Quality Control/ Quality Assurance Plan

PDF version (43 kb)

Below are examples of QC/QA Plans from Oregon and Oklahoma.

Oregon DOT Bridge Inspection Program QA Review

Bridge Inspection has played and will continue to play an ever-increasing important role in assuring that a safe infrastructure is available for the publics use. As our bridges continue to age and deteriorate, an accurate and thorough condition assessment of each structure is critical in maintaining a safe, functional and reliable highway system.

The six primary responsibilities of the bridge inspection program are:

  1. Maintain Public Safety and Confidence (Structural Concerns)
  2. Protect Public Investment (Maintenance Concerns)
  3. Maintain a desired level of service (Functionality Concerns)
  4. Provide Bridge Inspection Program Support
  5. Provide Accurate Bridge Records
  6. Fulfill Legal Responsibilities (In Compliance with CFR)

Fulfilling Our Legal Responsibilities

Though not specifically required in the Code of Federal Regulations, during a 1989 Bridge Inspection Program Review, FHWA strongly encouraged each State to provide a QA / QC review of the bridge inspections performed by that State. Each local FHWA Division Offices was directed to work closely with each State to develop a program that would follow-up inspection findings and provide a quality control of inspections performed. The objectives of the program were to be as follows:

FHWA considered the QA/QC Review program to be an integral part of the overall inspection program. The goal of the review program was to perform an independent field review of 5% of the completed inspections that were performed by each inspection team per year.

Thoroughness and Accuracy of the Bridge Inspection Report

As with all business practices, we should be cognizant of and continually scrutinize our business practices to assure that each is as efficient and as effective as possible. The word "Efficiency" as used herein refers to "doing things right the first time" (assuring that sufficient time and resources are allocated to each structure to ensure that the inspection was performed as thoroughly as necessary). The word "Effectiveness" as used herein refers to "doing the right things (assuring that each structure is inspected by the due date). Due to the large number of structures that are assigned to each inspector, it's imperative that each region inspector, budget their time and resources wisely. A rushed bridge inspection will quite often result in missed bridge inspection elements and inaccurate condition assessment rating information. A completely independent QA field review of the last bridge inspection will clearly point out differences and provide a measure of it's timeliness, thoroughness and accuracy.

Accuracy of the data in the bridge inspection database

The entire bridge program revolves around the bridge condition assessment information contained in the bridge inspection database. Large multi-million dollar decisions are made annually based solely on that data. Therefore, it is absolutely paramount that the data is as accurate and correct as possible. There is a lot of political embarrassment and loss of program credibility when it is shown that a program decision was made on faulty information. By performing a QA field review on the structures in the bridge program that are scheduled to receive some action, we are validating the information associated with that structure. Bottom-line, in addition to keeping the State of Oregon in compliance with the Code of Federal Regulations, initiation of such a program just makes good business sense.

STIP Projects

To assure that the right projects are getting into the State Transportation Improvement Program, every project needs a champion. By reviewing the structures, in the worst condition, in each region, the QA Review Team is able to discuss, on site, the appropriate strategy and can help develop the appropriate rehabilitation or replacement plan for every structure in question. The QA Review Team is basically functioning as a "sounding board", if you will.

Major Bridge Maintenance Projects

We consider these projects to be "stopgap" measures until a full rehabilitation or replacement project can be programmed by the STIP. These projects are also generally beyond the resources of the district bridge maintenance crews, in terms of time, money, equipment, or expertise involved. By reviewing the structures in the worst condition, the Review Team is able to discuss, on site, the appropriate repair / rehabilitation / replacement strategy and/or preliminary design concepts.

Load Rating / Load Posting Issues

Implementing Load Restrictions on structures are extremely political. However, on the other hand, one of the major responsibilities we are charged with is to assure that a safe facility is available to the public. Therefore, it is absolutely imperative that all deficiencies that directly influence the load rating calculations be located during the ODOT inspection effort and addressed immediately. By reviewing the bridges in the worst conditions, the QA review team provides a second look and/or a second opinion, regarding the severity of the deficiencies and their potential implications. It's like a person being confronted with a serious medical condition; they are encouraged to seek a second opinion from either another doctor or specialist in a given field of medical science.

Bridge Inspection Training

One of our major responsibilities is to provide a complete, thorough and accurate bridge inventory and condition assessment information. The QA Review Team is made up of bridge inspectors from the other regions and any newly hired bridge inspection staff, in order to assure statewide consistency between the geographically dispersed bridge inspectors and to provide on-the-job training for the new inspection staff. All questions are openly discussed, on site, to assure that everyone is in full agreement and that we are achieving statewide consistency. Also, ODOT Bridge Design Staff are encouraged to participate in the QA reviews, so they can obtain a better understanding of the bridge elements, the language contained in the condition state descriptions, and just exactly what the assigned condition assessment ratings are indicating about the bridge elements.

