Agency for Toxic Substances and Disease Registry Search  |  Index  |  Home  |  Glossary  |  Contact Us  
 
Oak Ridge Reservation: Public Health Assessment Work Group

Public Health Assessment Work Group
Meeting Minutes
May 5, 2003

Attendance

ORRHES Members attending:
Bob Craig (Work Group Chair), Kowetha Davidson (Subgroup Chair), George Gartseff, David Johnson, James Lewis, Pete Malmquist, and LC Manley

Public Members attending:
Gordon Blaylock, Tim Joseph, and Roger Macklin

ATSDR Staff attending:
Paul Charp, Burt Cooper, Melissa Fish, Lorine Spencer (phone), and Bill Taylor

ERG Contractor:
Liz Munsen (phone)

Purpose

Bob Craig called the PHAWG meeting to order and attendance was noted for the record.

The purpose of the meeting was to (1) discuss the lessons learned and the effectiveness of the new process that provides input into the Public Health Assessment (PHA), and (2) present and discuss ATSDR’s preliminary assessment of radionuclides released from White Oak Creek.

Discussion of the Lessons Learned and the Effectiveness of the New Process to Provide Input into the PHA

Presenter: James Lewis, ORRHES

James Lewis wanted to review the new process for providing input into the PHA so that the PHAWG could identify any weaknesses that needed to be addressed. Mr. Lewis presented a copy of the process flow sheet that was developed for this effort, and walked the PHAWG through the steps to see what the group had done thus far. There were three major areas in the process: preliminary assessment, data validation, and public comment and final PHAs. Under the preliminary assessment, the PHAWG 1 meeting was held. During this meeting, ATSDR identified the list of references that would be used for the PHA. Mr. Lewis explained that he had reviewed the minutes from that meeting, and that the PHAWG had indicated that it wanted a press release, which would explain that ATSDR was preparing a PHA and to request any additional information from the public. These minutes, from the November 4, 2002, PHAWG meeting, indicated that the Communications and Outreach Work Group (COWG) was supposed to contact Cathy Daniels.

During the PHAWG 2 meeting, there was a presentation by ATSDR’s Federal Facilities Assessment Branch (FFAB). During this meeting, members requested information, including uranium data from other areas surrounding the Y-12 facility. There were issues raised in this area because there were elevated levels of uranium from Bear Creek. The PHAWG discussed using data from the Tennessee Department of Environment and Conservation (TDEC) and suggestions were made about presenting information to the public. James Lewis thought that the PHAWG should keep the public informed about its activities.

During the PHAWG 2 and PHAWG 3 meetings, there were roundtable discussions about some of the information that had been obtained. James Lewis thought that the minutes should be re-read and that key points should be pulled out and given to ATSDR.

James Lewis described the data validation part of the process. He said that to his knowledge, this was where ATSDR came and presented its draft PHA. Mr. Lewis noted that at that time, ATSDR failed to provide copies to the subcommittee. He believed that ATSDR had corrected the problem, but that as a general rule, the members of ORRHES should receive a copy of the document when the PHAWG members receive their copy.

James Lewis noted that some people needed different levels of detail. He suggested that the PHAWG have ATSDR’s Community Involvement Branch (CIB) generate a document to summarize the PHA for the “lay people.” Mr. Lewis thought that people needed an opportunity to provide their input, and that the PHAWG needed to evaluate the process so that this input could occur in a timely manner.

Discussion

Bob Craig asked James Lewis if he wanted the press release item added to the flow sheet. Mr. Lewis responded that Dr. Craig was correct.

Lorine Spencer wanted to clarify a point in James Lewis’ discussion. She asked where Mr. Lewis wanted to put the press release on the process sheet because ATSDR had prepared a press release for the Uranium PHA public comment release. Bob Craig explained that Mr. Lewis wanted a press release to occur much sooner in the process. Mr. Lewis said that Dr. Craig was correct.

Bob Craig disagreed with James Lewis. He said that the work group had a process for distributing the PHA and that the PHAWG definitely wanted to view the document before the ORRHES. He added that the PHAWG acted as an “author” in this process, by working with ATSDR before the document was given to the subcommittee. Dr. Craig said that if Mr. Lewis was proposing that ATSDR give the document to ORRHES before the PHAWG had time to review it, then he objected to this suggestion. Dr. Craig explained that there were one or two minor mistakes in the distribution of the document, but that he believed that it was only because the publishers had thought that certain people who were on the PHAWG were also on the ORRHES. He said that this was a bit of a problem, but that it was an administrative issue that could be handled. However, he gathered that Mr. Lewis wanted to incorporate the ORRHES into what Dr. Craig saw as the job of the PHAWG. He thought that it was the PHAWG’s responsibility to carry out the work for the ORRHES and to take care of the necessary details. Thus, Dr. Craig disagreed with Mr. Lewis if that was what he proposed.

James Lewis responded that he had taken this idea to the COWG to look at the distribution list and that he had prepared a matrix. He added that he needed to go back to review what the recommendation was with regards to this issue. However, Mr. Lewis’ main point was that he wanted the ORRHES to become familiar with the process. Bob Craig recalled that the publishers had thought that Don Creasia was on the PHAWG, but that he had never been a member of the work group. Thus, he did not receive the document until the day of the ORRHES meeting. Mr. Lewis said that he had surveyed the group and that, in his opinion, some ORRHES members may want the document during that part of the process. Dr. Craig said that they could be notified, but that the PHAWG’s job was to “do the work” because there was too much for the entire subcommittee to handle.

Bob Craig stated that everyone was invited to the meetings and that the meeting minutes were published. He did not know what more they could do to elicit public participation.

Kowetha Davidson wanted to know the issue involved in James Lewis’ discussion. Mr. Lewis stated that this had been discussed at the COWG meeting, and that the PHAWG was engaging in a general discussion to review the process. He said that they should look at possible failures in communication and any weaknesses in the process. Mr. Lewis added that he had heard that more than one member of the ORRHES did not receive the PHA in time. He looked at this process, along with the COWG, and prepared a matrix to alleviate another similar occurrence. He said that he would bring the matrix to a future meeting and that the PHAWG could vote on it.

