Project Number | 466 | ||||||||
Date of Summary | March 18, 2004 | ||||||||
Subject | Validation and Calibration of API-RP-2A Using Hurricane Lili to Update the Hurricane Andrew JIP Results that provided the basis for API Section 17. | ||||||||
Performing Activity | ABS Consulting | ||||||||
Principal Investigator | Frank Puskar | ||||||||
Contracting Agency | Minerals Management Service | ||||||||
Estimated Completion | Complete | ||||||||
Description |
This project updates the API-RP-2A section using Hurricane Lili data to validate and calibrate Hurricane Andrew's JIP results. Hurricane Lili did much damage to platforms, including the complete loss of some of the units. The general project objectives were to:
|
||||||||
Progress |
Complete |
||||||||
Reports | |||||||||
AA (5.668 KB) | ABS Consulting, Risk Consulting Division, Hurricane Lili's Impact on Fixed Platforms, June 2004. | ||||||||