QA Review Process


  1. Office Review
    1. Assure that all inspections are performed by the prescribed due date.
    2. Assure that there is an appropriate level of follow-up on identified critical deficiencies.
  2. Field Review
    1. Selection of the bridge sampling.
      Bridges with urgent or critical maintenance recommendations
      Bridges with load rating / load posting issues
      Bridges that are in need of bridge rehab / replacement actions
      New structures recently opened to traffic - check initial inspection
      The sampling size will be at least 5% of the regional routine inspections performed
    2. Selection of the QA Review Team
      A QA Review will be performed in each region annually (host inspector)
      Bridge Inspection staff from other regions will rotate onto the team as well as any new bridge inspection staff. Bridge Design personnel are encouraged to participate in the QA Review process (guest inspectors)
    3. Independent inspection of the bridge
      The QA Review Team will generate a totally independent inspection report.
    4. Comparing bridge inspection findings
      The bridge inspection report generated by the QA Review Team will then be compared with the last bridge inspection report of record.
    5. Differences between the two inspections are then openly discussed so that we can determine why any differences might exist.
    6. Initiate interviews with the appropriate district bridge maintenance personnel to determine the effectiveness of the bridge inspection effort.

Oklahoma Quality Control and Quality Assurance Plan for State and Local Jurisdiction Bridge Safety Inspections

In order to insure that Oklahoma's bridges are being inspected and data is gathered in an accurate and consistent manner, it is necessary to implement quality control and quality assurance plans. For this purpose, quality control can be defined as the steps the inspecting agency and ODOT take to monitor that the inspections are performed correctly and the data collected is accurate. Quality assurance can be defined as the steps taken to insure that the work is being performed by qualified, quality inspectors and reviewers who are properly trained to perform the work.

Quality Control


Internal Quality Control (By Inspecting Agency)

At least once every inspection cycle (24 months), the reviewing engineer (the engineer who routinely reviews inspection reports) for the inspecting agency (either Off- or On-System consulting firm) will randomly choose five (5) bridges to review in the field for each team leader (the reviewing engineer must be someone other than the team leader). The composition of these five bridges will be such that they represent a cross-section of bridge types inspected. It is strongly recommended that they include one of each of the following; a truss bridge, a timber girder bridge, a steel girder bridge, a concrete girder bridge (prestressed or regularly reinforced) and a bridge length concrete culvert. One of these representative bridges will include a bridge that is rated three (3) tons (if available in the bridges inspected by the team leader). This field review will consist of the reviewing engineer assessing the correctness and completeness of the inspection, including codings, elements and quantities, photos required by the contract as well as those needed to depict critical conditions, etc. This review should be done with the inspector so that any improper codings or procedures can be immediately corrected. The internal reviewer for the On-System ODOT team leaders shall be the team leader's supervisor (or supervisor's designee...in most cases the county bridge coordinator in each division).

The Bridge Division will develop a Quality Control plan for On-System ODOT inspectors. On- and Off-System consultant inspection firms shall develop their own Quality Control plan. As a minimum, the plan will include the following:


Quality Control Report

Once the Quality Control Plan is approved by ODOT, the consultant or field division shall implement the plan. Following the field review, the consultant shall submit a report to the Bridge Division (with a copy to the appropriate field division) which contains the following:

On-System ODOT team leaders shall be reviewed by their supervisor (or designee, someone familiar with inspection procedures and codings) in this same manner, with a written report and suggestions for correcting findings returned to the Bridge Division.

External Quality Control (By ODOT)

Each inspecting agency shall be reviewed by ODOT in the field at least once during a two-year cycle. This review will be conducted by the persons in the field division county bridge coordinators office who are trained and are very familiar with inspection procedures and codings. It will consist of reviewing inspections of at least five (5) bridges in the field. These bridges will represent the different types of bridges commonly found in the counties inspected by that agency. As a minimum, one of each of the following bridge types should be reviewed; a truss bridge, a timber girder bridge, a steel girder bridge, a concrete girder bridge (prestressed or regularly reinforced) and a culvert. One of these representative bridges will include a bridge that is rated three (3) tons (if available). A Quality Control Report of the findings of this review shall be forwarded to the inspecting agency with a copy to the Bridge Division. In addition, the Bridge Division will randomly review four (4) inspecting agencies each year in the same manner. A copy of their findings will be forwarded to the inspecting agency and the appropriate field division.

In addition to the field review, the inspecting agency's office procedures may be reviewed. This may include loadratingprocedures, filing procedures and bridge file content, consultants in-house quality control plan, procedures and results, consultant's procedures for notification and follow-up with bridge owners for load posting and closing of bridges as required by ODOT policies, etc.

Quality Assurance


Continuing Training

As part of this quality control/quality assurance process, some form of continuing training will be required for all team leaders and the reviewing engineer. As a minimum, this training will consist of the following:

Disqualification

When the inspection review indicates that a team leader and/or an inspecting agency continues to make the same or similar mistakes, omissions, etc., ODOT shall implement disqualification procedures as follows:


Reasons For Disqualification

Typical reasons for disqualification can be, but are not limited to, the following:

The Oklahoma Department of Transportation has the final authority to carry out this disqualification process. The inspecting agency must agree to these procedures as part of any bridge safety inspection agreement before they will be allowed to perform any bridge safety inspections.