PIC is Back Online - PIC offline for a half day
due to hardware problems
October
25, 2004: PIC was offline unexpectedly on Monday for more than
5 hours due to a hardware problem. The problem that was found has
been resolved and no data was lost. PIC is running normally again.
Technical
staff had installed new hardware during the weekend and it did not
function properly. We apologize for the inconvenience and thank
you for your patience.
PIC Hardware Problem Fixed Friday - Database
server locked up; had to be restarted
October
4, 2004: PIC was offline unexpectedly on Friday for about 40
minutes due to a hardware problem. The problem that was found has
been resolved and no data was lost. PIC is running normally again.
Technical
staff are investing the root cause of the problem in order to prevent
a recurrence. We thank you for your patience.
PIC offline for Release on Weekend - PIC access
shutdown 4 pm EDT Friday
September
22, 2004: Access to the PIC production system will be shut down
at 4:00 p.m. Eastern Time (1:00 p.m. Pacific) on Friday, September
24, to permit installation and testing of PIC Release 5.5. All
users must exit the system by that time. (Failure to do so may delay
the release.) Please do not try to access the system during this
weekend.
PIC
will remain offline for the weekend to permit thorough testing of
this large release in a production environment. We expect PIC to
be back in operation sometime during the day on Monday, September
27, if not earlier.
We
regret this inconvenience to our users but feel it is necessary.
It should be noted that users will be able to submit month, quarter
and FY-end reports for 9/30 until midnight on that date.
PIC Offline Friday Night - PIC will be down starting
at 8 pm Friday night
September 3, 2004: PIC will be offline for scheduled maintenance
beginning Friday, September 3, at 8.00 pm Eastern (5:00 pm Pacific)
and will remain offline until sometime during the day Saturday.
PIC Upload Problems Resolved - Form 50058 data
uploads working again.
September 2, 2004: PIC Form 50058 uploads are working properly
again. A conflict with another PIH system caused the problem, which
has now been resolved. No uploaded data files were lost.
Users should resume uploading Form 50058 data normally. We are
monitoring the system to ensure there is no recurrence. We apologize
for the inconvenience and thank you for your patience.
SEMAP certifications for FYE 6/30 PHAs being
assessed must be submitted in PIC by Aug. 29, 2004.
August 17, 2004: For all Section 8 PHAs with FYE of 6/30/2004
and with 250 or more vouchers under contract as well as smaller
Section 8 PHAs that are designated "Troubled", your SEMAP certification
must be submitted in PIC no later than Sunday, August 29, 2004.
PHAs with less than 250 vouchers under contract who are not designated
"Troubled" need not submit a certification this time but may do
so if they so choose. If you submit a certification, it will
be scored.
If you are not sure whether you are required to submit, call your
local HUD Field Office. If you are having technical problems with
PIC SEMAP, call PICHelp at 1-800-366-6827.
PIC technical problems reported to PICHelp after the 8/29 deadline
will not be considered as justification for a late FYE 6/30/04 certification.
Two Form-50058 Error Codes Reversed
August
6, 2004: As part of Release 5.4, two new error codes were added
to PIC Form 50058 Submission submodule. They are:
- 5279 - Last action submitted for this tenant was Portability
Move-Out. Only VOID (from the same PHA) or Portability Move-In
(from a different PHA) can be sent. No other actions can be accepted.
- 5280 - Portability Move-Out record for this Head of Household
for the same Program Type within a different PHA does not exist.
Portability Move-In cannot be accepted.
We have found that their numbers and explanations in the error
reports are reversed. This means: when the error message says "5279",
the error is 5280 (as described above) and when it says "5280",
the error is 5279 (as described above).
Users can refer to the list of error codes, which can be downloaded
from the Form
50058 Forms, Guidebooks and Tools web page.
This will be corrected in the next PIC release. We apologize for
the confusion.
Major PIC Database Failure
July
16, 2004: PIC suffered a major database system failure on Tuesday
(7/13). The PIC system will not be available to users until the
failure can be repaired. The system is being restored from the Monday
night backup and will be available again at 5:00 pm (Eastern) today
(Friday).
As
part of the restoration, all Form 50058 uploads, online EOPs and
Alt. ID creations received since 11:00 pm (Eastern) Monday are being
restored into the database and users will not need to resubmit
them. Except for Form 50058 uploads, online EOPs and Alt.
ID creations, any other data entered into PIC submodules on Tuesday
or Wednesday (including password and user access changes) will
need to be re-entered.
We
apologize for the inconvenience to our users and ask for your cooperation.
