MISSION:
STS-108 --
12th ISS
Flight (UF1) - Raffaello MPLM |
Vehicle |
Endeavour/OV-105 |
Target KSC Launch
Date/Time |
Nov. 29, 2001 at
7:41 p.m. EST |
Target KSC Landing
Date/Time |
Dec. 10, 2001 at
3:16 p.m. |
Mission Duration |
10 days, 19 hours,
35 minutes |
Crew |
Gorie, Kelly,
Godwin, Tani; (ISS-4 up) Onufrienko, Bursch, Walz; (ISS-3
down) Culbertson, Dezhurov, Tyurin |
Orbital Insertion
Altitude and Inclination |
122 nautical miles/51.6 degrees |
|
|
Shuttle
Processing Note (previous
notes) |
Launch preparations for Shuttle Endeavour remain on schedule at Pad B. Ordnance installation and pressurization of the hypergolic propellant system are complete. Work in progress includes final stowage in both the Raffaello Multi-Purpose Logistics Module (MPLM) and the crew compartment. External Tank purge and aft closeouts are under way. No work is scheduled for the Thanksgiving holidays (Thursday-Friday). Over the weekend, the launch crew will begin preparations for picking up the final countdown, scheduled for 11 p.m. Monday, Nov. 26. The seven STS-108 crewmembers will arrive at KSC on Sunday, Nov. 25. |
|
MISSION:
STS-109
-- HST
Servicing Mission 3B |
Vehicle |
Columbia/OV-102 |
Target KSC Launch
Date/Time |
Feb. 14, 2002 |
Target KSC Landing
Date/Time |
Feb. 25, 2002 |
Mission Duration |
11 days |
Crew |
Altman, Carey,
Grunsfeld, Currie, Newman, Linnehan, Massimino |
Orbital Insertion
Altitude and Inclination |
308
nautical miles/28.5 degrees |
|
|
Shuttle
Processing Note (previous
notes) |
Columbia is in the Orbiter Processing Facility (OPF) undergoing pre-launch processing for the Hubble Space Telescope servicing mission. Airlock verification and Auxiliary Power Unit (APU) leak and functional testing are continuing, and preparations are under way to install the Main Engine heat shields. |
|
MISSION:
STS-110
-- 13th
ISS Flight (8A) - ITS S0, MT |
Vehicle |
Atlantis/OV-104 |
Target KSC Launch Date/Time |
March 21, 2002 |
Target KSC Landing Date/Time |
April 1, 2002 |
Mission Duration |
11 days |
Crew |
Bloomfield, Frick,
Ross, Smith, Ochoa, Morin, Walheim |
Orbital Insertion Altitude
and Inclination |
122 nautical miles
/51.6 degrees |
|
Shuttle
Processing Note (previous notes) |
Atlantis is powered down in its OPF bay as scheduled modification work continues. Processing operations will resume in mid-December.
|
|
STRUCTURAL
INSPECTION & MODIFICATION PERIOD |
|
|
|
Shuttle Processing Note (previous
notes) |
Shuttle managers continue to assess the content, schedule and location for the structural inspection and modification down period for Orbiter Discovery. System deservicing continues with removal of the right Orbiter Maneuvering System (OMS) pod. Discovery will be rolled back for temporary storage in the Vehicle Assembly Building next week. |
|
|