Quality Assurance Plan Documents for the Mixed Oxide Fuel Fabrication Facility
The following documents are associated with the Quality Assurance Plan for MOX FFF.
The following links on this page are to documents in Adobe Portable Document
Format (PDF). See our Plugins, Viewers, and
Other Tools page for more information. For successful viewing of PDF documents on our site please be sure to use the latest version of Adobe.
Quality Assurance Plan Documents |
Title and Date |
08/03/2007 D. Leach Ltr Re: Acceptance Review of the Mixed Oxide Project Quality Assurance Plan |
MOX Project Quality Assurance Plan (MPQAP) Revision 5 |
10/06/2006 Observation of DCS' Quality Assurance Audit for the MFFF |
1/11/2006 Revision 4, Change 1 of the MOX Project Quality Assurance Program |
Telephone Summary: MOX Quality Assurance Program Discussion, dated August 11, 2004 |
March
15-26, 2004, In-Office Review Summary: Duke Cogema Stone & Webster
Quality Assurance Program for the Mixed Oxide Fuel Fabrication Facility,
dated April 9, 2004 |
DCS MOX Project Quality Assurance Plan (MPQAP) Revision 4, dated November 12, 2003 |
NRC
Technical Review of Duke Cogema Stone & Webster Quality Assurance
Program, dated January 1, 2003 |
MOX
Project Quality Assurance Plan (MPQAP) Response to NRC Conditional
Approval and MPQAP
Revision 3, dated March 3, 2002 |
DCS
Quality Assurance Program for Construction of the MOX Fuel Fabrication
Facility, dated October 1, 2001 |
Response
to Draft SER for MPQAP, Revision 2, dated September 4, 2001 |
Draft Safety Evaluation Report for the MOX Project Quality
Assurance Plan, Rev. 2, dated August 17, 2001 |
Response
to NRC Request for Additional Information on the Mixed Oxide Quality
Assurance Plan, Rev. 2, dated July 18, 2001 |
Mixed Oxide Fuel Fabrication Facility Construction Application
Authorization Request - Request for Additional Information, dated June
21, 2001 |
NRC
Request for Additional Information #2 on MOX FFF Quality Assurance Plan
Updated June 19, 2001 |
MOX Construction Application Acceptance Letter, dated
March 28, 2001 |
Quality
Assurance Plan Updated Jan 24, 2001 to add topics related to
construction, dated January 24, 2001 |
DCS
Response to NRC's Request for Additional Information, dated January
29, 2001 |
Quality
Assurance Plan Summary of in-office review of MOX QA documents,
dated November 3, 2000 |
Quality Assurance Plan
Results of the NRC's initial acceptance review of the MOX QA
program, dated October 6, 2000 |
Quality Assurance Plan DCS's response to NRC's request for additional information |
Quality Assurance Plan
Rev. 1 of QA Plan submitted by DCS, dated June 22, 2000 |
|