Kowetha Davidson asked if the time provided to the ORRHES was insufficient. Bob Craig explained that to save on printing, the publishers had given the PHA to the PHAWG with plenty of time, and that the PHAWG had made its comments. People who were not members of the PHAWG were given the PHA five to six days ahead of time. One person was thought to have been on the PHAWG, but he was not. Thus, he did not receive the document before the meeting and he was unhappy about this.

Kowetha Davidson asked if there was a systematic problem with the distribution. Bob Craig replied that he did not think so. James Lewis said that they did not have an approach at that time. He added that they should not give people this type of document and only give them five days to review it, especially if those days fall over a weekend. Dr. Davidson noted that those members were given a cover letter that detailed which parts of the document to read; they were not supposed to read the entire document.

Bob Craig reiterated his point. The job of the PHAWG was to conduct the detailed, technical work. The PHAWG shouldered the responsibility for the subcommittee by reviewing the document and hoping that the ORRHES accepts the work group’s advice. The subcommittee members could review the document on their own, but the PHAWG had the main responsibility with regards to the document review. Dr. Craig thought that five days was plenty of time for the ORRHES to look at the document. James Lewis responded that they needed to think about this and mentioned Herman Cember as a person to keep in mind. He said that he would draw a timeline and would survey people to see what type of timeframe was desired. From his discussions with people, Mr. Lewis concluded that many members preferred at least 10 “working days” (not including the weekend) to review the document. Mr. Lewis added that he would present the COWG’s recommendation for consideration by the PHAWG. Dr. Craig commented that Dr. Cember was a member of the PHAWG and would have had plenty of time to review the document and to provide input. Mr. Lewis said that he would like to hear this from Dr. Cember and noted that he wished that Tony Malinauskas were here because he had synthesized all of the comments. Mr. Lewis thought that the PHAWG should make a “special effort” to give the document to the interested parties with enough time to provide comments. Dr. Craig looked forward to hearing the COWG’s recommendation.

Kowetha Davidson wanted to know if individuals had problems, and if so, what were the nature of the problems. She wanted these individuals to be sent to her. James Lewis stated that Dr. Davidson had given them a responsibility to evaluate the distribution strategy. Thus, they went back and developed a matrix, which was given to the CIB, and covered an approach to distributing all of these materials. They did not have a chance to present the matrix yet, but they would present it at a future meeting. Dr. Davidson made a correction. She said that she had referred to a distribution for the document that COWG was putting together, not for the PHA. She said that the COWG had discussed generating some documents and that she had asked for a distribution list for those COWG documents. Mr. Lewis said that he would go back and review the minutes, but that was not how they had interpreted her instructions. He added that they needed to focus on ensuring that the public received materials in a timely manner.

Minutes from the April 7, 2003, Meeting

Bob Craig asked the PHAWG for comments on the minutes. Gordon Blaylock noted the following corrections: (1) on page 20, third paragraph, the word “vapor” should be replaced with “three forms of mercury,” (2) on page 21, fourth paragraph, the “2003 Annual Report” should be replaced with the “Bechtel Jacobs 2003 Environmental Report,” (3) on page 25, third paragraph, the phrase should say that “if a lot of mercury is released to the environment by coal fire plants located in the vicinity,” and (4) on page 26, fourth paragraph, the word “level” should be replaced with the word “amount.”

Pete Malmquist made a motion to approve the minutes as corrected and David Johnson seconded the motion. The April 7, 2003, minutes were unanimously approved.

James Lewis asked if there were any action items in the body of the minutes. Bob Craig recalled that a letter was going to be written by the COWG and brought to the PHAWG. Dr. Craig had thought that the letter had been written because he prepared a first draft and sent the letter to Kowetha Davidson. Dr. Craig noted that Dr. Davidson re-worded the letter and made the document more “politically correct.” Dr. Craig thought that the resolution was that the COWG would draft the letter, but that he would write the first draft and give it to Dr. Davidson. Then, the letter would be sent to the COWG and the COWG would provide the letter to the PHAWG. Mr. Lewis had thought that the letter would start at the PHAWG, be sent to the COWG, brought back to the PHAWG, reviewed by the PHAWG, and presented to the ORRHES. At that time, if approved, the ORRHES would endorse the letter and send it out. Dr. Craig said that the final words at the last meeting were for Dr. Craig to prepare the first draft of the letter.

A meeting participant asked if the motion was read at the ORRHES meeting on April 8, 2003, but no one responded. James Lewis thought that the letter would be given to the PHAWG and then to the ORRHES. Bob Craig asked if the COWG was going to be involved in the process. Mr. Lewis thought that the COWG was no longer involved because he had performed the requested task. Pete Malmquist did not think that this letter went through the ORRHES. He said that the subcommittee had some problems with the way that the letter was written and that it was going to be re-drafted. Dr. Malmquist added that he did not think that the ORRHES knew what was mentioned in the letter, and that he did not think that the subcommittee had voted on anything. Dr. Craig thought that the ORRHES had eliminated the COWG from the process of generating this letter.

Presentation and Discussion of ATSDR’s Preliminary Assessment of Radionuclides Released from White Oak Creek

Presenter: Paul Charp, ATSDR

According to the project plan, Paul Charp was going to discuss (1) past releases from White Oak Creek, which was essentially the Task 4 Report of the state’s dose reconstruction project, and (2) current exposures from White Oak Creek, which ATSDR reviewed previously. During this meeting, Dr. Charp would review the Task 4 Report. Previously, ATSDR requested that three experts review this report; those comments would be distributed at a later date. Dr. Charp would discuss ATSDR’s review of current exposures (up to about 1996), give a summary of the Task 4 Report findings, and provide a summary of ATSDR’s review.

