Palisades

2Q/2008 Performance Indicators

Licensee's General Comments: none



Link to Notes

Unplanned Scrams per 7000 Critical Hrs 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
Unplanned scrams 0 0 0 1.0 0 0 1.0 1.0
Critical hours 2208.0 2163.5 1987.0 2049.2 1691.0 1749.1 2148.2 2158.1
                 
Indicator value 0.9 0.9 0.9 0.8 0.9 0.9 1.8 1.8


Licensee Comments: none




Link to Notes

Unplanned Power Changes per 7000 Critical Hrs 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
Unplanned power changes 0 1.0 1.0 0 0 1.0 0 0
Critical hours 2208.0 2163.5 1987.0 2049.2 1691.0 1749.1 2148.2 2158.1
                 
Indicator value 2.8 1.9 1.9 1.7 1.8 1.9 0.9 0.9

Licensee Comments:

2Q/08: The NRC granted Palisades Enforcement Discretion for Safeguards Transformer 1-1 Inoperability (72 hour shutdown LCO). The 24 hour NOED was in effect from 4/04/08 21:55 until the transformer was restored at 01:00 on 4/05/08. No power reduction required.






Link to Notes

Unplanned Scrams with Complications 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
Scrams with complications   0 0 0 0 0 0 0
                 
                 
Indicator value         0.0 0.0 0.0 0.0

Licensee Comments: none






Link to Notes

Safety System Functional Failures (PWR) 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
Safety System Functional Failures 0 2 2 0 0 2 0 1
                 
Indicator value 1 3 5 4 4 4 2 3

Licensee Comments:

2Q/08: LER 2008-002 - Breaker Cubicle Component Failure Results in HPSI Pump Inoperability.






Link to Notes

Mitigating Systems Performance Index, Emergency AC Power System 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
UAI (ΔCDF) 4.10E-09 1.80E-08 6.50E-08 8.20E-08 3.80E-08 3.60E-08 3.70E-08 4.10E-08
URI (ΔCDF) 5.50E-08 5.50E-08 -1.20E-08 1.50E-07 2.20E-07 2.20E-07 2.20E-07 2.20E-07
PLE NO NO NO NO NO NO NO NO
                 
Indicator value 5.91E-08 7.30E-08 5.30E-08 2.32E-07 2.58E-07 2.56E-07 2.57E-07 2.61E-07

Licensee Comments:

2Q/08: Reevaluation of September 2007 MSPI Failure for EDG 1-1 fuel oil leak is being reviewed. (Reference CR-PLP-2007-04078).






Link to Notes

Mitigating Systems Performance Index, High Pressure Injection System 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
UAI (ΔCDF) 2.10E-07 2.40E-07 1.30E-07 1.30E-07 1.30E-07 1.20E-07 1.60E-07 1.20E-07
URI (ΔCDF) -2.70E-07 -2.70E-07 -2.70E-07 -2.70E-07 -2.70E-07 -2.70E-07 -2.70E-07 -2.70E-07
PLE NO NO NO NO NO NO NO NO
                 
Indicator value -6.00E-08 -3.00E-08 -1.40E-07 -1.40E-07 -1.40E-07 -1.50E-07 -1.10E-07 -1.50E-07

Licensee Comments: none






Link to Notes

Mitigating Systems Performance Index, Heat Removal System 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
UAI (ΔCDF) -1.60E-08 -8.30E-09 -9.40E-09 -1.00E-08 -8.90E-09 -8.00E-09 -5.40E-09 -3.30E-09
URI (ΔCDF) -2.80E-07 2.80E-07 2.80E-07 2.80E-07 2.80E-07 2.80E-07 2.80E-07 2.80E-07
PLE NO NO NO NO NO NO NO NO
                 
Indicator value -2.96E-07 2.72E-07 2.71E-07 2.70E-07 2.71E-07 2.72E-07 2.75E-07 2.77E-07

Licensee Comments:

2Q/08: Evaluation of relay testing results for Breaker 152-209 associated with Auxiliary Feedwater Pump P-8C concluded the equipment remained capable of performing their design functions and were operable. (Reference CR-PLP-2008-01473). This submittal includes revision to previously submitted planned unavailability hours due to missed flow controller testing (RI-95). Data updates made in Jan 06, Feb 06, Sep 06, Dec 06, Jul 07, and Mar 08 with a small impact on MSPI result and no impact on the ???color??? of the indicator. Extent of condition reviews are in progress due to this issue. (Reference CR-PLP-2008-02172).

1Q/08: Evaluation is pending on relay testing results for Breaker 152-209 associated with Auxiliary Feedwater Pump P-8C. (Reference CR-PLP-2008-01473).

