PWR Sump Performance
Overview
Function of the Containment Sump
Description of the Safety Issues
Discovery of the Sump Performance Issue
NRC Activities
Public Meetings
Resolution Schedule
Regulatory Activities
Related Information
Historical Timeline
Frequently Asked Questions
Reports and Correspondence
Regulations and Guidance
Technical References
Regulatory References
Bulletin 2003-01
Generic Letter 2004-02
Other Correspondence

Resolution Schedule

The NRC is currently implementing its plan to have all pressurized‑water reactor (PWR) licensees perform a plant‑specific evaluation of the potential for excessive head loss across the containment sump screen because of the accumulation of debris on the containment sump screen. Key milestones from that plan to resolve Generic Safety Issue (GSI) 191, "PWR Sump Performance," are provided in the table below.

Based on the information available to date, continued operation of PWRs is justified until the plant‑specific evaluations are completed. To provide additional assurance until those evaluations are completed, the NRC asked the licensees of PWRs to implement interim compensatory measures. The NRC has reviewed the adequacy of the interim compensatory measures being implemented by licensees.

However, if the results ongoing NRC inspections and reviews indicate that unsafe conditions exist at any operating PWR, the NRC will take immediate plant‑specific actions to ensure the continued health and safety of the public. Also, if a licensee discovers that it is not in compliance with the NRC regulations during the implementation of the requested actions in Bulletin 2003‑01, it is required to take prompt corrective actions.

Date Activity Status
10/2008 Closure of GSI-191

Pending

06/2008 Complete Temporary Instruction 2515/166 inspections of plant changes

Ongoing

04/2008 Complete audit of selected plant analyses/modifications

Ongoing

02/2008 Initiate review of final supplemental generic letter responses

Pending

12/2005 Complete Temporary Instruction 2515/153 inspections of interim compensatory actions

Completed

12/2005 Close-out all Bulletin 2003-01 responses

Completed

03/2005 Licensees submit responses to generic letter

Ongoing

02/2005 Launch pilot program and identify pilot plants for application of sump evaluation methodology

Completed

01/2005 Public meeting on SE

Completed

12/2004 NEI 04-07 released (combining updated NEI evaluation methodology and SE)

Completed

12/2004 Issue safety evaluation (SE) on NEI evaluation methodology

Completed

12/2004 Participate in industry workshop on performing PWR sump evaluations

Completed

09/2004 Complete technical evaluation of NEI evaluation guidelines

Completed

09/2004 Issue generic letter requesting plant-specific evaulation of sump performance

Completed

varies Licensees implement compensatory measures

Ongoing

08/2004 Complete review of all Bulletin 2003-01 responses

Completed

07/2004 Receive revision to NEI evaluation methodology

Completed

05/2004 Receive new version of NEI evaluation methodology

Completed

03/2004 Workshop with industry on NEI Draft evaluation methodology technical issues

Completed

11/2003 Issue Regulatory Guide 1.82, Rev. 3

Completed

11/2003 Receive NEI Draft Containment Sump Evaluation Methodology and obtain contract assistance from Los Alamos National Laboratory

Completed

10/2003 Issue Temporary Instruction 2515/153 related to Bulletin 2003-01

Completed

06/2003 Issue Bulletin 2003-01 requesting compensatory measures regarding sump performance

Completed

09/2002 NEI guidance document, NEI 02-01, published

Completed

09/2001 Complete technical assessment of PWR sump blockage

Completed