[Code of Federal Regulations]
[Title 48, Volume 1]
[Revised as of October 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR31.205-42]

[Page 610-612]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 1--FEDERAL ACQUISITION REGULATION
 
PART 31--CONTRACT COST PRINCIPLES AND PROCEDURES--Table of Contents
 
          Subpart 31.2--Contracts With Commercial Organizations
 
Sec. 31.205-42  Termination costs.

    Contract terminations generally give rise to the incurrence of costs 
or the need for special treatment of costs that would not have arisen 
had the contract not been terminated. The following cost principles 
peculiar to terminktion situations are to be used in conjunction with 
the other cost principles in subpart 31.2:
    (a) Common items. The costs of items reasonably usable on the 
contractor's other work shall not be allowable unless the contractor 
submits evidence that the items could not be retained at cost without 
sustaining a loss. The contracting officer should consider the 
contractor's plans and orders for current and planned production when 
determining if items can reasonably be used on other work of the 
contractor. Contemporaneous purchases of common items by the contractor 
shall be regarded as evidence that such items are reasonably usable on 
the contractor's other work. Any acceptance of common items as allocable 
to the terminated portion of the contract should be limited to the 
extent that the quantities of such items on hand, in transit, and on 
order are in excess of the reasonable quantitative requirements of other 
work.
    (b) Costs continuing after termination. Despite all reasonable 
efforts by the contractor, costs which cannot be discontinued 
immediately after the effective date of termination are generally 
allowable. However, any costs continuing after the effective date of the 
termination due to the negligent or

[[Page 611]]

willful failure of the contractor to discontinue the costs shall be 
unallowable.
    (c) Initial costs. Initial costs, including starting load and 
preparatory costs, are allowable as follows:
    (1) Starting load costs not fully absorbed because of termination 
are nonrecurring labor, material, and related overhead costs incurred in 
the early part of production and result from factors such as--
    (i) Excessive spoilage due to inexperienced labor;
    (ii) Idle time and subnormal production due to testing and changing 
production methods;
    (iii) Training; and
    (iv) Lack of familiarity or experience with the product, materials, 
or manufacturing processes.
    (2) Preparatory costs incurred in preparing to perform the 
terminated contract include such costs as those incurred for initial 
plant rearrangement and alterations, management and personnel 
organization, and production planning. They do not include special 
machinery and equipment and starting load costs.
    (3) When initial costs are included in the settlement proposal as a 
direct charge, such costs shall not also be included in overhead. 
Initial costs attributable to only one contract shall not be allocated 
to other contracts.
    (4) If initial costs are claimed and have not been segregated on the 
contractor's books, they shall be segregated for settlement purposes 
from cost reports and schedules reflecting that high unit cost incurred 
during the early stages of the contract.
    (5) If the settlement proposal is on the inventory basis, initial 
costs should normally be allocated on the basis of total end items 
called for by the contract immediately before termination; however, if 
the contract includes end items of a diverse nature, some other 
equitable basis may be used, such as machine or labor hours.
    (d) Loss of useful value. Loss of useful value of special tooling, 
and special machinery and equipment is generally allowable, provided--
    (1) The special tooling, or special machinery and equipment is not 
reasonably capable of use in the other work of the contractor;
    (2) The Government's interest is protected by transfer of title or 
by other means deemed appropriate by the contracting officer; and
    (3) The loss of useful value for any one terminated contract is 
limited to that portion of the acquisition cost which bears the same 
ratio to the total acquisition cost as the terminated portion of the 
contract bears to the entire terminated contract and other Government 
contracts for which the special tooling, or special machinery and 
equipment was acquired.
    (e) Rental under unexpired leases. Rental costs under unexpired 
leases, less the residual value of such leases, are generally allowable 
when shown to have been reasonably necessary for the performance of the 
terminated contract, if--
    (1) The amount of rental claimed does not exceed the reasonable use 
value of the property leased for the period of the contract and such 
further period as may be reasonable; and
    (2) The contractor makes all reasonable efforts to terminate, 
assign, settle, or otherwise reduce the cost of such lease.
    (f) Alterations of leased property. The cost of alterations and 
reasonable restorations required by the lease may be allowed when the 
alterations were necessary for performing the contract.
    (g) Settlement expenses. (1) Settlement expenses, including the 
following, are generally allowable:
    (i) Accounting, legal, clerical, and similar costs reasonably 
necessary for--
    (A) The preparation and presentation, including supporting data, of 
settlement claims to the contracting officer; and
    (B) The termination and settlement of subcontracts.
    (ii) Reasonable costs for the storage, transportation, protection, 
and disposition of property acquired or produced for the contract.
    (iii) Indirect costs related to salary and wages incurred as 
settlement expenses in (i) and (ii); normally, such indirect costs shall 
be limited to payroll taxes, fringe benefits, occupancy costs, and 
immediate supervision costs.

[[Page 612]]

    (2) If settlement expenses are significant, a cost account or work 
order shall be established to separately identify and accumulate them.
    (h) Subcontractor claims. Subcontractor claims, including the 
allocable portion of the claims common to the contract and to other work 
of the contractor, are generally allowable. An appropriate share of the 
contractor's indirect expense may be allocated to the amount of 
settlements with subcontractors; provided, that the amount allocated is 
reasonably proportionate to the relative benefits received and is 
otherwise consistent with 31.201-4 and 31.203(c). The indirect expense 
so allocated shall exclude the same and similar costs claimed directly 
or indirectly as settlement expenses.

[48 FR 42301, Sept. 19, 1983]