4Q/06: 5 failures were reported in November related to switch/controller mis-positionings. These were associated with AFW Pump handswitches (3 failures) and AFW Flow Control Valve controller position (2 failures). The failures were reported in Palisades LER 2006-007, Auxiliary Feedwater Control Switches Not Position for Automatic System Actuation






Link to Notes

Mitigating Systems Performance Index, Residual Heat Removal System 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
UAI (ΔCDF) 1.10E-08 4.00E-08 4.00E-08 4.00E-08 1.10E-08 1.10E-08 1.10E-08 1.10E-08
URI (ΔCDF) -4.00E-08 -4.00E-08 -4.00E-08 -4.00E-08 -4.00E-08 -4.00E-08 -4.00E-08 -4.00E-08
PLE NO NO NO NO NO NO NO NO
                 
Indicator value -2.90E-08 0.00E+00 0.00E+00 0.00E+00 -2.90E-08 -2.90E-08 -2.90E-08 -2.90E-08

Licensee Comments: none






Link to Notes

Mitigating Systems Performance Index, Cooling Water Systems 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
UAI (ΔCDF) 1.00E-07 2.50E-08 2.50E-08 2.80E-08 2.80E-08 2.50E-08 5.40E-10 -4.20E-08
URI (ΔCDF) 4.70E-07 4.70E-07 4.80E-07 4.80E-07 4.80E-07 4.80E-07 -2.20E-07 -2.20E-07
PLE NO NO NO NO NO NO NO NO
                 
Indicator value 5.70E-07 4.95E-07 5.05E-07 5.08E-07 5.08E-07 5.05E-07 -2.19E-07 -2.62E-07

Licensee Comments:

2Q/08: Evaluation of relay testing results for Breaker 152-208 associated with Component Cooling Pump P-52B concluded the equipment remained capable of performing their design functions and were operable. (Reference CR-PLP-2008-01409).






Link to Notes

Reactor Coolant System Activity 7/06 8/06 9/06 10/06 11/06 12/06 1/07 2/07 3/07 4/07 5/07 6/07
Maximum activity 0.018300 0.022200 0.015700 0.017400 0.017800 0.024900 0.027300 0.028200 0.036000 0.033800 0.040800 0.041000
Technical specification limit 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
                         
Indicator value 1.8 2.2 1.6 1.7 1.8 2.5 2.7 2.8 3.6 3.4 4.1 4.1
Reactor Coolant System Activity 7/07 8/07 9/07 10/07 11/07 12/07 1/08 2/08 3/08 4/08 5/08 6/08
Maximum activity 0.037000 0.055400 0.058400 0.005210 0.013800 0.009210 0.009320 0.010600 0.011200 0.011500 0.012200 0.012900
Technical specification limit 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
                         
Indicator value 3.7 5.5 5.8 0.5 1.4 0.9 0.9 1.1 1.1 1.2 1.2 1.3

Licensee Comments: none






Link to Notes

Reactor Coolant System Leakage 7/06 8/06 9/06 10/06 11/06 12/06 1/07 2/07 3/07 4/07 5/07 6/07
Maximum leakage 0.007 0.059 0.059 0.040 0.055 0.079 0.111 0.238 0.125 0.164 0.238 0.001
Technical specification limit 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
                         
Indicator value 0.1 0.6 0.6 0.4 0.6 0.8 1.1 2.4 1.3 1.6 2.4 0
Reactor Coolant System Leakage 7/07 8/07 9/07 10/07 11/07 12/07 1/08 2/08 3/08 4/08 5/08 6/08
Maximum leakage 0.001 0.001 0.001 0.004 0.005 0.005 0.005 0.004 0.007 0.007 0.008 0.017
Technical specification limit 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0
                         
Indicator value 0 0 0 0 0.1 0.1 0.1 0 0.1 0.1 0.1 0.2

Licensee Comments: none






Link to Notes

Drill/Exercise Performance 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
Successful opportunities 40.0 25.0 18.0 28.0 22.0 19.0 58.0 42.0
Total opportunities 40.0 26.0 23.0 30.0 22.0 20.0 60.0 42.0
                 
Indicator value 96.7% 96.8% 96.5% 96.3% 95.5% 95.3% 95.7% 95.8%

Licensee Comments: none






Link to Notes

ERO Drill Participation 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
Participating Key personnel 114.0 121.0 126.0 125.0 123.0 122.0 117.0 112.0
Total Key personnel 114.0 125.0 131.0 126.0 124.0 124.0 117.0 112.0
                 
Indicator value 100.0% 96.8% 96.2% 99.2% 99.2% 98.4% 100.0% 100.0%

Licensee Comments: none






Link to Notes

Alert & Notification System 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
Successful siren-tests 183 183 183 183 183 183 182 183
Total sirens-tests 183 183 183 183 183 183 183 183
                 
Indicator value 99.7% 99.9% 100.0% 100.0% 100.0% 100.0% 99.9% 99.9%

Licensee Comments: none






Link to Notes

Occupational Exposure Control Effectiveness 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
High radiation area occurrences 0 0 0 0 1 0 0 0
Very high radiation area occurrences 0 0 0 0 0 0 0 0
Unintended exposure occurrences 0 0 0 0 0 0 0 0
Indicator value 1 1 1 0 1 1 1 1

Licensee Comments: none






Link to Notes

RETS/ODCM Radiological Effluent 3Q/06 4Q/06 1Q/07 2Q/07 3Q/07 4Q/07 1Q/08 2Q/08
RETS/ODCM occurrences 0 0 0 0 0 0 0 0
                 
Indicator value 0 0 0 0 0 0 0 0

Licensee Comments: none






Physical Protection information not publicly available.



 
 
 
 