Slides Presented from the Task 4 Report

Paul Charp presented an overhead that showed all of the pathways that were evaluated in the Task 4 Report, as well as the recreational use of the river. The diagram showed pictures of a skier/swimmer, cattle, farmer, fisherman, hunter, and geese. The picture also identified the locations of White Oak Creek and White Oak Lake, and showed the Oak Ridge National Laboratory (ORNL, also known as X-10) as the source term. ATSDR went over the key issues that were covered in the Task 4 Report, which included contacting surface water and sediment during recreation, consuming game animals (the Task 4 Report looked at geese and fish), consuming fish and turtles, eating homegrown vegetables that grew along the Clinch River and where the Clinch River was used as a water source, and external radiation from materials that were present in the area of concern.

Paul Charp displayed an overhead that detailed the area of interest. The map showed the location of the X-10 complex, where White Oak Creek dumped into the Clinch River below Melton Hill, when it merged with the Tennessee River around Kingston, and then how it continued downstream to Spring City where the Watts Bar Dam was located.

Paul Charp explained that the beginning figures in his presentation were taken from the Task 4 Report. Dr. Charp presented a figure (Figure 5.2 in the Task 4 Report) that showed the significant events of waste management from X-10 starting around 1943, when construction began on the Clinton Laboratory, until 1960, when White Oak Dam was flooded and Trench 5 was completed. (On May 19, 2003, Gordon Blaylock noted that this comment was incorrect because White Oak Dam flooded in 1943.) The figure showed that there was about 16 to 17 years of burial material that was going into the burial grounds at X-10 or grounds associated with X-10. The figure also pointed out significant events, such as flooding and new pits that were built. Dr. Charp discussed the settling basin part of the figure that referred to its storage of 1.5 million gallons of waste. (On May 19, 2003, Gordon Blaylock stated that the term “settling basin” was out of context in this situation, and that this term should not be referred to until later on.)

Paul Charp presented another figure from the Task 4 Report that identified three reference populations based on fish consumption. This analysis was for people who lived along the Clinch River. Category I consisted of people who ate the most fish; these persons consumed an average of 1 to 2.5 meals per week on a regular basis. Category II was made up of persons who consumed 0.25 to 1.3 meals of fish per week. Category III was comprised of people who very rarely ate fish, with a range of 0.04 to 0.33 meals per week.

Paul Charp showed the Task 4 Report’s (Table 3.2 in the Task 4 Report) summary of radionuclides and pathways that were identified for further analysis. These included deep water, fish, external shoreline sediments, and various dredging pathways. The report concluded that there was no swimming in White Oak Creek and that there was no irrigation water, so those pathways were eliminated for further analysis. (Gordon Blaylock submitted written comments that noted that there is also no swimming and no irrigation water in the Clinch River.)

A summary of reference individuals by exposure pathway (Table 13.2 in the Task 4 Report) was presented. The exposure pathways included drinking water, fish ingestion, external exposure, and ingestion of milk and meat. According to Paul Charp, the majority of these individuals were associated with the K-25 facility, the Kingston Steam Plant, and fishing along the Clinch River.

The Task 4 Report also developed doses (Table 13.5 in the Task 4 Report). These doses looked at the bone, breast (female), lower large intestine, red bone marrow, and skin following ingestion of drinking water, milk, and meat. The doses were in centi-Sievert (cSv), which is equal to one roentgen equivalent man (rem). For example, 0.25 to 0.55 cSv equals 0.25 rem or 25 millirem (mrem), or 0.55 rem or 500 mrem. Paul Charp explained that the dose to skin was essentially non-existent and that the numbers in parentheses in the table represented the 50th percentile. Thus, according to this table, the 50th percentile for bone was 0.11 cSv or 0.11 rem to bone, following the ingestion of drinking water.

Paul Charp explained that there were many graphs in the Task 4 Report that showed the analysis conducted by SENES. This analysis evaluated the measured releases at several mile markers along the Clinch River and compared these to SENES’ predicted measurements. Dr. Charp showed cesium 137 as an example. He said that the predicted and measured concentrations were fairly close, and that the concentration estimates were in “very good agreement” from about 1945 through 1990. In addition, the majority of the measurements conducted by SENES followed this same type of trend—a good correlation between the predicted and measured concentrations. (On May 19, 2003, Gordon Blaylock noted that this statement was incorrect since SENES did not conduct any measurements.) Because of the rise and fall of the river, some of the dissolved cesium was deposited in the sediments. He noted that there was “good agreement” between the measured and predicted cesium concentrations in shoreline sediments for Clinch River Mile (CRM) 14. Also, Dr. Charp said that there was not a lot of uncertainty in the data analysis. Furthermore, SENES conducted this process for cesium, cobalt, ruthenium, strontium, and a couple of other radionuclides.

A table with the measured and predicted radionuclide inventories in the Clinch River for 1962 and 1977 (Table 6.8 in the Task 4 Report) was presented. The table showed the estimated and predicted inventory for both 1962 and 1977. According to the report, ruthenium 106 had dropped to less than 1% during this time period.

Paul Charp explained that he had taken a 3-page long table from the Task 4 Report for the annual total releases to White Oak Creek. Instead of putting in 90 figures for the various data points, Dr. Charp divided the data into 6-year intervals. He presented a graph of the data, which showed that the major releases to White Oak Creek occurred between 1956 and 1961. (Gordon Blaylock submitted written comments, which stated that the releases to White Oak Creek were from White Oak Dam [WOD].) The period with the second highest releases took place from 1962 to 1967. After these two time periods, the numbers were very low.

Paul Charp presented a figure with a time line that showed how much cesium had been absorbed in infants and adults. For infants, 10% was absorbed, whereas 5% was absorbed in adults. An adult would receive 2.5 x 10-9 rem or picocuries (pCi).

Paul Charp presented a summary of the measured radionuclide concentrations in shoreline sediment from 1991 to 1994 (Table 6.11 in the Task 4 Report). This table looked at the cesium and cobalt detected in the shoreline from the Clinch River to Melton Hill Dam, and essentially to Watts Bar Dam. Because these concentrations were in becquerel/kilogram (Bq/kg), the pCi/gram (pCi/g) would be derived by multiplying by 27 and then dividing by 1,000. Dr. Charp explained that there were extremely low levels of both cesium and cobalt in the Tennessee River, and from the Clinch River to the Watts Bar Reservoir.

