The following is the list of inspections and associated inspection reports for the maintenance rule baseline inspections. The lists of persons contacted, inspection procedures used, items opened, acronyms, and documents reviewed have been deleted from these files (saves 5-10K per file). If you need an official copy, one must be obtained from the public document room(s) or you may download an unofficial copy here.


Plant
Completed Inspection Status Date
Inspection Report Date
ADAMS Accession Numbers
Arkansas Nuclear One
January 30, 1998
May 7, 1998
Notice of Violation - ML032300700
Response Letter - ML032300707
Enclosure 2 - ML032300709
Beaver Valley
July 11, 1997
August 5, 1997
Letter - ML032300689
Inspection Report - ML032300692
Big Rock
Shutdown Plant
May 8, 1998
June 4, 1998
Letter - ML032300710
Notice of Violation - ML032300712
Inspection Report- ML032300713
Braidwood
December 19, 1997
January 30, 1998

Letter - ML032300657
Notice of Violation - ML032300658
Inspection Report - ML032300661

Browns Ferry
April 18, 1997
May 21, 1997
Letter - ML032300671
Inspection Report - ML032300674
Brunswick
March 20, 1998
April 20, 1998
Letter - ML032300280
Inspection Report - ML032300293
Byron
April 15, 1997
June 12, 1997
Letter - ML032300185
Notice of Violation - ML032300188
Inspection Report - ML032300189
Callaway
August 22, 1997
December 24, 1997
Letter - ML032300273
Notice of Violation - ML032300275
Inspection Report - ML032300278
Calvert Cliffs
April 3, 1998
May 1, 1998
Letter - ML032300269
Inspection Report - ML032300272
Catawba 1 & 2
February 14, 1997
March 20, 1997
Letter - ML032300167
Notice of Violation - ML032300171
Inspection Report - ML032300173
Clinton
April 14, 1998
June 12, 1998
Letter - ML032300418
Inspection Report - ML032300423
Comanche Peak
May 15, 1998
July 31, 1998
Letter - ML032300594
Notice of Violation - ML032300598
Inspection Report - ML032300606
Cooper
August 16, 1996
October 7, 1996

Letter - ML032300402
Notice of Violation - ML032300404
Inspection Report - ML032300409

Crystal River
June 26, 1998
July 20, 1998
Letter - ML032300302
Notice of Violation -ML032300304
Inspection Report -ML032300309
Davis-Besse
January 17, 1997
March 6, 1997

Letter - ML032690045
Notice of Violation - ML032690050
Inspection Report - ML032690052

DC Cook
September 13, 1996
November 14, 1996
Letter - ML032300281
Notice of Violation - ML032300284
Inspection Report -ML032300287
Diablo Canyon
July 11, 1997
September 12, 1997
Letter - ML032300457
Notice of Violation - ML032300461
Inspection Report - ML032300464
Dresden
May 7, 1997
June 6, 1997
Letter - ML032300244
Notice of Violation - ML032300249
Inspection Report - ML032300253
Duane Arnold
October 10, 1997
November 15, 1997
Letter - ML032300714
Notice of Violation - ML032300717
Inspection Report - ML032300720
Farley
September 12, 1997
October 20, 1997
Letter - ML032300363
Inspection Report - ML032300366
Fermi
February 13, 1998
March 25, 1998
Letter - ML032300219
Notice of Violation - ML032300231
Inspection Report - ML032300232
Fitzpatrick
October 3, 1997
January 7, 1998
Letter - ML032300294
Inspection Report - ML032300295
Fort Calhoun
June 12, 1998
October 26, 1998
Letter - ML032300248
Notice of Violation - ML032300255
Inspection Report - ML032300256
Ginna
March 20, 1998
May 1, 1998
Letter - ML032300716
Inspection Report - ML032300719
Grand Gulf
March 3, 1997
April 8, 1997
Letter - ML032300347
Notice of Violation - ML032300353
Inspection Report - ML032300357
Hatch 1 & 2
October 25, 1996
November 22, 1996
Letter - ML032300489
Notice of Violation - ML032300497
Inspection Report - ML032300501
Hope Creek
Febraury 28, 1997
April 18, 1997
Letter - ML032300697
Inspection Report - ML032300699
Indian Point 2
June 12, 1998
July 15, 1998
Letter - ML032300679
Inspection Report - ML032300682
Indian Point 3
December 13, 1996
February 14, 1997
Letter - ML032300505
Notice of Violation - ML032300514
Inspection Report - ML032300517
Kewaunee
August 8, 1997
September 12, 1997
Letter - ML032300492
Notice of Violation - ML032300499
Inspection Report - ML032300500

