FIN 07-20
Construction began in 1987. Repayment contract X-XX-XX-XXXXX with the New Irrigation District covers repayment of municipal and industrial water and recreation costs. The contract includes contributions of $30,000,000 allocable to all project functions. Power costs are to be repaid by the New Power System.
Applicable multipurpose allocation percentages and interest
rates include:
|
|
|
|
Power |
30.000% |
8.890% |
1987 power repayment rate |
M&IW |
40.000% |
10.693% |
1987 rate per Water Supply Act & Repayment Contract |
Recreation |
10.000% |
10.693% |
1987 rate per Water Supply Act & Repayment Contract |
Fish/Wildlife |
5.000% |
||
Flood Control |
15.000% |
||
Total |
100.000% |
The recreation, Fish and Wildlife, and flood control multipurpose functions are nonreimbursable. Fifty percent of the single-purpose recreation costs are reimbursable.
Acronyms: CY Current Year IDC Interest During Construction M&IW Municipal and Industrial Water ND Net Disbursements PY Prior Year