Licensee's General Comments: none
Unplanned Scrams per 7000 Critical Hrs | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
Unplanned scrams | 0 | 0 | 0 | 1.0 | 0 | 0 | 1.0 | 1.0 |
Critical hours | 2208.0 | 2163.5 | 1987.0 | 2049.2 | 1691.0 | 1749.1 | 2148.2 | 2158.1 |
Indicator value | 0.9 | 0.9 | 0.9 | 0.8 | 0.9 | 0.9 | 1.8 | 1.8 |
Licensee Comments: none
Unplanned Power Changes per 7000 Critical Hrs | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
Unplanned power changes | 0 | 1.0 | 1.0 | 0 | 0 | 1.0 | 0 | 0 |
Critical hours | 2208.0 | 2163.5 | 1987.0 | 2049.2 | 1691.0 | 1749.1 | 2148.2 | 2158.1 |
Indicator value | 2.8 | 1.9 | 1.9 | 1.7 | 1.8 | 1.9 | 0.9 | 0.9 |
Licensee Comments:
2Q/08: The NRC granted Palisades Enforcement Discretion for Safeguards Transformer 1-1 Inoperability (72 hour shutdown LCO). The 24 hour NOED was in effect from 4/04/08 21:55 until the transformer was restored at 01:00 on 4/05/08. No power reduction required.
Unplanned Scrams with Complications | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
Scrams with complications | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Indicator value | 0.0 | 0.0 | 0.0 | 0.0 |
Licensee Comments: none
Safety System Functional Failures (PWR) | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
Safety System Functional Failures | 0 | 2 | 2 | 0 | 0 | 2 | 0 | 1 |
Indicator value | 1 | 3 | 5 | 4 | 4 | 4 | 2 | 3 |
Licensee Comments:
2Q/08: LER 2008-002 - Breaker Cubicle Component Failure Results in HPSI Pump Inoperability.
Mitigating Systems Performance Index, Emergency AC Power System | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
UAI (ΔCDF) | 4.10E-09 | 1.80E-08 | 6.50E-08 | 8.20E-08 | 3.80E-08 | 3.60E-08 | 3.70E-08 | 4.10E-08 |
URI (ΔCDF) | 5.50E-08 | 5.50E-08 | -1.20E-08 | 1.50E-07 | 2.20E-07 | 2.20E-07 | 2.20E-07 | 2.20E-07 |
PLE | NO | NO | NO | NO | NO | NO | NO | NO |
Indicator value | 5.91E-08 | 7.30E-08 | 5.30E-08 | 2.32E-07 | 2.58E-07 | 2.56E-07 | 2.57E-07 | 2.61E-07 |
Licensee Comments:
2Q/08: Reevaluation of September 2007 MSPI Failure for EDG 1-1 fuel oil leak is being reviewed. (Reference CR-PLP-2007-04078).
Mitigating Systems Performance Index, High Pressure Injection System | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
UAI (ΔCDF) | 2.10E-07 | 2.40E-07 | 1.30E-07 | 1.30E-07 | 1.30E-07 | 1.20E-07 | 1.60E-07 | 1.20E-07 |
URI (ΔCDF) | -2.70E-07 | -2.70E-07 | -2.70E-07 | -2.70E-07 | -2.70E-07 | -2.70E-07 | -2.70E-07 | -2.70E-07 |
PLE | NO | NO | NO | NO | NO | NO | NO | NO |
Indicator value | -6.00E-08 | -3.00E-08 | -1.40E-07 | -1.40E-07 | -1.40E-07 | -1.50E-07 | -1.10E-07 | -1.50E-07 |
Licensee Comments: none
Mitigating Systems Performance Index, Heat Removal System | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
UAI (ΔCDF) | -1.60E-08 | -8.30E-09 | -9.40E-09 | -1.00E-08 | -8.90E-09 | -8.00E-09 | -5.40E-09 | -3.30E-09 |
URI (ΔCDF) | -2.80E-07 | 2.80E-07 | 2.80E-07 | 2.80E-07 | 2.80E-07 | 2.80E-07 | 2.80E-07 | 2.80E-07 |
PLE | NO | NO | NO | NO | NO | NO | NO | NO |
Indicator value | -2.96E-07 | 2.72E-07 | 2.71E-07 | 2.70E-07 | 2.71E-07 | 2.72E-07 | 2.75E-07 | 2.77E-07 |
Licensee Comments:
2Q/08: Evaluation of relay testing results for Breaker 152-209 associated with Auxiliary Feedwater Pump P-8C concluded the equipment remained capable of performing their design functions and were operable. (Reference CR-PLP-2008-01473). This submittal includes revision to previously submitted planned unavailability hours due to missed flow controller testing (RI-95). Data updates made in Jan 06, Feb 06, Sep 06, Dec 06, Jul 07, and Mar 08 with a small impact on MSPI result and no impact on the ???color??? of the indicator. Extent of condition reviews are in progress due to this issue. (Reference CR-PLP-2008-02172).
