Project Number | 566 |
Date of Summary | October 25, 2006 |
Subject | Assessment of the Acceptability and safety of Using Equipment, Particularly BOP and Wellhead Components at Pressures in Excess of the Rated Working Pressure |
Performing Activity | WEST Engineering Services |
Principal Investigator | Raleigh Williamson; Robert Olsen |
Contracting Agency | Minerals Management Service |
Estimated Completion | Completed |
Description |
Specific information was collected on Blowout Preventers (BOP)
and Well Head Components exposed to pressures greater than the Manufacturer
Allowable Working Pressure (MAWP) on platforms in the Gulf of Mexico Region.
Objectives:
|
Progress | Completed |
Reports |
|
AA
(67 pages)
![]() |