Energy Facilities Under Review
Boardman to Hemingway
Cascade Wind Project
Golden Hills Wind Farm Project
Helix Wind Power Facility
Newberry Geothermal Project
Snake River Ethanol Project
Boardman to Hemingway
Proposed Line:
Approximately 298 miles of single circuit 500 kilovolt (kV) transmission line connecting the power plant near Boardman, Oregon and the planned Hemingway substation near Murphy, Idaho
 
Location: Boardman, Oregon to Southern Idaho
 
Status:
The Oregon Department of Energy (ODOE) received a Notice of Intent (NOI) from Idaho Power Company (Idaho Power) on August 28, 2008 to apply for an Energy Facility Site Certificate for a new transmission line, called the Boardman to Hemingway Transmission Line Project. The proposed transmission line consists of approximately 298 miles of single circuit 500 kilovolt (kV) transmission line connecting the power plant near Boardman, Oregon and the planned Hemingway substation near Murphy, Idaho. The proposed transmission line will cross federal, state and private lands.
 
Applicant:
 Idaho Power Company (Idaho Power)
 
Website: http://www.boardmantohemingway.com/idaho_power.aspx
 
Contact:
Eric Hackett, Project Manager
PO Box 70
Boise, ID 83707
Phone: 208-388-5712
E-mail Eric

 
Department of Energy Staff: Adam Bless
 
History:
 
 
Documents:

Cascade Wind Project
Proposed Facility:
Wind energy facility with a peak generating capacity of approximately 60 megawatts.
 
Location: Wasco County
 
Status:
First Wind LLC has submitted a preliminary application  for a site certificate. The Department is reviewing the application for completeness.
 
On October 9, the applicant submitted its response to the Department's first Request for Additional Information (RAI). The response is posted on the applicant's website.
 
Applicant:
First Wind LLC
 
Website: www.cascadewind.com
 
Contact:
Krista A. Kisch
Vice President
Business Development - West Region
First Wind
110 West A Street, Suite 675
San Diego, CA 92101
 
(619) 320-2010
 
Department of Energy Staff: Adam Bless
 
History:
  • July 12, 2006:  Applicant submitted a request for expedited review.
  • July 25, 2006:  Department of Energy approved expedited review.
  • April 10, 2007: Applicant submitted a preliminary application for a site certificate. 
 
Documents:
(The applicant has posted the preliminary application and additional information on its website.)

Golden Hills Wind Farm Project
Proposed Facility:
A wind energy facility with a peak generating capacity of up to 400 megawatts.
 
Location: Sherman County
 
Status:
On August 4, 2008, the Oregon Department of Energy (ODOE) issued notice to the public and nearby property owners that Golden Hills Wind Farm LLC (GHWF) has submitted a complete Site Certificate Application for the proposed Golden Hills Wind Project.
 
Since issuing that notice, ODOE has learned that some properties adjacent to the project have changed hands. Also, GHWF has slightly changed the footprint of its project, so some different individuals are now adjacent property owners. For this reason, ODOE is issuing this second notice of the Golden Hills Project to ensure that all adjacent property owners receive notice. 
 
Application Filed
The Golden Hills Wind Project requires a Site Certificate from the Oregon Energy Facility Siting Council (EFSC).  GHWF submitted a preliminary application in August 2007.  The preliminary application was not complete, and GHWF submitted supplemental information at ODOE’s request. On August 4, 2008, ODOE deemed the application “complete”.  This does not mean a final decision has been made. However, it means the application is considered complete and filed, and ODOE has the information it needs to complete the review of this project.

 
Applicant:
BP Alternative Energy of North America, Inc.
Website: www.goldenhillswind.com
 
Contact:
Kelly O’Brien
BP Alternative Energy North America Inc.
700 Louisiana Street
Suite 3300
Houston, TX 77002
 
(713) 354-2153
 
Department of Energy Staff: Adam Bless
 
History:
  • April 11, 2007: Applicant submitted a Notice of Intent.
  • July 6, 2007: Department of Energy issued a Project Order.
  • August 10, 2007: Applicant submitted a preliminary application.
  • August 4, 2008: Date of Filing (application complete)  
 
Documents:

Helix Wind Power Facility
Proposed Facility:
Wind energy facility with up to 68 wind turbines and a combined peak generating capacity of not more than 102 megawatts.
 
Location: Umatilla County.
 
Status:
The applicant has submitted a Preliminary Application.
 

Applicant:
Iberdrola Renewables, Inc.
 

Contact:
Sara McMahon Parsons
Iberdrola Renewables, Inc.
1125 NW Couch Steet, Suite 700
Portland, OR 97209
 
(503) 796-7732
 
Department of Energy Staff: John White
 
History:
  • August 12, 2008: Applicant submitted a Preliminary Application.
 
Documents:
  • Preliminary Application: The Preliminary Application is not available on this website. The Preliminary Application is available for public review at the Oregon Department of Energy in Salem, at the Pendleton Public Library, at the Umatilla Public Library and at the Helix Library.

Newberry Geothermal Project
Proposed Facility:
Geothermal energy facility with a peak generating capacity of up to 143 megawatts.
 
Location: Deschutes County.
 
Status:
The applicant has submitted a Notice of Intent.
 

Applicant:
Newberry Geothermal Holdings LLC
 

Contact:
Douglas S. Perry
Newberry Geothermal Holdings LLC
300 Atlantic Street, Suite 301
Stamford CT 06901
 
(203) 276-1600
 
Department of Energy Staff: John White  
History:
  • July 3, 2008: Applicant submitted a notice of intent.
 
Documents:
  • Notice of Intent, July 2008
    Part A (applicant information) [906 kb pdf]
    Part B (project description and location) [176 kb pdf]
    Part C (project location map) [372 kb pdf]
    Part D (additional information) [384 kb pdf]

Snake River Ethanol Project
Proposed Facility:
Ethanol production facility producing approximately 130 million gallons of ethanol per year.
 
Location:
Malheur County
 
Status:
The applicant has submitted a Notice of Intent.
 
Applicant:
Snake River Ethanol LLC
 
Contact:
John McCreedy
3184 Elder Street
Boise, Idaho 83705
 
(208) 383-6521
 
Department of Energy Staff: Adam Bless
 
History:
  • July 3, 2008: Applicant submitted a Notice of Intent.
 
Documents:
  • Notice of Intent, July 2008 (not currently available on line)

 
Page updated: September 12, 2008