1Q/08: Evaluation is pending on relay testing results for Breaker 152-209 associated with Auxiliary Feedwater Pump P-8C. (Reference CR-PLP-2008-01473).
4Q/06: 5 failures were reported in November related to switch/controller mis-positionings. These were associated with AFW Pump handswitches (3 failures) and AFW Flow Control Valve controller position (2 failures). The failures were reported in Palisades LER 2006-007, Auxiliary Feedwater Control Switches Not Position for Automatic System Actuation
Mitigating Systems Performance Index, Residual Heat Removal System | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
UAI (ΔCDF) | 1.10E-08 | 4.00E-08 | 4.00E-08 | 4.00E-08 | 1.10E-08 | 1.10E-08 | 1.10E-08 | 1.10E-08 |
URI (ΔCDF) | -4.00E-08 | -4.00E-08 | -4.00E-08 | -4.00E-08 | -4.00E-08 | -4.00E-08 | -4.00E-08 | -4.00E-08 |
PLE | NO | NO | NO | NO | NO | NO | NO | NO |
Indicator value | -2.90E-08 | 0.00E+00 | 0.00E+00 | 0.00E+00 | -2.90E-08 | -2.90E-08 | -2.90E-08 | -2.90E-08 |
Licensee Comments: none
Mitigating Systems Performance Index, Cooling Water Systems | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
UAI (ΔCDF) | 1.00E-07 | 2.50E-08 | 2.50E-08 | 2.80E-08 | 2.80E-08 | 2.50E-08 | 5.40E-10 | -4.20E-08 |
URI (ΔCDF) | 4.70E-07 | 4.70E-07 | 4.80E-07 | 4.80E-07 | 4.80E-07 | 4.80E-07 | -2.20E-07 | -2.20E-07 |
PLE | NO | NO | NO | NO | NO | NO | NO | NO |
Indicator value | 5.70E-07 | 4.95E-07 | 5.05E-07 | 5.08E-07 | 5.08E-07 | 5.05E-07 | -2.19E-07 | -2.62E-07 |
Licensee Comments:
2Q/08: Evaluation of relay testing results for Breaker 152-208 associated with Component Cooling Pump P-52B concluded the equipment remained capable of performing their design functions and were operable. (Reference CR-PLP-2008-01409).
