Scenes from March 24, 2002

broadflag2.JPG (268188 bytes) At Area D following excavation, flags denote the location of 20 samples collected to confirm the removal of contaminants. Four samples were split with the Suffolk County Department of Health Services.
divert.JPG (247704 bytes) At Area A, a temporary river dam with 4-inch diameter pipe detour water to help dry a portion of the river to be vacuum guzzled. 

Scenes from March 29, 2002

tractor5.JPG (250862 bytes) At Area D, 731 cubic yards of topsoil/compost mixture was spread over the area from which contaminated sediment was removed.  The application of a topsoil/compost mixture follows the requirements of the New York State Department of Environmental Conservation.
rifflebed3.JPG (269953 bytes) At the Drying Beds, an excavator exposes soil to air to help the drying process. Nearly 750 cubic yards of contaminated sediment were removed from Area D.

Scene from April 1, 2002

supersack1.JPG (247931 bytes) At Area A, sacks filled with approximately 10-tons of dried sediment each, await transport to a temporary storage location at BNL prior to offsite disposal. 

Scenes from April 2, 2002

coconut.JPG (327067 bytes) At Area D, engineer Amanda Ludlow uses a biodegradable stake to fasten the first of 26 coconut mats to the recently seeded topsoil/compost mixture. The coconut mats help prevent erosion, protect the seeds from birds, and provide additional organic matter to the newly constructed wetland.
BobRay.JPG (200198 bytes) At Area A, Project Engineer Bob Litzke explains the sediment-drying process to Ray Bettinelli, president of the Peconic River Sportman's Club. Sediment from the vacuum guzzler is first unloaded into a screened drying tank for 48 hours. The weight of the sediment squeezes water through the screen where it collects on the bottom of the tank. Later, the sediment is moved into the intercept box (right) and mixed with a white, inert, drying agent. When dry, the sediment is bagged in a 10-ton, white supersack (left), ready for transport to an offsite disposal facility.

Scenes from April 4, 2002

experisedge4.JPG (302342 bytes) At Area D, following the placement of the new topsoil/compost mixture and the removal of invasive plants (canary grass and phragmites), tussock sedges are planted. Along the upper edges of the river, nearly 2,200 sedges were planted. In the lower half of the river, 1,900 soft rushes were planted. In the early summer, bur reeds will be planted among the soft rush.
guzzleclose8.JPG (324981 bytes) At Area A, wetland plants are left undisturbed, as the vacuum guzzler works around them.


Scene from April 10, 2002

AREAA3.JPG (273957 bytes) At Area A, the section know as A-2 has been dewatered with a large capacity pump. The water was temporarily detoured to the HQ Measuring Station. The dewatering enables more effective vacuum guzzling. When the vacuum guzzling is complete, the flow of the river will be returned to its natural state.

Scenes from April 23, 2002

guzzle6.JPG (842714 bytes) At Area A, the vacuum guzzling process is underway in the newly dewatered section. To date, nearly 600 cubic yards of contaminated sediment have been removed from Area A.
waterrecover2.JPG (870664 bytes) At the Drying Beds, water is recovered into drums and stored in secondary containment for later testing and disposal.