General Electric Co. - VESR1.0 Site Identification
2.0 Site Status SummaryOn April 15, 1970, NRC authorized the licensee to possess but not operate the reactor. The license was renewed on June 11, 1976, to expire in 2016. The facility has been maintained in SAFSTOR condition. The facility is next to the Vallecitos Boiling Water Reactor which is also in SAFSTOR. The licensee plans to maintain the facility in SAFSTOR until other ongoing nuclear and radioactive activities are also to be decommissioned to provide an integrated site decommission. NRC issued an Order on September 6, 2007, approving the direct transfer of GE's interest in License TR-1 to GE-Hitachi Nuclear Energy Americas, LLC. 3.0 Major Technical or Regulatory IssuesNone 4.0 Estimated Date For Closure01/20/2018 |