Reactor Coolant System Activity | 7/06 | 8/06 | 9/06 | 10/06 | 11/06 | 12/06 | 1/07 | 2/07 | 3/07 | 4/07 | 5/07 | 6/07 |
Maximum activity | 0.018300 | 0.022200 | 0.015700 | 0.017400 | 0.017800 | 0.024900 | 0.027300 | 0.028200 | 0.036000 | 0.033800 | 0.040800 | 0.041000 |
Technical specification limit | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 |
Indicator value | 1.8 | 2.2 | 1.6 | 1.7 | 1.8 | 2.5 | 2.7 | 2.8 | 3.6 | 3.4 | 4.1 | 4.1 |
Reactor Coolant System Activity | 7/07 | 8/07 | 9/07 | 10/07 | 11/07 | 12/07 | 1/08 | 2/08 | 3/08 | 4/08 | 5/08 | 6/08 |
Maximum activity | 0.037000 | 0.055400 | 0.058400 | 0.005210 | 0.013800 | 0.009210 | 0.009320 | 0.010600 | 0.011200 | 0.011500 | 0.012200 | 0.012900 |
Technical specification limit | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 |
Indicator value | 3.7 | 5.5 | 5.8 | 0.5 | 1.4 | 0.9 | 0.9 | 1.1 | 1.1 | 1.2 | 1.2 | 1.3 |
Licensee Comments: none
Reactor Coolant System Leakage | 7/06 | 8/06 | 9/06 | 10/06 | 11/06 | 12/06 | 1/07 | 2/07 | 3/07 | 4/07 | 5/07 | 6/07 |
Maximum leakage | 0.007 | 0.059 | 0.059 | 0.040 | 0.055 | 0.079 | 0.111 | 0.238 | 0.125 | 0.164 | 0.238 | 0.001 |
Technical specification limit | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 |
Indicator value | 0.1 | 0.6 | 0.6 | 0.4 | 0.6 | 0.8 | 1.1 | 2.4 | 1.3 | 1.6 | 2.4 | 0 |
Reactor Coolant System Leakage | 7/07 | 8/07 | 9/07 | 10/07 | 11/07 | 12/07 | 1/08 | 2/08 | 3/08 | 4/08 | 5/08 | 6/08 |
Maximum leakage | 0.001 | 0.001 | 0.001 | 0.004 | 0.005 | 0.005 | 0.005 | 0.004 | 0.007 | 0.007 | 0.008 | 0.017 |
Technical specification limit | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 | 10.0 |
Indicator value | 0 | 0 | 0 | 0 | 0.1 | 0.1 | 0.1 | 0 | 0.1 | 0.1 | 0.1 | 0.2 |
Licensee Comments: none
Drill/Exercise Performance | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
Successful opportunities | 40.0 | 25.0 | 18.0 | 28.0 | 22.0 | 19.0 | 58.0 | 42.0 |
Total opportunities | 40.0 | 26.0 | 23.0 | 30.0 | 22.0 | 20.0 | 60.0 | 42.0 |
Indicator value | 96.7% | 96.8% | 96.5% | 96.3% | 95.5% | 95.3% | 95.7% | 95.8% |
Licensee Comments: none
ERO Drill Participation | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
Participating Key personnel | 114.0 | 121.0 | 126.0 | 125.0 | 123.0 | 122.0 | 117.0 | 112.0 |
Total Key personnel | 114.0 | 125.0 | 131.0 | 126.0 | 124.0 | 124.0 | 117.0 | 112.0 |
Indicator value | 100.0% | 96.8% | 96.2% | 99.2% | 99.2% | 98.4% | 100.0% | 100.0% |
Licensee Comments: none
Alert & Notification System | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
Successful siren-tests | 183 | 183 | 183 | 183 | 183 | 183 | 182 | 183 |
Total sirens-tests | 183 | 183 | 183 | 183 | 183 | 183 | 183 | 183 |
Indicator value | 99.7% | 99.9% | 100.0% | 100.0% | 100.0% | 100.0% | 99.9% | 99.9% |
Licensee Comments: none
Occupational Exposure Control Effectiveness | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
High radiation area occurrences | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 |
Very high radiation area occurrences | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Unintended exposure occurrences | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Indicator value | 1 | 1 | 1 | 0 | 1 | 1 | 1 | 1 |
Licensee Comments: none
RETS/ODCM Radiological Effluent | 3Q/06 | 4Q/06 | 1Q/07 | 2Q/07 | 3Q/07 | 4Q/07 | 1Q/08 | 2Q/08 |
RETS/ODCM occurrences | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Indicator value | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Licensee Comments: none