*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date
of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will
be updated on a periodic basis. Please see the NRC Public Meetings Page
or contact the below listed PM for the latest information on meetings and status.
Milestones |
Schedule Date |
Actual Date |
Receive License Renewal (LR) Application |
08/27/07 |
08/28/07 |
FRN Published- Receipt & Availability |
09/24/07 |
09/24/07 |
FRN Published – Acceptability/Opportunity for Hearing and Intent/ Environmental Scoping Meeting |
10/26/07 |
10/26/07 |
FRN Published-Notice of Intent to Conduct Environmental
Scoping |
11/02/07 |
11/05/07 |
Audit - Environmental |
11/13/07 |
11/13/07 |
Public Meeting - LR Overview & Environmental Scoping |
11/27/07 |
11/27/07 |
Audit - Scoping & Screening Methodology |
12/03/07 |
12/03/07 |
Deadline for Filing Hearing Requests and Petitions
for Intervention |
12/26/07 |
12/26/07 |
Environmental Scoping Period Ends |
01/02/08 |
01/07/08 |
Environmental Requests for Additional Information (RAIs)
Issued |
02/04/08 |
02/04/08 |
Audit - Aging Management Programs (AMPs/TLAAs) |
03/03/08 |
03/03/08 |
Environmental RAIs - Response Received |
03/05/08 |
03/05/08 |
Audit - Aging Management Reviews (AMRs) |
Canceled |
Canceled |
Audit - 3rd Optional AMP/TLAA/AMR |
TBD* |
Canceled |
Safety RAIs - Issued |
06/30/08* |
06/30/08 |
Inspection - Regional |
06/23/08 |
06/23/08 |
Safety RAI - Responses Received |
07/30/08* |
07/30/08 |
Public Exit Meeting - Regional Inspections |
TBD |
|
Draft Supplemental Environmental Impact Statement (SEIS) - Issued |
09/17/08 |
|
EPA FRN Published - Availability / Comment on draft
SEIS |
09/25/08 |
|
Public Meeting - Draft SEIS |
10/30/08* |
|
Safety Evaluation Report (SER) with Open Items - Issued |
12/29/08* |
|
End of draft SEIS Comment Period |
12/03/08 |
|
Inspection - Final Optional |
TBD |
|
ACRS Subcommittee Meeting on SER with Open Items |
02/09* |
|
SER with Open Items - Responses Received |
03/09* |
|
Regional Administrator's letter - Issued |
TBD |
|
SER - Issued |
05/29/09* |
|
ACRS Full Committee Meeting on SER |
07/09* |
|
Final SEIS - Issued |
05/13/09 |
|
EPA FRN Published - Availability of Final SEIS |
05/22/09 |
|
ACRS Letter – Issued |
07/09* |
|
Staff Recommendation to Director, NRR |
08/09* |
|
Decision Director NRR - Approval (25 months if no hearing)) |
09/28/09* |
|
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment
periods on rules, renewal guidance, and other documents. The
Reactor License Renewal Public Involvement page
provides general information to help the public participate.