Skip to contentUnited States Department of Transportation - Federal Highway AdministrationSearch FHWAFeedback

Asset Management

<< Previous Contents Next >>

The Georgia Experience

Agency Facts

5. What Has Georgia Learned?

GDOT has learned that it can defend its LCCA because its methodology is sound - it has adopted and implemented practices based on respected methodologies. Additionally, Georgia has learned some valuable lessons by partnering with FHWA.

A review conducted by the FHWA-Georgia Division Office and the FHWA Resource Center of an LCCA conducted by GDOT on a project on the I-475 mainline, for example, revealed that GDOT utilized an analysis period that did not accurately demonstrate the differences in lifecycle costs associated with the various design alternatives. FHWA worked with GDOT to extend the analysis period, which dramatically changed the results of the analysis.

Working through this process with the FHWA has not only helped GDOT fine-tune its LCCA application but also improve its working relationship with FHWA. That, in turn, led to the two agencies coming together in May 2006 for a frank discussion of what the GDOT is looking for in terms of LCCA software. As a result of those conversations, the next release of RealCost will include some of the very features that GDOT has requested.

Figure 6: Aerial view of downtown Atlanta, including Turner Field.
Aerial photograph of Atlanta's Turner field, I-75, and surrounding area.

Table 1: The decision matrix for Georgia's LCCA on I-85.
Decision Matrix

Initial Construction Agency Costs Maintenance Costs (nominal / discounted) Annualized Agency Costs (LCC) Annualized User Costs (LCC) Salvage Value Expected Life (Rehabilitation Frequency) Construction (production rate – initial days) Ease of Repairing / Maintaining (production rate – rehab days) Constructibility / Traffic Control (Lifts) Proven Design in Agency Total Score Rank
Relative Importance 50% 25% 5% 5% 2% 2% 2% 2% 2% 5%   
ALTERNATIVE 1-CRC Unbonded Overlay Mainline Overlay -Full Replacement
@ Overpass Bridges
0.74

37.2
0.86

21.6
0.99

5.0
1.00

5.0
0.00

0.0
0.80

1.6
0.78

1.6
1.00

2.0
1.00

2.0
0.50

2.5
78.5 3
ALTERNATIVE 2-CRC Unbonded Overlay Mainline Overlay – Raise Bridges 0.75

37.6
0.86

21.6
1.00

5.0
1.00

5.0
0.00

0.0
0.80

1.6
0.78

1.6
1.00

2.0
1.00

2.0
0.50

2.5
78.8 2
ALTERNATIVE 3-CRC Full Depth Mainline 0.70

34.9
1.00

25.0
0.95

4.7
0.92

4.6
1.00

2.0
1.00

2.0
0.78

1.6
1.00

2.0
0.83

1.7
1.00

5.0
83.5 1
ALTERNATIVE 4-HMA HMA Overlay PCC Mainline Overlay – Full Replacement @ Overpass Bridges 1.00

50.0
0.10

2.5
0.82

4.1
0.20

1.0
0.00

0.0
0.32

0.6
1.00

2.0
0.16

0.3
0.40

0.8
0.50

2.5
64.0 4
ALTERNATIVE 5-HMA HMA Overlay PCC Mainline Overlay – Raise Bridges 0.94

46.9
0.10

2.5
0.79

4.0
0.20

1.0
0.00

0.0
0.32

0.6
1.00

2.0
0.16

0.3
0.40

0.8
0.50

2.5
60.7 5
ALTERNATIVE 6-HMA Full Depth Mainline 0.77

38.4
0.13

3.1
0.75

3.7
0.27

1.3
0.00

0.0
0.40

0.8
0.79

1.6
0.17

0.3
0.33

0.7
1.00

5.0
55.0 6
<< Previous Contents Next >>

Events

More Information

Contact

Nathaniel Coley
Office of Asset Management
202-366-2171
E-mail Nathaniel

 
This page last modified on 02/20/08
 

FHWA
United States Department of Transportation - Federal Highway Administration