Part 36 (Schedule 31) approved permissible
diesel-powered equipment presently operating in underground coal mines must
comply with the requirements specified under sections 75.1907(b)(2) and (b)(3)
of Part 75 by November 25, 1999. Manufacturers have begun to apply for and
receive new approvals for their existing machines that have been modified to
meet these requirements. The new approval number issued to this upgraded
Part 36 (Schedule 31) permissible diesel-powered equipment will be a two hundred number or higher (31-200, 31-201, etc.).