U.S. Department 400 Seventh Street, S.W. of Transportation Washington, D.C. 20590 Pipeline and Hazardous Materials Safety Administration Mr. R. Alan Englehart Vice President, Engineeringloperations Texas Gas Transmissions, LLC Post Office Box 20008 Owensboro, Kentucky 42301 RE: CPF NO. 2-2006-1 004 Dear Mr. Englehart: Enclosed is the Final Order issued by the Associate Administrator for Pipeline Safety in the above-referenced case. It makes a finding of violation and requires certain corrective action. When the terms of the compliance order are completed, as determined by the Director, Southern Region, this enforcement action will be closed. Your receipt of this Final Order constitutes service of that document under 49 C.F.R. Ħħ 190.5. Sincerely, James Reynolds Pipeline Compliance Registry Office of Pipeline Safety Enclosure cc: Ms. Linda Daugherty, Director, Southern Region, OPS CERTIFIED MAIL - RETURN RECEIPT REOUESTED DEPARTMENT OF TRANSPORTATION PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION OFFICE OF PIPELINE SAFETY WASHINGTON, D.C. 20590 In the Matter of ) ) Texas Gas Transmission, LLC, 1 CPF No. 2-2006-1004 Respondent. FINAL ORDER Between August 9,2005 and August 25,2005 and, pursuant to 49 U.S.C. 3601 17, representatives of the Pipeline and Hazardous Materials Safety Administration (PHMSA), Southern Region, Office of Pipeline Safety (OPS), and the Kentucky Public Service Commission conducted a gas integrity management inspection of Respondent's integrity management program (IMP), in Owensboro, Kentucky. As a result of the inspection, the Director, Southern Region, OPS, issued to Respondent, by letter dated March 9, 2006, a Notice of Probable Violation and Proposed Compliance Order (Notice). In accordance with 49 C.F.R. 3 190.207, the Notice proposed finding that Respondent violated 49 C.F.R. Part 192 and proposed that Respondent take certain measures to correct the alleged violation.. Respondent responded to the Notice by letter dated, April 10,2006 (Response). Respondent did not contest the allegation of violation but offered an explanation and provided information concerning the corrective actions it has taken to comply. Respondent did not request a hearing, and therefore has waived its right to one. FINDINGS OF VIOLATION (Uncontested) In its Response, Respondent did not contest the alleged violation in the Notice. Accordingly, I find that Respondent violated the following section of49 C.F.R. Part 192, as more fully described in the Notice: 49 C.F.R. 3 192.917(c) -Failure to conduct a risk assessment that follows ASMEIANSI B3 1.8S, section 5, and considers the identified threats for each covered segment; failure to use the risk assessment to prioritize the covered segments for the baseline and continual reassessments (33 192.9 19, 192.92 1, 192.937), and to determine what additional preventive and mitigative measures are needed (3 192.935) for the covered segment. Respondent's risk assessment, analysis and risk ranking algorithm utilized for the covered pipeline segments did not include consideration of failure consequences factors which is required by 49 C.F.R. Ħħ 192.91 7(c). This finding of violation will be considered a prior offense in any subsequent enforcement action taken against Respondent. COMPLIANCE ORDER The Notice proposed a compliance order with respect to Items lfor violations of 49 C.F.R. Ħħ192.917(c). Under 49 U.S.C. Ħħ 601 18(a), each person who engages in the transportation of gas or who owns or operates a pipeline facility is required to comply with the applicable safety standards established under chapter 601. Pursuant to the authority of 49 U.S.C. Ħħ 601 18 (b) and 49 C.F.R. Ħħ 190.2 17, Respondent is ordered to take the following actions to ensure compliance with the pipeline safety regulations applicable to its operations. Respondent must - 1. Re-run all risk assessments, analysis and risk ranking of all covered segments in your pipeline system, consider failure consequence factors and all information relevant to determine the risk associated with pipeline operation, as required by 49 C.F.R. Ħħ 192.917(c) and ASMEIANSI B3 1.8S, section 3 and 5. Complete this item within 180 days of receipt of this Order. 2. Submit the new risk assessments, analysis and risk ranking documentation on all covered pipeline segments that include consideration of failure consequence factors and all information relevant to determine the risk associated with your covered pipeline segments. Complete this item within 180 days of receipt of this Order. 3. Submit documentation and evidence of completion of these actions to Ms. Linda Daugherty, Director, OPS, Southern Region, Pipeline and Hazardous Materials Safety Administration, 233 Peachtree Street, Suite 600, Atlanta, GA 30303. The Director, OPS, Southern Region may grant an extension of time for compliance with any of the terms of this order for good cause. A request for an extension must be in writing and adequately justify the reasons for the extension. Failure to comply with this Final Order may result in the assessment of civil penalties of up to $100,000 per violation per day, or in the referral of the case for judicial enforcement. Under 49 C.F.R. 5 190.2 15, Respondent has a right to submit a Petition for Reconsideration of this Final Order. The petition must be received within 20 days of Respondent's receipt of this Final Order and must contain a brief statement of the issue(s). -The te&s of the order, including any required corrective action, remain in full effect unless the Associate Administrator, upon request, grants a stay. The terms and conditions of this Final Order are effective on receipt. a y $erard Date Issued A ciate Administrator for Pipeline Safety