Headquarters Daily Report
REGION II
Management Changes at Browns Ferry
Licensee/Facility:
TENNESSEE VALLEY AUTHORITY
Browns Ferry 1, Browns Ferry 2, Browns Ferry 3
DECATUR, Alabama
Dockets: 05000259, 05000260, 05000296
[1] GE-4, [2] GE-4, [3] GE-4
License No:
|
Notification:
MR Number: 2-2008-0001
Date: 02/19/2008
|
Discussion:
On February 19, 2008, Tennessee Valley Authority announced that Russell “Rusty” West was selected as the Site Vice President for Browns Ferry Nuclear Plant. Mr. West recently served as Site Vice President at AmerGen Energy's Three Mile Island Plant at Pennsylvania. Mr. West is replacing Michael Skaggs who was serving as the temporary Site Vice President at Browns Ferry since December of 2007. Mr. West will assume his new position effective March 3, 2008.
Accession Numbers:
Accession No |
Accession Date |
ML080510636 |
02/20/2008 |
Contacts:
Name |
Office Abbrev |
Phone No |
E-Mail |
NEASE, REBECCA L |
R2 |
(404) 562-4530 |
RLN1@nrc.gov |
REGION III
CHANGES IN PERRY/DAVIS BESSE SENIOR MANAGEMENT
Licensee/Facility:
FIRSTENERGY NUCLEAR OPERATING CO.
Perry 1
PERRY, Ohio
Dockets: 05000440
[1] GE-6
License No:
FirstEnergy Nuclear Operating Co.
Davis-Besse
OAK HARBOR, Ohio
Dockets: 05000346
[1] B&W-L-LP
|
Notification:
MR Number: 3-2008-0004
Date: 02/19/2008
Resident Inspector's Office
|
Discussion:
On February 18, 2008, FirstEnergy Nuclear Operating Co. (FENOC) announced that John Grabnar has been named Site Engineering Director at Perry. Mr. Grabnar is currently the Site Engineering Director at Davis-Besse. After receiving his Senior Reactor Operator license at Perry in 2001, he went on to serve as the Davis-Besse Design Engineering Manager before accepting the position as Davis-Besse Site Engineering Director in June 2006.
The current Site Operations manager at Davis-Besse, Don Moul, will succeed Mr. Grabnar as the Davis-Besse Site Engineering Director. Mr. Moul has served as Site Operations manager since June 2006. He has held a number of leadership positions within FENOC at both the Davis-Besse and Beaver Valley sites. Mr. Moul and Mr. Grabnar will be reporting to Senior Vice President of Fleet Engineering Dan Pace. These changes will take effect as soon as each can turn over duties to his successor.
Regional Action: Information only; no further action anticipated.
Accession Numbers:
Accession No |
Accession Date |
ML080510006 |
02/19/2008 |
Contacts:
Name |
Office Abbrev |
Phone No |
E-Mail |
FRANKE, MARK E |
R3 |
(440) 259-3610 |
MEF1@nrc.gov |
RUTKOWSKI, JOHN |
R3 |
(419) 244-4494 |
JER7@nrc.gov |
|