A table was shown that provided the potential exposure pathways, locations of interest, applicable time periods, and estimated exposure populations for the Clinch River (Table 7.10 in the Task 4 Report). The table included the following exposure pathways: drinking water, fish ingestion, milk and/or meat ingestion, and external exposure. According to Paul Charp, the population estimates shown indicated that these could have been fairly insignificant. The figures ranged from 25 people in Jones Island to over 20,000 people along the Clinch River, and took about 60 years of exposure into account. (Gordon Blaylock submitted written comments that noted that references to people in Jones Island should be written as “people in the area of Jones Island.”)

Paul Charp explained that SENES looked at other data from laboratory reports from 1951 (Table 8.4 in the Task 4 Report). The radionuclide concentrations in carp, crappie, and other fish were analyzed. He used an example of 360,000 Bq/kg that was detected in the bone of redhorse on upper White Oak Lake. If 360 was multiplied by 27, then a concentration of approximately 1,000 pCi/g would be derived for upper White Oak Lake.

A table containing the organ doses for adults based on material in the sediments (Table 13.4 in the Task 4 Report) was shown next. Paul Charp said that these were mainly for cesium, cobalt 60, and possibly strontium 90 exposure. He pointed out the mid-doses for bone. Dr. Charp said that an individual at Jones Island had a central value of 12 mrem, and that an individual in the city of Kingston had a 50 mrem central value. (Gordon Blaylock submitted written comments that noted that references to people in Jones Island should be written as “people in the area of Jones Island.”) He noted that these doses were relatively small doses to the organs.

Paul Charp presented a table with the fish consumption for Jones Island and the city of Kingston (Table 13.3 in the Task 4 Report). (Gordon Blaylock submitted written comments that noted that references to people in Jones Island should be written as “people in the area of Jones Island.”) He used an example of cesium in the breast in females for Kingston. Dr. Charp said that the risk for Category I was about 30 mrem/year. He selected cesium because it was a whole body isotope, meaning that it was uniformly distributed to all of the tissues in the body. He also pointed out that the dose for the lower large intestine for cesium was about 54 mrem/year.

ATSDR’s Summary of the Expert Panel (Task 4)

Paul Charp explained that ATSDR had three experts review the Task 4 Report to answer the following question—Does the White Oak Creek radionuclide releases report provide a foundation on which ATSDR can base follow-up public health actions or studies (i.e., is there sufficient information for public health professionals to draw conclusions and make public health decisions)? Dr. Charp presented the following slides, which summarized the comments from the expert panel. Dr. Charp’s comments during the presentation are denoted by quotation marks.

The task requirements for the review consisted of 9 tasks:

  • the study design and scientific approaches
  • methods of data acquisition, models and analyses, and statistical reliability
  • completeness of data and analyses included bioconcentration factors
    • “a uniform bioconcentration factor does not exist; these are based on the media and species”
  • data interpretation and clarity of report

The major areas of consideration were the following:

  • source terms and radionuclide concentrations
    • “these will drive the doses and the decisions in the evaluation”
  • uncertainty and sensitivity analysis
    • “indicate if the reviewers thought that the correct parameters were used to determine the doses”
  • health effects and public health

The summary of the comments on the overall content was:

  • well written and its objectives were clearly stated
  • overall design and scientific approach were appropriate

Direct comments from the reviewers included:

  • “break new and important ground in the use of uncertainty analysis in environmental assessment”
  • “truly exemplary compared to other projects in risk assessment and dose reconstruction”

Overall design questions:

  • Radionuclide concentrations in water and sediment at downstream locations in the Clinch River from 1944 to 1991.
  • Radionuclide concentrations in fish from the Clinch River had deficiencies in their approaches.
    • the analysis fails to separate influence of the uncertainty and variability in model parameters on risk estimates
    • the report fails to properly calibrate the HEC model used for predicting radionuclide concentrations in water and sediment
    • the report fails to study model uncertainty in predicting radionuclide concentrations in water and sediment
    • the analysis fails to incorporate radionuclide-specific adjustment factors for using reconstructed radionuclide concentrations in water at one river mile from measurements at another river mile
    • the use of site-specific bioconcentration factors to model radionuclide concentrations in fish is not well supported by the field data

Additional overall comments:

  • Quite valid and consistent with earlier studies in Oak Ridge and the Columbia River.
  • Useful for public health decision making; careful attention given to assumptions behind the estimates; may be applicable for preliminary decision making, but may not be sufficient to allow detailed public health decision making.
  • Results of the assessment on the estimates of radionuclide concentrations, and the dose and risk estimates based on these concentrations, are limited and are not scientifically defensible since the implementation involved with the treatment of empirical data (general and specific) and modeling is often inappropriate.

Additional comments:

  • Scientific interpretations were appropriate.
  • Agreed that the conclusions and recommendations were based on the information provided in the report.
    • Exception—total estimated release of radioactivity for all years was not documented in the report.
  • The report presents enough details to allow for independent evaluation and verification of models and estimates (1 reviewer).
  • Not enough details are available (2 reviewers).
    • One identified this as the primary weakness of the report and specifically pointed out that the details of the models used to estimate the radionuclide concentrations in the Clinch River water and sediment are not provided.

Public health related comments:

  • Provides sufficient and adequate information for later public health analysis and decisions (1 reviewer).
  • While the report provides a good starting point in supporting public health decisions and a number of conclusions about historical releases of radionuclides can be drawn, it does not provide sufficient and adequate information to determine follow-up public health actions or policies (2 reviewers).

Radionuclide concentration estimates:

  • The estimates of concentrations either are or appear to be appropriately compared with historically measured concentrations (2 reviewers).
  • The modeled concentrations are not in agreement with historically measured concentrations (1 reviewer).
    • This does not agree with the justification for using the proposed models to estimate doses and risks.