LaCross
Shutdown Plant

May 22, 1998
June 16,1998
Letter - ML032300479
Inspection Report - ML032300482
LaSalle
January 16, 1998
February 9, 1998
Letter - ML032300205
Inspection Report - ML032300206
Limerick
July 10, 1998
August 26, 1998
Letter - ML032300403
Notice of Violation - ML032300407
Inspection Report - ML032300411
McGuire
August 22, 1997
October 3, 1997
Letter - ML032300560
Inspection Report - ML032300566
Millstone 2
May 22, 1998
July 7, 1998
Letter - ML032300636
Inspection Report - ML032300640
Millstone 3
March 21, 1997
May 8, 1997
Letter - ML032300458
Notice of Violation - ML032300463
Inspection Report - ML032300465
Monticello
June 6, 1997
July 16, 1997
Letter - ML032300728
Notice of Violation - ML032300731
Inspection Report - ML032300732
Nine Mile Point 1
October 11, 1996
January 15, 1997
Letter - ML032300152
Inspection Report - ML032300156
Nine Mile Point 2
June 19, 1998
July 23, 1998
Letter - ML032300635
Inspection Report - ML032300641
North Anna
October 10, 1997
November 24, 1997
Letter - ML032300426
Inspection Report - ML032300428
Oconee
June 27, 1997
August 4, 1997
Letter - ML032300693
Notice of Violation - ML032300695
Inspection Report - ML032300696
Oyster Creek
April 11, 1997
May 30. 1997
Letter - ML032300721
Inspection Report - ML032300723
Palisades
March 20, 1997
April 16, 1997
Letter - ML032300484
Inspection Report - ML032300487
Palo Verde
July 19, 1996
August 21, 1996
Letter - ML032300261
Inspection Report - ML032300263
Peach Bottom
August 9, 1996
October 9, 1996
Letter - ML032300146
Inspection Report - ML032300147
Perry
November 8, 1996
January 29, 1997
Letter - ML032300350
Notice of Violation - ML032300356
Inspection Report - ML032300358
Pilgrim
May 1, 1998
June 29, 1998
Letter - ML032300724
Inspection Report - ML032300729
Point Beach
December 15, 1997
January 12, 1998
Letter - ML032300318
Notice of Violation - ML032300320
Inspection Report - ML032300324
Prarie Island
October 11, 1996
January 10, 1997
Letter - ML032300432
Notice of Violation - ML032300436
Inspection Report - ML032300440
Quad Cities
September 12, 1997
October 24, 1997
Letter - ML032300364
River Bend
October 31, 1997
February 12, 1998
Letter - ML032300659
Notice of Violation - ML032300663
Inspection Report - ML032300667
Robinson
November 7, 1997
December 5, 1997
Letter - ML032300332
Notice of Violation - ML032300337
Inspection Report - ML032300342
Salem
August 29, 1997
December 1, 1997
Letter - ML032300675
Inspection Report - ML032300678
San Onofre
December 5, 1997
March 2, 1998
Letter - ML032300322
Notice of Violation - ML032300326
Inspection Report - ML032300338
Seabrook
January 31, 1997
March 31, 1997
Letter - ML032300123
Notice of Violation - ML032300127
Inspection Report - ML032300130
Sequoyah
December 6, 1996
January 2, 1997
Letter - ML032300257
Notice of Violation - ML032300260
Inspection Report - ML032300262
Shearon Harris
July 25, 1997
August 27, 1997
Letter - ML032300702
Notice of Violation - ML032300706
Inspection Report - ML032300708
South Texas Project
March 27, 1998
June 16, 1998
Letter - ML032300136
Notice of Violation - ML032300138
Inspection Report - ML032300142
St. Lucie
September 20, 1996
October 16, 1996
Letter - ML032300647
Notice of Violation - ML032300651
Inspection Report - ML032300654
Surry
January 17, 1997
February 20,1997
Letter - ML032300616
Inspection Report - ML032300621
Susquehanna
June 8, 1998
July 16,1998
Letter - ML032300648
Three Mile Island
May 22, 1998
June 19, 1998
Letter - ML032300607
Inspection Report - ML032300611
Turkey Point
February 27, 1998
March 26, 1998
Letter - ML032300439
Inspection Report -ML032300448
V.C. Summer
May 16, 1997
June 20, 1997
Letter - ML032300362
Notice of Violation - ML032300374
Inspection Report -ML032300385
Vermont Yankee
December 19, 1998
February 5, 1997
Letter - ML032300264
Notice of Violation - ML032300266
Inspection Report - ML032300267
Vogtle
January 30, 1998
March 12, 1998
Letter - ML032300341
Inspection Report - ML032300346
Waterford 3
January 31, 1997
March 21, 1997
Letter - ML032300622
Notice of Violation - ML032300626
Inspection Report - ML032300630
Watts Bar
May 22, 1998
July 6, 1998
Letter - ML032300520
Notice of Violation - ML032300525
Inspection Report - ML032300530
WNP-2
November 22, 1996
January 29, 1997
Letter - ML032300683
Notice of Violation - ML032300687
Inspection Report - ML032300688
Wolf Creek
April 24, 1998
July 6, 1998
Letter - ML032300211
Notice of Violation - ML032300212
Inspection Report - ML032300213

Zion
Shutdown Plant

June 19, 1998
July 7, 1998
Letter - ML032300314
Notice of Violation - ML032300315