This grid is still considered a "relatively untested deepwater or remote
area. "You must submit the following information per NTL 2006-G04:
1.Waste and Discharge Information (§§ 250.217 and 250.248) (a) Projected generated wastes. (5) Deepwater development operations.
2.Waste and Discharge Information (§§ 250.217 and 250.248) (b) Projected ocean discharges. (4) Deepwater development operations.
3.Support Vessels and Aircraft Information (§§ 250.224 and 250.257) (d) Solid and liquid wastes transportation. (4) Deepwater development operations. Preparation of a Grid EA is not applicable to Grids 18, 19, 20, or 21.
***
You must submit a plan for an ROV monitoring survey per NTL
2008-G04.
****
You do not have to submit a plan for an ROV monitoring survey per NTL
2008-G04.