skip navigation
Text Size small medium large  

skip navigation
Energy Supply & Demand
Electric
Hydropower
Gas
Liquefied Natural Gas (LNG)
Safety and Inspections
Environment
Industry Activities
General Information
FERC's LNG Highlights
Project Review Process
The Importance of LNG
Laws and Regulations
Related Websites
Oil
 
Find information about projects in your area
   
  Find projects in your area
   
> For Citizens: LNG Overview
> Enforcement Hotline
> Calendar: Conferences
 
Industries

LNG - Project Review Process - Decision
    Upon Commission approval, the developer will receive:

    1. A Commission Order stating its decision on whether to approve construction and operation of the LNG terminal;
    2. Market rate authority; and
    3. Conditions that must be met prior to construction, usually originating from the Cryogenic Design and Inspection Manual.

    The developer must also secure the following prior to construction from the state in which construction will occur:

    1. Section 401 permits - water quality certificate;
    2. Section 404 permits - dredge and fill permit; and
    3. Coastal Zone Management clearance.

    < Review Post-Decision >




Updated: June 30, 2005