Bioconcentration factors:

  • Appear reasonable and incorporate a reasonable degree of uncertainty, are based on a wide range of information, and make use of local information where possible (2 reviewers).
  • The use of bioconcentration factors in fish is not adequately supported (1 reviewer).
    • Grouping species of several tropic levels.
    • The resulting distribution is much lower than the recommended values of the International Atomic Energy Agency (IAEA).
    • A better job could have been done in comparing the bioconcentration factors in the study to values from the literature.

Uncertainty and sensitivity analysis:

  • Impressed with the extensive use of statistical approaches, uncertainty analyses, and sensitivity analyses throughout the report.
  • Most comprehensive seen, but the analysis is incomplete and its interpretation is limited.
    • Variability is not addressed in the assessment.
  • Two reviewers commented that the distribution functionsappropriately describe the variability of the parameters.

Uncertainty:

  • Overall, the approach is reasonable and appropriate.
    • Uncertainty estimates were not expanded for periods of time when data on radionuclide concentrations were not available.
    • Tendency to make use of uncertainty factors, rather than examine the model more closely, in an effort to understand the reason for differences between model predictions and measured values.
    • Several instances when the uncertainty factors are not implemented appropriately (i.e., the adjustment factors for spatial scaling of measured radionuclide concentrations should be radionuclide-specific).

Two omitted sources of uncertainty:

  • The use of the linear non-threshold hypothesis for cancer risks may cause the lower end of the risk estimate intervals presented in the report to be too high.
  • The upper end of the risk estimate intervals may be lower than in the real situation because the risk estimates do not incorporate possible synergistic effects, and some choices of probability distribution functions appear overly restrictive.
    • “ATSDR does not support the use of risk.”

Highest risk:

  • Those people who consumed large amounts of fish (or wildlife) from 1944 to 1953 have the highest risk of an adverse health effect.
    • One of the reviewers stated that the report provides only limited information to allow identification of a population at significant increased risk.
  • Both reviewers concluded that it is unlikely that adverse health effects would be statistically detectable.

Epidemiological impact:

  • Estimated doses and risks are far below the observed threshold necessary to guide epidemiological planning and decision-making.
  • Information about doses from individual exposure pathways, together with estimates of the number of individuals who were potentially exposed to these doses, would probably be useful for epidemiologic planning and decisions.
  • The extent to which the data can be interpreted for epidemiologic purposes may be limited because the report does not provide details on the number of people who were potentially impacted by the combined pathways.
    • “This comment is incorrect as there is a table in the Task 4 Report that shows that there could be as many as 20,000 people affected.”

ATSDR’s Evaluation of the Lower Watts Bar Reservoir (LWBR)

Paul Charp explained that Carol Connell, a health physicist with ATSDR, conducted an evaluation of the LWBR. He showed the following slides, which summarized this health consultation.

Purpose:

  • ATSDR was asked by the community to evaluate whether DOE actions were sufficient to protect the public from ORR contaminants in the LWBR.
  • DOE proposed to leave the contaminated sediment in place at the LWBR.

Background based on the Task 4 Report:

  • Radionuclides, predominantly cesium 137, strontium 90, and cobalt 60, were released from the ORR to the Clinch River and eventually reached the LWBR.
  • White Oak Dam is the main point of release to the Clinch River.

Assessment methodology:

  • In evaluating potential health hazards associated with leaving the contaminated sediment in place at the LWBR:
    • ATSDR used available environmental data collected from the LWBR in the 1980s and 1990s:
      • surface water
      • sediment—surface and subsurface samples
      • fish—channel catfish, bluegill, and largemouth bass
    • ATSDR considered various exposure situations along the LWBR.
    • ATSDR used worst-case assumptions when evaluating hazards.

Media

Primary Contaminants

Maximum Concentration (pCi/g)

Surface Water

H-3, Sr-90, Co-60, Cs-137, Pu-238, Pu-239, total uranium

All below EPA’s MCLs or proposed/current limits

Surface
Sediment

Sr-90

0.90

Cs-137

10.31

Co-60

0.34

Subsurface
Sediment

Sr-90

3.30

Cs-137

58.35

Co-60

1.21

Biota

Sr-90

1.00 (with bone)

Cs-137

0.16 (wet tissue)

Co-60

0.24 (wet tissue)

Paul Charp explained that all of the concentrations that were detected in surface water were below the U.S. Environmental Protection Agency’s (EPA) proposed/current drinking water standards. Dr. Charp said that this suggested that people could drink water from the Clinch River.

Paul Charp presented another table to show the exposure situations and routes by media:

Media

Exposure Situations

Route of Exposure

Surface Water

Domestic use (unfiltered)

Domestic use (unfiltered)

 

Ingestion

Sediment

Swimming

Dermal contact

Fishing

Dermal contact

Use as topsoil

Dermal contact

Biota

Fishing

Ingestion

Findings:

  • Surface water exposure
    • Low level of radionuclides in surface water.
    • No hazards for persons drinking or swimming in the water.
  • Sediment exposure
    • Subsurface sediment had the highest detected levels of contamination.
    • No hazards for contacting surface or subsurface sediments.
  • Fish consumption
    • No hazards from eating fish containing detected concentrations of radionuclides.

Paul Charp read a portion of the executive summary of the Task 4 Report from page ES-11, which stated that … “it is unlikely that any observed trends in the incidence of disease in populations that utilized the Clinch River and Lower Watts Bar Reservoir after 1944 could be conclusively attributed to exposure to radionuclides released from the X-10 site, even though this present dose reconstruction study has identified increased individual risks as high as 1 x 10-3 resulting from these exposures.” Dr. Charp added that the detailed peer review comments were “shaky,” but that the overall comments indicated that this was a good report.

