Bechtel
Constructors Corp., ARB No. 97-149 (ARB Mar. 25,
1998)
U.S. Department of Labor
Administrative Review Board
200 Constitution Avenue, N.W.
Washington, D.C. 20210
ARB CASE NO. 97-149
(Formerly ARB Case No. 95-045A)
(ALJ CASE NO. 91-DBA-3)
DATE: March 25, 1998
In the Matter of:
BECHTEL CONSTRUCTORS
CORPORATION,
Prime Contractor
RODGERS CONSTRUCTION
COMPANY,
Prime Contractor
BALL, BALL AND BROSAMER, INC.,
Prime Contractor
THE TANNER COMPANIES,
Subcontractor
With respect to laborers and mechanics
employed by the Subcontractor on Contracts
4-CC-30-02120 (Brady Pumping Plant), Central
Arizona Project ("CAP"), 5-CC-30-02770 (Red
Rock Pumping Plant, CAP), 4-CC-30-01480
(Picacho Pumping Plant, CAP), 5-CC-30-03560
(Tucson Aqueduct, Reach 3, CAP).
DECISION AND ORDER OF REMAND
This matter is before the Administrative Review Board, United States
Department of Labor, pursuant to the Davis-Bacon Act (the Act), 40 U.S.C. §276a et
seq. and the regulations at 29 C.F.R. Parts 6 and 7. The case is pending on the Petition for
Review filed by the Administrator, Wage and Hour Division (Administrator), seeking review of
the Decision and Order on Remand (D.O.R.) issued by the Administrative Law Judge on August
21, 1997. For the following reasons, we reverse the D.O.R., grant the Administrator's Petition
for Review, and remand this matter for further action consistent with this decision.
BACKGROUND
The ALJ issued an initial Decision and Order (D. and O.) in this matter on
May 5, 1995, that denied the Administrator's request to withdraw from factual stipulations entered
[Page 2]
into prior to the hearing. The stipulations involved the distances between certain batch plants and
the sites of construction for three pumping stations on the Central Arizona Project (CAP). In the
May 5, 1995 D. and O., the ALJ relied on the stipulations to support a finding that the disputed
work was performed at locations too remote from the actual "site of the work,"
i.e. those locations where the construction work would remain upon completion, to
be covered by the applicable regulations. Therefore, the ALJ dismissed the Administrator's DBA
prevailing wage and Contract Work Hours and Safety Standards Act, 40 U.S.C. §327
et seq., overtime claims against the Respondents.
The Administrator sought review of the ALJ's D. and O. with respect to the
findings concerning the three pumping stations. Briefs were filed and an oral argument was held.
The Board issued a decision reversing the ALJ's conclusions concerning the pumping stations and
remanding the matter. Bechtel Constructors Corporation, et al. (Bechtel
I), ARB Case No. 95-045A, July 16, 1996. The facts of this case are thoroughly discussed
in Becthel I and we will not repeat them here, other than as necessary to show the
basis for our reversal of the August 21, 1997, D.O.R.
DISCUSSION
I. The Board's Decision in Bechtel I
In discussing the record evidence related to the issue of whether the disputed
work was performed directly upon the site of the work, the Board in Bechtel I stated:
The facts of this case clearly suggest that the work
performed at the temporary batch plants satisfy the test set out in Section 5.2(l)(1).
Aerial photographs of the Red Rock and Picacho sites place the temporary batch
plants on land integrated into the work area adjacent to the pumping plants.
Workers at the batch plants were employed on the sites of work equally as much
as the workers who cleared the land and the workers who inventoried, assembled,
transported or operated tools, equipment or materials on nearby or adjacent
property. Unless the Board were also to exclude these workers, and in doing so
largely nullify the wage protections of the DBA, there is no principled basis for
excluding the batch plant workers.
Tanner might concede that the batch plants
were located proximate to the pumping stations, but argue that concrete
from the batch plant was also transported and used on aqueduct construction
miles from the plant. This argument is unpersuasive in that it is the nature
[Page 3]
of such construction, e.g. highway, airport and aqueduct construction, that the work
may be long narrow and stretch over many miles. Where to locate a storage area or a batch plant
along such a project is a matter of the contractor's convenience and is not a basis for excluding
the work from the DBA. The map of the project introduced at hearing by Tanner, RX 22,
abundantly illustrates that the project consisted of miles of narrow aqueduct connected by pumping
stations. The only feasible way to meet the needs of the aqueduct construction was to have the
concrete prepared at a convenient site and transported to the precise area of need. This equally
holds true for the storage and distribution of other materials and equipment. Faced with such a
project, the Board finds that work performed in actual or virtual adjacency to one portion of the
long continuous project is to be considered adjacent to the entire project. See, L.P. Cavett
Co. v. United States Dep't. of Labor, supra at 979-980.
1 The incorrect stipulations
- found in Parties' Joint Exhibit 1 - stated:
These three batch plants were located from one-half to
fifteen miles from the physical places where the construction
called for in these contracts remained when the work was
completed.
2 The ALJ
discredited employee testimony on the basis that "these people will be awarded back pay if
DOL is successful in this case. It is to their benefit to have the batch plants located as close as
possible to the construction sites." D. O. R. at 5. Similarly, the ALJ discredited the
testimony of Respondent Tanner's "management employees who would be expected to be
biased in favor of Tanner." Id.
3 In Bechtel
I we found, based upon the photographic evidence, that the stipulations regarding the
distances between the batch plants were "known to be false." At 4. The ALJ opines
that this statement is inaccurate, D. O. R. at 2, and we reject this purported correction of our prior
order for the same reason.
4 We reject
Respondent Tanner Companies Motion to Strike BCTD's brief since it was filed within the time
limit set for reply briefs.
5 If anything,
reference to 29 C.F.R. §5.2(l)(2) clarifies and limits the coverage provisions of 29 C.F.R.
§5.2(l)(1) by virtue of the requirement that "batch plants . . . are part of the site
of the work provided they are dedicated exclusively, or nearly so, to performance of the
contract or project." (Emphasis in original.)
6The Wage Appeals
Board previously endorsed use of the Mt.Clemens methodology for computing back
wages where absolute precision is impossible. See Apollo Mechanical, Inc., WAB
Case No. 90-42, Mar. 13, 1991, at slip op. 2-3. See also P.B.M.C., Inc., WAB Case
No. 87-57, Feb. 8, 1991, where the WAB explained that under Mt. ClemensPottery, an employee who seeks to recover unpaid wages "has the burden of
proving that he performed work for which he was not properly compensated." 328 U.S. at
687.
However, where an employer's records are inaccurate or incomplete,
employees are still entitled to the statutorily mandated wage even though the incompleteness of
the record introduces some imprecision into the calculation. In such circumstances, an employee
meets his burden "if he proves that he has in fact performed work for which he was
improperly compensated and if he produces sufficient evidence to show the amount and extent of
that work as a matter of just and reasonable inference." 328 U.S. at 687. The employer
then has the burden to demonstrate the precise number of hours worked or to present evidence
sufficient to negate "the reasonableness of the inference to be drawn from the employee's
evidence." 328 U.S. at 688. In the absence of such a showing, the court "may then
award damages to the employee, event though the result be only approximate."
Id. Furthermore, Mt. ClemensPottery provides specific
guidance on the responsibilities of the trier of fact: "Unless the employer can provide
accurate estimates [of hours worked], it is the duty of the trier of facts to draw whatever
reasonable inferences can be drawn from the employees' evidence . . . ." Id.
at 693.