MISSION:
STS-108 --
12th ISS
Flight (UF1) - Raffaello MPLM |
Vehicle |
Endeavour/OV-105 |
Target KSC Launch
Date/Time |
Nov. 29, 2001 |
Target KSC Landing
Date/Time |
Dec. 10, 2001 |
Mission Duration |
10 days, 20 hours |
Crew |
Gorie, Kelly,
Godwin, Tani; (ISS-4 up) Onufrienko, Bursch, Walz; (ISS-3
down) Culbertson, Dezhurov, Tyurin |
Orbital Insertion
Altitude and Inclination |
122 nautical miles/51.6 degrees |
|
|
Shuttle
Processing Note (previous
notes) |
At Launch Pad 39B, the Space Shuttle Main Engine Flight Readiness Test (FRT) was completed last Friday and the Helium Signature Test over the weekend. During the FRT a failure occurred in the yaw actuator of Engine Number 2. The actuator will be replaced with no impact to the launch schedule. During this week the Raffaello Multi Purpose Logistics Module will be installed in the Orbiter and the Countdown Demonstration Test (TCDT) will take place with STS-108 crew participation. |
|
MISSION:
STS-109
-- HST
Servicing Mission 3B |
Vehicle |
Columbia/OV-102 |
Target KSC Launch
Date/Time |
Feb. 14, 2002 |
Target KSC Landing
Date/Time |
Feb. 25, 2002 |
Mission Duration |
11 days |
Crew |
Altman, Carey,
Grunsfeld, Currie, Newman, Linnehan, Massimino |
Orbital Insertion
Altitude and Inclination |
308
nautical miles/28.5 degrees |
|
|
Shuttle
Processing Note (previous
notes) |
SCAPE operations were conducted over the weekend checking out the Auxiliary Power Units. Orbiter Columbia's main engines will be installed this week. |
|
MISSION:
STS-110
-- 13th
ISS Flight (8A) - ITS S0, MT |
Vehicle |
Atlantis/OV-104 |
Target KSC Launch Date/Time |
March 21, 2002 |
Target KSC Landing Date/Time |
April 1, 2002 |
Mission Duration |
11 days |
Crew |
Bloomfield, Frick,
Ross, Smith, Ochoa, Morin, Walheim |
Orbital Insertion Altitude
and Inclination |
122 nautical miles
/51.6 degrees |
|
Shuttle
Processing Note (previous notes) |
Orbiter Atlantis remains powered down for modification work that will continue until mid-December.
|
|
STRUCTURAL
INSPECTION & MODIFICATION PERIOD |
|
|
|
Shuttle Processing Note (previous
notes) |
Shuttle managers continue to assess the content, schedule and location of Discovery's structural inspection and modification period. Discovery's de-servicing operations are
under way. |
|
|