From its evaluation of the LWBR, ATSDR concluded that the LWBR sediment, if left in place and undisturbed, did not and would not pose a health problem for people who use the river for swimming, fishing, and domestic purposes. In addition, ATSDR made the following three recommendations: (1) the current advisory along the LWBR for polychlorinated biphenyls (PCBs) should remain in effect, (2) any plans to construct or dredge in the reservoir should be evaluated by the Interagency Working Group, and (3) municipal water systems that draw water from the reservoir should continue to be analyzed for radionuclides, particularly if and when the ORR is aware of increases in surface water contaminant releases from the reservation.

Discussion

Gordon Blaylock asked when ATSDR conducted its health consultation. Paul Charp said that it was in 1996 or 1997. Dr. Blaylock asked if ATSDR had data up to 2003; Dr. Charp said that the agency did not.

Bob Craig asked if White Oak Creek dumped into the Clinch River above Melton Hill Dam. Many people answered that the creek dumped into the river below Melton Hill Dam.

Gordon Blaylock explained that when the ORNL was built, it was designed to be open for only one year. However, this time period was extended and when the facility started to release radioactivity, all of the waste was supposed to be put into large gunite tanks. When the facility started to release the waste from the tanks, it went down to White Oak Creek. Because this caused the concentrations to increase insignificantly, a large retention area was constructed. It was built in 1944 within a time period of about six months. Paul Charp asked if these were the 500,000-gallon tanks that were located by the cafeteria. Dr. Blaylock said that Dr. Charp was correct. Dr. Blaylock continued that these tanks were originally supposed to hold everything from the facility and to receive all of the radionuclides. However, when the facility was not closed as intended, there had to be a method devised to deal with the radioactive waste. Thus, the facility started to release the waste to White Oak Creek. Two ponds were used—one held the waste for 24 hours, while the other pond released the waste. These ponds were used alternatively, and the waste was released to White Oak Creek. As a result of these disposal practices, the activity in the river was too high. Thus, this retention area was built for the waste, and the facility discontinued releasing waste into the river.

Tim Joseph pointed out that the retention basins were not lined, unlike today’s type of basins. Paul Charp wanted to clarify that there was not an engineering barrier (other than gravel) used. Dr. Joseph said that this was correct and that it was important to note. Dr. Charp added that any seepage was dependent on the veracity of the soil.

Gordon Blaylock noted that there was a barrier at White Oak Creek, but that people still fished there. Tim Joseph asked if Dr. Blaylock was referring to the cable barrier and he said that Dr. Joseph was correct. Dr. Joseph continued that the barrier was simply a cable that went across with a sign that said not to enter the area. He said that people would lift this up, go under the cable, and fish at the creek.

A meeting participant suggested that when the tables from the Task 4 Report were redone, that ATSDR change the values to mrem. Paul Charp said that these were only kept as cSv because of the timeframe.

Gordon Blaylock did not think that ruthenium was included in the sediment analysis because it usually moves right out of the water. Paul Charp replied that one of the figures showed that ruthenium 104 had a very short half-life and that it dropped off to almost no concentration around 1970. Dr. Blaylock said that it was ruthenium 106 that dropped off. A meeting participant asked Paul Charp about the units of measure. Dr. Charp thought that it was in picocuries per liter (pCi/L). Gordon Blaylock said that it could not be in pCi because more than a curie per year (Ci/year) was currently released to White Oak Creek. The group discussed the matter and resolved that the measurements were in total Ci.

Bob Craig asked if ruthenium 106 was the primary isotope that was released. Paul Charp replied that it would be if it had been done in Ci. Dr. Craig asked if it was water soluble. Gordon Blaylock said that ruthenium 106 had a very short half-life and that it did not go to the sediments because it stayed in the water. He explained that these releases occurred in 1956 when the facility was reprocessing fuel rods. Three big pits were dug on the side of White Oak Lake and waste from the rod reprocessing was dumped into these pits. Later, so much waste was accruing that a pipeline was built through the pits, and then the pits started running over and seeping. One of these pits leaked a maximum of 50 Ci/day. Dr. Blaylock thought that over 2,000 Ci were released in one year (1956) over White Oak Dam, but this was a short half-life. He thought that it was two weeks for ruthenium 106. Dr. Charp checked in a book and said that it had a half-life of one year. Dr. Craig noted that one-year was not that short, but that the radionuclide stayed in the water column. Dr. Blaylock thought that ruthenium went to rhodium, which had the largest beta of any radionuclide. Thus, a person could receive a large dose of rhodium.

A meeting participant asked what the biological affinity was for ruthenium 106. Gordon Blaylock replied that it had a concentration factor of about one.

Bob Craig thought that cesium was the radionuclide of concern with White Oak Lake. Gordon Blaylock stated that it was because it had a long half-life. Dr. Craig asked if it remained in the sediment. Dr. Blaylock replied that SENES measured and estimated that roughly 170 Ci of cesium remained in White Oak Creek sediment after White Oak Lake was drained. (On May 19, 2003, Dr. Blaylock said that this statement was incorrect because SENES estimated, but did not measure anything.) Paul Charp responded that there were similar problems with Savannah River. Dr. Blaylock added that the amount of cesium in Park Pond was very small compared to White Oak Lake.

Gordon Blaylock said that he was not sure about the current levels, but that the last time he checked, the total amount of activity in White Oak Lake was 350 Ci in sediment (primarily cesium, strontium, and other isotopes). Tim Joseph mentioned that the main reason that the coffer dam was built was because the lake would go up and down, and it would bring in sediments. Dr. Blaylock explained that when the lake was drained in 1956 and the flood occurred after that, the activity was washed over the dam. A lot of the radionuclides were transported to Watts Bar and down the river, and a lot was deposited in White Oak Creek Embayment. He knew that there were high concentrations in the creek going up to 2,500 pCi/g (rough estimate) for cesium. (On May 19, 2003, Dr. Blaylock corrected this statement to read, “He knew there were high concentrations in the creek going up to 40,000 pCi/g [rough estimate] for cesium.”) This was down deep in the sediment, about 20 or 30 centimeters below the surface, so it was not of concern. However, it was later found that the sediment surface in White Oak Creek had a little lower than that level caused by Melton Hill Dam. They had a “lock and release,” where everyday they released water from the dam. The “sloshing back and forth” was taking the sediment out of White Oak Creek and moving it down to the river.

