Event Notification Report for March 21, 2003




                    U.S. Nuclear Regulatory Commission
                              Operations Center

                              Event Reports For
                           03/20/2003 - 03/21/2003

                              ** EVENT NUMBERS **

39681  39682  39683  

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   39681       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: BRUNSWICK                REGION:  2  |NOTIFICATION DATE: 03/19/2003|
|    UNIT:  [1] [] []                 STATE:  NC |NOTIFICATION TIME: 23:15[EST]|
|   RXTYPE: [1] GE-4,[2] GE-4                    |EVENT DATE:        03/19/2003|
+------------------------------------------------+EVENT TIME:        21:30[EST]|
| NRC NOTIFIED BY:  David Jester                 |LAST UPDATE DATE:  03/20/2003|
|  HQ OPS OFFICER:  ERIC THOMAS                  +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |CAUDLE JULIAN        R2      |
|10 CFR SECTION:                                 |                             |
|APRE 50.72(b)(2)(xi)     OFFSITE NOTIFICATION   |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       94       Power Operation  |94       Power Operation  |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| SINK HOLE IN SITE STABILIZATION POND                                         |
|                                                                              |
| "The site stabilization pond has developed a sink hole which has created a   |
| partial bypass of the normal treatment system from an unauthorized release   |
| point. The stabilization pond receives water pumped from a Storm Drain Basin |
| which collects storm drainage from various areas around the site. This       |
| release from an unauthorized discharge point requires notification to the    |
| State of North Carolina in accordance with our NPDES permit. This report     |
| initiated per [50.72(b)(2)(xi)] due to State of North Carolina               |
| notification."                                                               |
|                                                                              |
| The licensee has notified the NRC Resident Inspector.                        |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   39682       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: SUSQUEHANNA              REGION:  1  |NOTIFICATION DATE: 03/20/2003|
|    UNIT:  [1] [2] []                STATE:  PA |NOTIFICATION TIME: 04:39[EST]|
|   RXTYPE: [1] GE-4,[2] GE-4                    |EVENT DATE:        03/20/2003|
+------------------------------------------------+EVENT TIME:        00:15[EST]|
| NRC NOTIFIED BY:  Robert Boesch                |LAST UPDATE DATE:  03/20/2003|
|  HQ OPS OFFICER:  ERIC THOMAS                  +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |PETE ESELGROTH       R1      |
|10 CFR SECTION:                                 |                             |
|AINC 50.72(b)(3)(v)(C)   POT UNCNTRL RAD REL    |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|2     N          N       0        Refueling        |0        Refueling        |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| INOPERABLE SECONDARY CONTAINMENT                                             |
|                                                                              |
| "On 3/20/03 at 0015 hours during performance of Secondary Containment        |
| drawdown testing, it was determined that the Technical Specification maximum |
| allowed combined flowrate of 2885 SCFM for Zone 1 and Zone 3 was exceeded.   |
| The average flow for the two zones was approximately 3000 SCFM. The          |
| condition required the Station to declare both zones inoperable, and placed  |
| Unit 1 in a 4 hour LCO to restore Secondary Containment. Unit 2 is already   |
| in Mode 5, however the condition would have prevented all additional fuel    |
| moves. The Standby Gas Treatment System was capable of maintaining the DP    |
| requirement of 0.25 " vac. water gauge during the test. By 0330              |
| investigation had reduced flow from the two zones to approximately 2600      |
| SCFM, and the LCO was exited. The inoperability of Secondary Containment is  |
| a loss of an entire Safety Function that is needed to control the release of |
| radioactive material, and is reportable under 10CFR50.72(b)(3)(v)(c)."       |
|                                                                              |
| The licensee notified the NRC Resident Inspector.                            |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   39683       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: PALO VERDE               REGION:  4  |NOTIFICATION DATE: 03/20/2003|
|    UNIT:  [1] [2] [3]               STATE:  AZ |NOTIFICATION TIME: 13:13[EST]|
|   RXTYPE: [1] CE,[2] CE,[3] CE                 |EVENT DATE:        03/20/2003|
+------------------------------------------------+EVENT TIME:        08:30[MST]|
| NRC NOTIFIED BY:  DAN MARKS                    |LAST UPDATE DATE:  03/20/2003|
|  HQ OPS OFFICER:  ARLON COSTA                  +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |CLAUDE JOHNSON       R4      |
|10 CFR SECTION:                                 |                             |
|APRE 50.72(b)(2)(xi)     OFFSITE NOTIFICATION   |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       97       Power Operation  |97       Power Operation  |
|2     N          Y       98       Power Operation  |98       Power Operation  |
|3     N          Y       99       Power Operation  |99       Power Operation  |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| MEDIA COVERAGE OF TERRORIST TARGET                                           |
|                                                                              |
| "The following event description is based on information currently           |
| available.  If through subsequent reviews of this event, additional          |
| information is identified that is pertinent to this event or alters the      |
| information being provided at this time, a follow-up notification will be    |
| made via the ENS or under the reporting requirements of 10CFR50.73.          |
|                                                                              |
| "This ENS notification is to inform the agency of an issue within the NRC's  |
| purview that may affect or raise a concern about the public health and       |
| safety.                                                                      |
|                                                                              |
| "It has been reported in two news articles that the Palo Verde Nuclear       |
| Generating Station has been identified as a terrorist target.  These two     |
| articles have been copied from the internet                                  |
| [ww.cnn.com/2003/US/Southwest/03/20/nuclear.plant.threat/index.html and      |
| www.washtimes.com/national/20030320-43174000.htm] and attached to this       |
| notification. We have also been informed of television coverage on the same  |
| subject on CNN and local networks.                                           |
|                                                                              |
| "The Palo Verde Nuclear Generating Station is prepared to respond to media   |
| questions, but has no plans to issue a press release.                        |
|                                                                              |