FEMA has established Time Limits for requesting assistance and for completing work using Public Assistance Program grants.

Requesting Assistance

Completing Work

The time frames for completing eligible work are also measured from the date of declaration of the disaster and vary depending on the type of work.

Time Extension

All time frames are set by regulation; however, if extenuating circumstances or unusual project conditions exist, a time extension may be requested through the grantee. The grantee has the authority to extend the time frames for completion of debris removal and emergency work by 6 months and permanent work by 30 months. For all other extensions, the grantee must request the extension from FEMA.