skip navigation links 
 
 Search Options 
Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us blue spacer  
secondary page banner Return to NRC Home Page
Power Uprates
Approved Applications
Pending Applications
Expected Applications

Pending Applications for Power Uprates

The following power uprates are currently under review by the NRC. The licensees for the following plants have not been authorized by the NRC to operate the plants at power levels that reflect the following increases.

(TYPE -- S = Stretch; E = Extended; MUR= Measurement Uncertainty Recapture)
(TBD = To Be Determined)

NO. PLANT % UPRATE MWt SUBMITTAL DATE PROJECTED COMPLETION
DATE
TYPE
1 Browns Ferry Unit 2 15 494 06/25/2004 Fall 2008 E
2 Browns Ferry Unit 3 15 494 06/25/2004 Fall 2008 E
3 Browns Ferry Unit 1 15 494 06/28/2004 Fall 2008 E
  Total MWt   1482
     
  Total MWe   494      


Privacy Policy | Site Disclaimer
Wednesday, August 13, 2008