LNG - Project Review Process - Decision
Upon Commission approval, the developer will receive:
- A Commission Order stating its decision on whether to approve
construction and operation of the LNG terminal;
- Market rate authority; and
- Conditions that must be met prior to construction, usually
originating from the Cryogenic Design and Inspection Manual.
The developer must also secure the following prior to construction
from the state in which construction will occur:
- Section 401 permits - water quality certificate;
- Section 404 permits - dredge and fill permit; and
- Coastal Zone Management clearance.
|
|
|
|
|