Sept. 20, 2004
With river work complete, Snoqualmie community, agencies to celebrate expected flood relief
2004
Archived News
1986 flood in the town of Snoqualmie
![1986 Flooding in the town of Snoqualmie](%7E/media/environment/dnrp/newsroom/2004/1186_snoq_flood_lg.ashx) |
Flood
season is almost here and yet the Snoqualmie community can rest a
little easier this fall now that work is essentially complete on a
multi-million dollar river-widening project to reduce the threat of
devastating floodwaters.
The
project team -- the City of Snoqualmie, King County and the U.S. Army
Corps of Engineers -- is inviting community members to join in
celebrating completion of the Snoqualmie 205 Flood Reduction Project on
September 29, 2 p.m., at the Salish Lodge.
"We
are delighted we were able to accomplish this for the people of the
Upper Snoqualmie Valley," said King County Executive Ron Sims. "This is
how it is supposed to work -- federal, county and city governments
working together with private industry to protect peoples' lives and
property."
Some
work still remains, but the widening of the river above Snoqualmie
Falls to open up a pair of bottlenecks in the river channel is
complete. During high river flows, the bottlenecks held up water and
contributed to the flooding of hundreds of homes and businesses in and
around the City of Snoqualmie, historically one of the most flood-prone
communities in the state.
"We
are elated," said Snoqualmie Mayor Fuzzy Fletcher. "The citizens who
have suffered from chronic flood losses are the biggest winners of this
project. This represents the first structural flood relief in the
history of our city. It's no coincidence that the National Flood
Insurance Program has paid more claims in the City of Snoqualmie than
in any other Washington city."
1990 Flood in the town of Snoqualmie
![1990 Flooding in the town of Snoqualmie](%7E/media/environment/dnrp/newsroom/2004/1190_snoq_flood_lg.ashx) |
Fletcher
pointed out that flood damages in the Snoqualmie area occur whenever
river flows exceed 30,000 cubic feet per second, which in the last 43
years has happened 25 times. Roughly two-thirds of the homes and
businesses in and around Snoqualmie were flooded in November 1990.
"It
has been a privilege to work with so many talented and caring partners
on such an important regional project," said Col. Debra Lewis,
Commander of the Seattle District, U.S. Army Corps of Engineers. "We
expect that these flood-control measures will provide immediate public
health and safety benefits. By reducing the frequency, duration and
depth of flood water, the project will prevent damages of an estimated
$837,000 per year."
The
Corps has identified more than 650 flood-prone structures in the
Snoqualmie area, including three public schools, eight churches, 39
commercial structures, 25 mobile homes and 577 houses.
The
channel excavation work has been completed under a $3.3 million dollar
contract that the Corps of Engineers awarded to Goodfellow Brothers,
Inc., of Wenatchee, WA. The contractor finished the in-river excavation
on September 14, and their remaining work should be complete in October.
Although
the channel excavation work is nearly finished, other portions of the
Snoqualmie project will continue into next year and beyond. The project
will remove an abandoned railroad bridge, part of which fell into the
river in 1990. It will also establish native vegetation on several
riverbank areas. Finally, the project includes a Downstream Assistance
Program that will provide a cost share to downstream property owners
who will raise their homes, barns, or other structures above 100-year
flood levels. Total cost of the entire project is estimated at $7.65
million, of which the Corps is funding $4.4 million.
For more information, please contact Rivers Section Senior Engineer Tom Bean at 206-296-8377. Project information is also available for review on the King County Web site.