Bob Craig asked for clarification concerning the 54 mrem/year in Kingston. He wanted to know if this was annually. Paul Charp believed that this was over 47 years. Gordon Blaylock was not sure. Dr. Craig thought that this was insignificant.

A meeting participant said that the reviewer comment that the “total estimated release of radioactivity for all years was not documented in the report” was incorrect.

Gordon Blaylock commented on the bioconcentration factors slide. Paul Charp explained that a study should not have grouped fish of several tropic levels (i.e., bottom feeders would not be grouped with top feeders). Dr. Blaylock said that the study was not conducted in that manner and that he had written the IAEA reports. Dr. Charp said that this only represented one reviewer’s comments. Dr. Blaylock thought that it “would have been nice” if SENES was given an opportunity to see the reviewers’ comments and to respond to them. Dr. Charp said that the comments would be attached to the document. Dr. Blaylock expressed that this was too late to receive the comments because SENES could have responded to the comments. Tim Joseph added that SENES should have been able to respond to the comments, especially because they were “clearly mistaken.” Dr. Joseph thought that incorrect comments should not be included. Dr. Blaylock said that a person who reviewed a document should be able to stand by his/her comments.

Bob Craig mentioned that an “anonymous” peer review could be conducted to enable reviewers to respond, while also keeping their anonymity. Burt Cooper explained that this was not “technically” their area. He said that Henry Falk at ATSDR worked with the “peer review.” Gordon Blaylock asked if Dr. Falk had people respond to the comments. Mr. Cooper stated that people were not asked to respond to the comments because the peer review was only used for internal ATSDR decision-making. James Lewis asked if Dr. Blaylock could respond now that he had seen the reviewers’ comments. In response to Dr. Craig, Paul Charp explained that ATSDR would not necessarily disregard these comments, but that it would “weigh in” that they may not be correct. Tim Joseph thought that it was important for the working group to not have these mistakes published.

Kowetha Davidson said that there were too many contradictions within the reviewers’ comments. Based on what they had seen so far, she did not think that the comments were very useful. Bob Craig added that he did not know who the reviewers were, but that they certainly had expertise in different areas. Paul Charp replied that he knew two of the reviewers and had heard of the other reviewer.

Gordon Blaylock said that the Clinch River water was used for drinking water at the K-25 facility for several years. Bob Craig asked if the water was treated. Dr. Blaylock replied that the water was treated with a water intake structure at CRM 14. He added that in the 1950s and 1960s, there was a spill at White Oak Creek and this was shut down.

Kowetha Davidson asked if there was a maximum contaminant level (MCL) for total radionuclides. Paul Charp responded that there was an MCL for man-made beta and photon emitters, which was 50 pCi/L. Dr. Charp added that the MCL for tritium was about 20,000 pCi/L. He noted that these MCLs were derived by the dose. Dr. Charp explained that EPA used a dose of 4 mrem/year in water to determine the MCL. He added that the isotope had to be known, and that the MCL was calculated by using EPA dose factors. However, the MCL might not be equivalent to the National Council for Radiation Protection and Measurements (NCRP) or International Commission on Radiological Protection (ICRP) standards.

A meeting participant asked how the screening numbers were selected (e.g., 50 pCi/L). Paul Charp replied that the MCL was defined as 50 pCi/L for man-made beta and gamma radionuclides. He used the example of tritium, which was proposed for an increase to 60,400 pCi/L, but that it was decided it could not be raised. The meeting participant thought that this may be worth discussing.

Kowetha Davidson asked if doses were added when there was more than one radionuclide. Paul Charp said that this was normally done for MCLs, which was called the “sum of the ratios technique.” The concentration of water was taken and divided by the MCL. If the sum of the ratio was greater than 1.0 (as defined in the Drinking Water Act), then the MCL was exceeded.

In regards to a question about the duration of doses, Paul Charp referred to an appendix from the Task 4 Report. Dr. Charp explained that he looked at a number of the equations that were used to estimate dose and risk. He looked at the screening level risk estimate for ingestion of beef exposed to dredge sediment. He brought the PHAWG’s attention to “ED”, which stood for exposure duration in years. He said that all of the exposure durations were based on the number of years from the time of release to the Task 4 Report. Thus, the duration was from the beginning of the exposure to 1991. In reference to the recommendations slide, Gordon Blaylock believed that a person had to go through a committee before dredging or building a pier. He said that this process was already in place.

Gordon Blaylock asked if Kingston was the municipal water system below the Watts Bar. Several meeting participants agreed. Tim Joseph noted that the city of Kingston’s water intake was one mile up from the Tennessee River. Pete Malmquist thought that it was only a couple of hundred yards. Dr. Blaylock said that when the Clinch River was “pulling down,” the water could back up to the intake structure. He said that SENES evaluated this in the Task 4 Report and that he thought that the distance was about a mile. Paul Charp asked about Spring City. Dr. Malmquist said that the city of Kingston was the only city that was close to the intake. He added that this would be “low flow” out of the Tennessean and flow out of the Clinch River to go back up. Dr. Blaylock thought that this was “very unusual.” He asked if Broadway used a small stream. Dr. Malmquist replied that Broadway took it from the embayment.

Burt Cooper said that ATSDR conducted an exposure investigation several years ago that identified people who consumed the greatest number of fish and turtles from the Lower Watts Bar Reservoir. Blood samples were taken from the individuals and evaluated for PCBs and mercury. According to Mr. Cooper, ATSDR did not find levels that were generally elevated among people identified as the greatest consumers of fish and turtles.

Gordon Blaylock said that he knew that ATSDR was not trying to indicate any facilities, but that there were more PCBs coming down the Tennessee River than the Clinch River.

Bob Craig asked where they were on the outline. James Lewis asked if they had already listed the resources, as detailed under the PHAWG 1 meeting. Paul Charp said that he would check with Jack Hanley. Mr. Lewis thought that they were between PHAWG 1 and PHAWG 2.

