Work Planning/Permit Review Committee

  1. Charge
    Assist Light Sources Directorate Staff and User personnel regarding compliance with PRM 1.3.6 - Work Planning and Control Procedure. The committees apply the graded approach to identify hazards, risks and controls; determine complexity levels, and to establish the rigor of additional planning and reviews necessary to accomplish tasks. Job tasks deemed outside of a designated qualification matrix will require enhanced work planning. Committees review and approve submitted work permits.

    NSLS reports to Operations Section Head, Emil Zitvogel.

    NSLS-II reports to ESH Manager, W. Robert Casey.


  2. Membership
    NSLS Membership List
    A. Boerner, Chair
    R. Kiss, Deputy Chair & Building Manager
    R. Scheuerer, Senior Mechanical Supervisor
    R. Chmiel, Primary Reviewer
    D. Bauer, assigned Environmental Compliance Rep
    M.A. Corwin, Training Coordinator
    C. Weilandics, assigned Industrial Hygienist Rep
    F. Zafonte, assigned Facility Support Rep
    Alternate Primary Reviewers
    1st: J. Aloi
    2nd: A. Ackerman


    NSLS-II Membership List
    G. Van Derlaske, Chair & Facilities Manager
    A. Boerner, Deputy Chair
    N. Gmür, Primary Reviewer
    E. Johnson, Light Sources Directorate
    M.A. Corwin, Training Coordinator
    D. Bauer, assigned Environmental Compliance Rep
    C. Weilandics, assigned Industrial Hygiene Rep
    F. Zafonte, assigned Facility Support Rep
    Alternate Primary Reviewer
    R. Chmiel


  3. Meeting Frequency
    Meetings are called by Committee Chair based on work planning requests.