March 16, 2000

Previous March Next

Sun

Mon

Tues

Wed

Thur

Fri

Sat

      1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31  
             

MISSION: STS-101 -- 3rd ISS Flight (2A.2a) - SPACEHAB DM

VEHICLE Atlantis/OV-104/
LOCATION Orbiter Processing Facility bay 3
TARGET KSC LAUNCH DATE/TIME NET April 17, 2000 at about 7:03 p.m. (under review)
TARGET KSC LANDING DATE/TIME April 28, 2000 at about 3:30 p.m.
LAUNCH WINDOW up to 10 minutes
MISSION DURATION 11 days
CREW Halsell, Horowitz, Weber, Williams, Voss, Helms, Usachev
ORBITAL ALTITUDE and INCLINATION 160 nautical miles/51.6 degrees
Shuttle Processing Note
Shuttle managers today announced a target launch date of no earlier than April 17 for Shuttle Atlantis. The new date accommodates Shuttle processing and flight crew training requirements.

Following minor delays during rollover preparations, orbiter Atlantis is now scheduled to rollover to the Vehicle Assembly Building later today pending weather constraints. Once Atlantis is mated to the external tank and solid rocket boosters in VAB high bay 3, main engine No. 1 will be replaced. The work will be completed in the VAB over a period of about 3 days. Space Shuttle Atlantis is currently slated for rollout to Launch Pad 39A on March 24.


MISSION: STS-92 -- 5th ISS Flight (3A) -- Z-1 Truss, PMA-3
VEHICLE Discovery/OV-103
LOCATION OPF bay 1
TARGET KSC LAUNCH DATE/TIME TBD
TARGET KSC LANDING DATE/TIME TBD
MISSION DURATION 11 days
CREW Duffy, Melroy, Wakata, Chiao, Wisoff, Lopez-Alegria, McArthur
ORBITAL ALTITUDE and INCLINATION 160 nautical miles/51.6 degrees

Shuttle Processing Note
Auxiliary power unit leak and functional tests are complete. Leak checks of Discovery's orbiter docking system continue. The integrated hydraulic test is scheduled this week. Robot arm servicing begins this week.


MISSION: STS-97 -- 6th ISS Flight (4A) -- PV Module P6
VEHICLE Endeavour/OV-105
LOCATION OPF bay 2
TARGET KSC LAUNCH DATE/TIME TBA
TARGET KSC LANDING DATE/TIME TBA
MISSION DURATION 9 days
CREW Jett, Bloomfield, Tanner, Noriega, Garneau
ORBITAL ALTITUDE and INCLINATION 173 nautical miles/51.6 degrees

Shuttle Processing Note

Testing of Endeavour's radiators is complete. Orbiter maneuvering system pod functional tests continue and preparations to remove Endeavour's external airlock are ongoing.

 

For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

09/22/2000

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc./
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director