SEMAP Certifications for FYE 3/31 - SEMAP certification
problem resolved
April
22, 2004: PIC SEMAP has not been accepting certifications
from 3/31 FYE PHAs as it should since April 1. The PIC maintenance
team has now corrected the problem and HAs are able to prepare and
submit SEMAP certifications for FYE 3/31 at this time.
SEMAP
certifications for FYE 3/31 PHAs being assessed must be submitted
in PIC by Sunday, May 30, 2004.
For
all Section 8 PHAs with FYE 3/31/2004 and with 250 or more vouchers
under contract as well as smaller Section 8 PHAs that are designed
"Troubled", your SEMAP certification must be submitted
in PIC no later than Sunday, May 30, 2004. PHAs with less than 250
vouchers under contract who are not designated "Troubled"
need not submit a certification this time but may do so if they
so choose. If you submit a certification, it will be scored.
If
you are not sure whether you are required to submit, call your local
HUD Field Office. If you are having technical problems with PIC
SEMAP, call PICHelp at 1-800-366-6827.
Sect. 8 Reports Working Properly - Data problems
corrected and reports re-run
April
14, 2004: The data problems with the monthly Section 8 "Delinquency"
and "RCR" reports previously reported here have been corrected.
The data in the reports should now accurately reflect
conditions at the end of March 2004.
Thank
you for your patience.
Sect. 8 Reports Error - Faulty data in Sect. 8
Delinq. & RCR Reports for 3/31/04
April
5, 2004: Due to data calculation bug introduced inadvertently
in the last PIC release, the values for "50058 Required"
units were almost doubled for all Section 8 programs and, consequently,
their reporting rates were halved. This data is erroneous.
We
are working on an emergency release to correct the problem, which
should be installed and tested by next week. We apologize for any
worries this might have caused users.
Demo-Dispo processing problem fixed - "IBS" application
function properly for removals
March
29, 2004: PIC Demo-Dispo module, which was not properly processing
removals from inventory where the original Demo-Dispo application
number began with "IBS" is now processing them properly.
PHAs
may now enter the actual removals in PIC Demo-Dispo as described
in the Demo-Dispo User Manual for all application types
The
PIC Demo-Dispo User Manual can be downloaded in "pdf" format from
www.hud.gov/offices/pih/systems/pic/userguides.cfm
PIC Release 5.3 installed in record time
March
21, 2004: We are pleased to report that PIC Release 5.3 installation
and testing was completed in record time. In addition, the problems
with Viewer Reports and PIC Building & Unit Download requests
have been corrected and they can once again be accessed.
Late
Saturday night the system was brought back online for users. Go
to the PIC Home Page for a link to the
change in Release 5.3 under "What's New".
Page display error in Viewer Reports & Downloads
March
1, 2004: A "Page cannot be displayed" error cropped
up in Viewer Reports and in Download due to a data mismatch caused
by the Leap Day (2/29). The underlying data is not affected, merely
the display of it. The resolution to the problem is being tested
in PICTEST. Once testing is completed, the fix will be installed
in PIC production as soon as it can be arranged. We apologize for
the inconvenience.
SEMAP certifications due by 2/29/04
February
26, 2004: Reminder - For all Section 8 PHAs with FYE of 12/31/2003
and with 250 or more vouchers under contract as well as smaller
Section 8 PHAs that are designated "Troubled", your SEMAP
certification must be submitted in PIC no later than Sunday, February
29, 2004 (3 days to go). PHAs with less than 250 vouchers under
contract who are not designated "Troubled" need not submit
a certification this time but may do so if they so choose. If you
submit a certification, it will be scored. If you are not sure whether
you are required to submit, call your local HUD Field Office. If
you are having technical problems with PIC SEMAP, call PICHelp at
1-800-366-6827.
Indicators 11-12 are off in SEMAP
January
23, 2004: Indicators 11 (Pre-contract HQS inspections) and 12
(Annual HQS inspections) are turned off and not being used at all
in SEMAP scoring. (Indicator 12 has been turned off since 2001.
Indicator 11 was turned off in 2002 due to a data processing problem).
Indicator 12 is scheduled to be turned on again effective for the
3/31/2004 FYE. However, Indicator 11 will remain turned off until
a date to be determined (at least 12/31/2004 or later).
Emergency Release Installed
January
15, 2004: PIC Emergency Release 5.2.1 has been installed to
resolve a JAVA processing problem that affected the efficiency of
processing Form 50058. In addition, to serve PIC users better, the
release added the capability to add a banner "ticker"
announcement to the PIC Logon page to alert users to special conditions
or schedules. We demonstrate it for this release but it will be
reserved for special alerts and warnings in the future.
Year
2003 Headlines
|