum of Agreement regarding historic preservation has been signed
by the consulting parties. Demolition for the K-25 building is scheduled
to begin in early October 2008.
48. K-1085 Old Firehouse Burn Drum Burial Site- This is a time-critical removal
action to mitigate risks from buried drums and associated waste near the perimeter
fence of ETTP. Removal action at the site was completed in 2003 and most material
properly disposed. Residual material has been disposed and documented in
a completion letter. The action was completed December 2006. Additional
removal actions are underway to remove residual downgradient contaminated soil
detected during investigations to close out the Exposure Unit.
49. East Tennessee Technology Park, Zone 1 Interim Record of Decision - The ROD
was signed November 2002 to address selected sources in approximately 1400 acres.
Excavation is the selected remedy. Source areas include contaminated soils, buried
waste, and debris (scrap metal) outside the main plant area. The ROD requires
investigations of areas to address data insufficiency. A pilot was initiated
at the Blair Road Quarry in February 2004 to evaluate the Dynamic Verification
Strategy (DVS), a methodology which uses systematic planning, dynamic work plans,
and real-time measurements. Two Phased Construction Completion Reports
were approved in 2006 with approximately 988 acres now identified as meeting
the future industrial use classification. The remedy is expected to be complete
in 2009; however DOE has recently proposed to extend this work to 2016 as part
of the accelerated closure of ETTP. To date, approximately 1013 of the
estimated 1400 acres have been determined to meet the industrial use scenario.
50. East Tennessee Technology Park, Zone 2 - A ROD was signed April 2005 to address
approximately 800 acres located within the fenced security area. The scope
of the ROD requires investigations in areas to address data insufficiency, excavation
of the K-1070-B Classified Burial Ground, and allows disposal of concrete debris
and rubble within the footprint of the K-25 Building vaults. The remedy also
allows for concrete disposal, which meets the acceptance criteria, in other non-vault
areas following excavation. A Phased Construction Completion Report was
approved in 2007 with approximately 108 acres now identified as meeting the future
industrial use classification. Cleanup is expected to be complete in 2009;
however DOE has recently proposed to extend this work to 2016. To date,
approximately 252 of the estimated 800 acres have been determined to meet the
industrial use scenario.
51. Metals Recovery Building - The field work for this D&D removal action
has been completed. Final approval awaits disposition of TRU waste
from the project.
52. Surface Impoundments Operable Unit - The remedial action, which consisted
of excavation of the impoundments, stabilization and onsite disposal at the EMWMF,
was completed in May 2004.
53. ETTP Remaining Facilities - A Remaining Facilities Action Memo, generic
Standard Operating Protocol (Removal Action Work Plan), and Waste Handling Plan
was developed to address 508 facilities targeted for demolition before closure
of the East Tennessee Technology Park in 2008. These 508 facilities have been
divided into approximately 11 sub-projects. Each sub-project will have a project
specific Sampling and Analysis Plan and a Waste Handling Plan Part 2, in order
to fulfill CERCLA and FFA requirements, while accelerating clean-up. Waste Handling
Plans have been approved for Low Risk /Low Complexity facilities and buildings
K-29, K-1401, K-1420, and Centrifuge Equipment. Sub-projects are being
prioritized and implemented based on a schedule that takes into consideration
coordination with the Zone 1 and 2 Soils Remediation project, as well as risk,
logistics, funding, etc. Completion of all 11 sub-projects in targeted for 2009.
54. ETTP Site-wide Final Operable Unit – This ROD will address the groundwater
and surface water/sediment ecological receptor pathway across ETTP. Field and
laboratory work in support of the RI/FS Work Plan were completed in 2006. The
final RI/FS report has been placed on hold pending the outcome of a treatability
study designed to address DNAPLs in the subsurface. The final ROD for this operable
unit is currently scheduled for FY 2012.
55. Property Transfers are another mechanism by which DOE is accelerating site
closure while saving funds. Properties which DOE can show are protective for
the intended use may be transferred under a Covenant Deferral Request (CDR) which
allows DOE to transfer properties prior to completion of CERCLA remediation activities.
There are approximately 26 facilities at ETTP proposed for early transfer. Collectively
these 26 properties represent a potential cost savings of up to 99 million dollars
in O&M and D&D expenses. The first draft CDR was submitted to EPA and
TDEC for approval in early 2004. To date, three CDRs have been approved
and represent 6 buildings and approximately 18 acres of vacant property transferred.
EPA concurred on a Clean Parcel Determination (CPD) for an 18-acre parcel in
May 2008, and anticipates concurrence on a fourth parcel consisting of over 100
acres in the fall of 2008.
56. Low Level Legacy Wastes – An Action Memorandum (AM) was signed October
2003 to conduct a non-Time Critical Removal Action to dispose of 22,200 cubic
yards of accumulated (i.e., legacy) low level wastes stored in containers adjacent
to the K-33 Building at the East Tennessee Technology Park. The AM calls
for disposition of the waste in the on-site CERCLA waste landfill. DOE
completed the response action and submitted a Removal Action Completion Report
in 2005.
57. A time critical removal action is currently underway (Action Memo approved
12/20/07) to address the uncontrolled release of hexavalent chromium to Mitchell
Branch at the East Tennessee Technology Park. The groundwater collection system
will pump the contaminated groundwater to the Central Neutralization Facility
and greatly reduce and/or eliminate the ongoing release of hexavalent chromium
to the creek.
For information about the contents of this page please contact Donna Bledsoe