2007 Category A and B Transactions

The following is a list of the major projects approved by Ex-Im Bank's Board of Directors during 2007 that were categorized as either environmental Category A or B. The environmental factors associated with each project are summarized, as well as the time period for which the EIA was made available by Ex-Im Bank for each Category A project.

CATEGORY A TRANSACTIONS

CASE NO. PROJECT  COUNTRY
PROJECT NAME & LOCATION  (Brief Description)
KEY ENVIRONMENTAL FACTORS
AMOUNT FINANCED PERIOD OF EIA AVAILABILITY BOARD ACTION
AP082075 Ghana Construction and delivery of two petroleum pipelines feeding a major expansion of an existing oil storage tank farm Baseline data on regional flora and fauna, air quality, water quality, spill impacts, emergency response to spills, construction wastes, noise, environmental management and monitoring $109.53 million 87 Days Approved 5/31/07
AP082263 India Crude oil refinery processing plant to produce gasoline, jet fuel, diesel, naptha, kerosene, etc. and a polypropylene plant, associated marine tank farm and product export facilities to expand a marine terminal. Air quality; water quality and supply; solid and liquid non-hazardous wastes; noise; natural habitats; environmental management and monitoring. $500.0 million 355 Days Approved 5/16/07
AP082625 Saudi Arabia The project involved a major expansion to a large, existing petrochemical plant with a new polymer production facility and an intermediate compound production facility.   The new units will produce high and low density polyethylene, polystyrene as well as ethane, propane, propylene, etc. Air quality, water quality, hazardous and non-hazardous solid waste disposal, waste management plans, waste water effluents during construction, noise, cultural resources. $586.65 million 259 Days Approved 9/12/07
AP083216 Sri Lanka 300 MWe oil-fired combined cycle power plant Air quality, water quality and supply, solid and liquid non-hazardous wastes, hazardous and toxic materials and wastes, noise, resettlement, indigenous peoples and cultural resources, natural habitats, environmental management and monitoring $23.79 million 130 Days Approved 7/27/07

 

CATEGORY B TRANSACTIONS

CASE NO. PROJECT/ COUNTRY PROJECT NAME & LOCATION               (Brief Description) KEY ENVIRONMENTAL FACTORS CONSIDERED  AMOUNT FINANCED BOARD ACTION
AP082872 Singapore The project will add a new semiconductor fabrication line to an existing fabrication facility. Air quality, water quality, solid and liguid non-hazardous wastes, noise $609.73 million Approved 5/16/07
AP083385 Mexico The project involves optimization and development of the existing Cantarell offshore crude oil and gas field production operations.  Project located in the Bay of Campeche in southeastern Mexico. Emergency Spill Response Plans, air quality, water quality, solid and liquid non-hazardous wastes, hazardous and toxic materials and wastes. $200.0 million Approved 9/27/07

 

 