Bob Craig said that it looked as though they already had their conclusions. Paul Charp responded that the conclusions were only based on the Task 4 Report. Dr. Charp thought that the “big issue” was to resolve the reviewers’ comments. Dr. Craig questioned preparing a complete PHA since they already know the conclusions. He said that they were stripped for resources and had a lot of work that still needed to be completed. He asked if there was an expedited PHA that could be done in lieu of using technical time and technical resources that could be better utilized for other topics (e.g., iodine 131). Burt Cooper said that if the PHAWG made a recommendation to ATSDR that a full-blown PHA not be conducted, then this recommendation would be considered.

Tim Joseph wondered if it was really going to take that much additional time to prepare a full-blown assessment, rather than a shorter version, since ATSDR already had the needed information. Dr. Joseph was concerned about how the reviewers’ comments would be handled if they were placed into the report. Bob Craig wanted SENES to look at the comments. Gordon Blaylock pointed out that people would question why radionuclides were not addressed. However, he believed that a shorter version would be appropriate.

Bob Craig wanted to know if they should ask ATSDR if there was anything to be saved by not conducting a full-blown PHA.

Kowetha Davidson asked if the PHA would still have to be released for public comment if the document was expedited. Burt Cooper stated that ATSDR would have a public comment period for anything that it prepared.

Paul Charp explained that ATSDR could prepare documents other than PHAs. For instance, ATSDR could conduct a health consultation that would explain the presentation given today and put it in an organized manner. It would also show the Task 4 Report results, as well as the reviewers’ comments on the report. It would provide the current review of the Clinch River, and also include information from Dee Williamson concerning the state data (once it is received). A consultation would detail any changes from the time that Carol Connell conducted her assessment to the recent data. The consultation would then be sent out for public comment. If the document included the technical reviewers’ comments, then SENES would have an opportunity to respond.

Burt Cooper said that Congress gave ATSDR some relief in its mandate a few years ago. ATSDR is no longer required to conduct a PHA at every National Priorities List (NPL) site. A health consultation, or something similar, could be conducted if it was deemed appropriate. Tim Joseph asked if the conclusions differed. Mr. Cooper said that the conclusions did not differ, and that the document contained conclusions and recommendations. Dr. Joseph was concerned that if the public wanted a health assessment, then the public may not be satisfied if ATSDR did not produce a PHA.

James Lewis said that they had talked about “down streamers” (i.e., where Pete Malmquist lived). Mr. Lewis wanted to know if this was a primary issue. A meeting participant responded that it was. Mr. Lewis asked if the people living downstream would accept something that was not a complete assessment.

Tim Joseph asked what the time and resource difference were between a PHA and a health consultation. Burt Cooper replied that he could not supply an answer at the time, but that he would check. Dr. Joseph thought that it was extremely important to finally put the public’s questions to rest.

Pete Malmquist noted that one of the recommendations for the LWBR was that there was no dredging without approval. He noted that people were already required to obtain permission, so if ATSDR did not prepare a health assessment, then people may ask why they needed to do that. Paul Charp responded that those recommendations were based on information that was known in 1996. Thus, once the data have been reviewed, these recommendations could change.

James Lewis thought that they were behind in looking at the community concerns database. He said that they needed to look at the database to see what the issues and concerns were before they “leapfrog” into something else. Burt Cooper said that ATSDR would look at the new data regardless of which path it decided to take.

Kowetha Davidson had two questions. First, would a health consultation become part of the overall health assessment? Burt Cooper responded that it would. Second, could an expedited health assessment be conducted without going through all of the usual steps? Mr. Cooper said that ATSDR would have to go through the usual procedures.

Bob Craig asked for clarification on if the PHAWG wanted ATSDR to evaluate the possibility of conducting a technical consultation. James Lewis said that the PHAWG needed to look at the outstanding issues to see what the “down streamers” were concerned about. Paul Charp made a suggestion to let ATSDR review the most recent data to see if there were any drastic changes. In addition, ATSDR would try to obtain clarification on the reviewers’ comments.

Bob Craig wanted to obtain input from SENES about mixing the trophic levels. George Gartseff thought that the assessments would be based on available data. He said that in the course of finding out that the Task 4 Report was good enough for ATSDR to use, there were differences in opinion. Mr. Gartseff believed that this was ATSDR’s chance to say that it looked at these differences, and that for certain reasons it concluded that a comment was valid or not valid. He added that he would not direct ATSDR to prepare a different document.

New Business

Pete Malmquist summarized a conversation that he had with Jack Hanley. Mr. Hanley had notified Dr. Malmquist that Ed Fromm from ATSDR had offered his services as a statistician to work with Dee Williamson. James Lewis had also read this e-mail and noted that they should accept expertise when it is offered.

Two ATSDR employees hired to work out of the Oak Ridge office were introduced to the PHAWG. Bill Taylor, a chemist and toxicologist who had previously worked with ATSDR (1992-1999), and Melissa Fish, who previously worked as an intern with ATSDR, were introduced.

The meeting was adjourned at 7:30 pm.

 Resources on Oak Ridge Reservation Health Effects
Education & Training Opportunities General Information Publications and Products
Fact Sheets Questions & Answers Presentations
horizontal dividing line
rectangle border
Oak Ridge Reservation
bullet Home
bullet Public Health Activities
bullet Public Participation
bullet Community Resources
bullet ORRHES Subcommittee
bullet Contact Us
bullet Site Map
rectangle border
 Events
Calendar of Meetings
divider

Programs

State Agency Links
List of ATSDR state cooperative agreement partners. divider

 

 
 

This page last updated on February 16, 2005
For more information, contact ATSDR at:
1-800-CDC-INFO or e-mail (public inquiries)

ATSDR Home  |  Search  |  Index  |  Glossary  |  Contact Us
About ATSDR  |  News Archive  |  ToxFAQs  |  Public Health Assessments
Privacy Policy  |  External Links Disclaimer  |  Accessibility
US Department of Health and Human Services