[Page 8]
Conclusion
The Administrator's June 3, 2004 final determination that the work Sanders performed for ASSI at the pit used for the Crow Reservation road project was not subject to the prevailing wage provisions of the DBA is unreasonable because she did not discuss or apply the definition for "site of the work" at 29 C.F.R. § 5.2(l). Therefore, we Vacate the final determination and Remand this matter to the Administrator with instructions to proceed in a manner consistent with this opinion.
SO ORDERED.
OLIVER M. TRANSUE
Administrative Appeals Judge
DAVID G. DYE
Administrative Appeals Judge
[ENDNOTES]
1 40 U.S.C.A. §§ 3141-3148 (West Supp. 2003). The regulations that implement the Act are found at 29 C.F.R. Parts 1 and 5 (2007).
2 40 U.S.C.A. § 3142(a).
3 Id.
4 29 C.F.R. Part 1.
5 40 U.S.C.A. § 3142(b); 29 C.F.R. § 1.3.
6 See 29 C.F.R. § 1.2(a)(1).
7 Tab I.
8 Tab B at 1.
9 Sanders's "Appeal of Administrator's Adverse Decision Not Granting Prevailing Wage" (Sanders Appeal) at 3.
10 Tab H.
11 Id.
12 Tab K.
13 Tab D.
14 Tab B at 2.
15 Employees covered under the Walsh-Healy Act, 29 U.S.C.A. § 201 et seq. (West 1998), must be paid in accordance with the minimum wage requirements of the Fair Labor Standards Act, 41 U.S.C.A. § 35 et seq. (West 2000).
16 Tab B at 2.
17 See 29 C.F.R. § 7.9(a) ("Any party or aggrieved person shall have a right to file a petition for review with the Board (original and four copies), within a reasonable time from any final decision in any agency action under part 1, 3, or 5 of this subtitle.").
18 29 C.F.R. § 7.1(b)(2007). See Secretary's Order 1-2002, 67 Fed. Reg. 64,272 (Oct. 17, 2002).
19 29 C.F.R. § 7.1(e).
20 Miami Elevator Co. & Mid-American Elevator Co., Inc., ARB Nos. 98-086, 97-145, slip op. at 16 (Apr. 25, 2000). See also Millwright Local 1755, ARB No. 98-015, slip op. at 7 (May 11, 2000); Dep't of the Army, ARB Nos. 98-120, 98-121, 98-122, slip op. at 16 (Dec. 22, 1999) (under the parallel prevailing wage statute applicable to federal service procurements, the Service Contract Act, 41 U.S.C.A. § 351 et seq (West 1987)), citing ITT Fed. Servs. Corp. (II), ARB No. 95-042A (July 25, 1996) and Service Employees Int'l Union (I), BSCA No. 92-01 (Aug. 28, 1992).
21 Titan IV Mobile Serv. Tower, WAB No. 89-14, slip op. at 7 (May 10, 1991), citing Udall v. Tallman, 380 U.S. 1, 16-17 (1965).
22 40 U.S.C.A. § 3142(a), (c)(1).
23 29 C.F.R. § 5.2 (j)(1).
24 29 C.F.R. § 5.2 (j)(1)(iii) (emphasis added). See also 29 C.F.R. § 5.2(i) ("Building" and "work" "generally include construction activity as distinguished from manufacturing, furnishing of materials, or servicing and maintenance work," "unless conducted in connection with and at the site of such a building or work.) (emphasis added).
25 29 C.F.R. § 5.2(l). This regulation became effective on January 19, 2001, before the BIA's Crow Indian road construction project began, and, therefore, applies here. See 65 Fed. Reg. 80,268 (Dec. 20, 2000).
26 29 C.F.R. § 5.2(l)(2) applies to mineral pits. See Ball, Ball & Brosamer, Inc., WAB No. 90-18, slip op. at 10 (Nov. 29, 1990) (applying site of the work definition to a "sand and gravel pit" that provided sand, gravel and other aggregates).
27 Tab B at 1.
28 Sanders Appeal at 2-3.
29 Sanders appears before us pro se.
30 Tab N at 1.
31 Id.
32 Administrator's Statement at 10-11.
33 See Miami Elevator, slip op. at 16.
34 65 Fed. Reg. at 80,270.
35 65 Fed. Reg. at 80,272.
36 Id. In Bechtel, the DBA-covered construction project at issue consisted of the construction of 330 miles of aqueduct and pumping stations. Temporary batch plants located up to one half mile from each of the pumping stations under construction were built to provide concrete for the project. The Board considered whether the batch plants were located at the "site of the work." The Board noted that "it is the nature of construction, e.g., highway, airport and aqueduct construction, that the work may be long, narrow and stretch over many miles" and, therefore, concluded that "[w]here to locate a storage area or batch plant along such a project is a matter of the contractor's convenience and is not a basis for excluding the work from the DBA." Bechtel, slip op. at 7. And after examining aerial photographs, a map of the project, and the nature of the construction, the Board found that "work performed in actual or virtual adjacency to one portion of the long continuous project is to be considered adjacent to the entire project." Id.