November 5, 2001

 
2001 Year at a Glance

Status Reports

October Status Reports
 
Note

This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights.  Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm for the latest schedule of future Shuttle missions.

 

MISSION: STS-108 -- 12th ISS Flight (UF1) - Raffaello MPLM

Vehicle Endeavour/OV-105
Target KSC Launch Date/Time Nov. 29, 2001
Target KSC Landing Date/Time Dec. 10, 2001
Mission Duration 10 days, 20 hours
Crew Gorie, Kelly, Godwin, Tani; (ISS-4 up) Onufrienko, Bursch, Walz; (ISS-3 down) Culbertson, Dezhurov, Tyurin 
Orbital Insertion Altitude and Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

At Launch Pad 39B, the Space Shuttle Main Engine Flight Readiness Test (FRT) was completed last Friday and the Helium Signature Test over the weekend. During the FRT a failure occurred in the yaw actuator of Engine Number 2. The actuator will be replaced with no impact to the launch schedule. During this week the Raffaello Multi Purpose Logistics Module will be installed in the Orbiter and the Countdown Demonstration Test (TCDT) will take place with STS-108 crew participation.
 

MISSION: STS-109 -- HST Servicing Mission 3B

Vehicle Columbia/OV-102
Target KSC Launch Date/Time Feb. 14, 2002
Target KSC Landing Date/Time Feb. 25, 2002
Mission Duration 11 days
Crew Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino 
Orbital Insertion Altitude and Inclination 308 nautical miles/28.5 degrees
 

Shuttle Processing Note  (previous notes)

SCAPE operations were conducted over the weekend checking out the Auxiliary Power Units. Orbiter Columbia's main engines will be installed this week.
 

MISSION: STS-110 -- 13th ISS Flight (8A) - ITS S0, MT

Vehicle Atlantis/OV-104
Target KSC Launch Date/Time March 21, 2002
Target KSC Landing Date/Time April 1, 2002
Mission Duration 11 days
Crew Bloomfield, Frick, Ross, Smith, Ochoa, Morin, Walheim
Orbital Insertion Altitude and Inclination 122 nautical miles /51.6 degrees
 

Shuttle Processing Note  (previous notes)

Orbiter Atlantis remains powered down for modification work that will continue until mid-December.
 

STRUCTURAL INSPECTION & MODIFICATION PERIOD

Vehicle Discovery/OV-103
 

Shuttle Processing Note  (previous notes)

Shuttle managers continue to assess the content, schedule and location of Discovery's structural inspection and modification period. Discovery's de-servicing operations are under way.
 

The Kennedy Space Center (KSC) Newsroom offers an electronic subscription service for status reports, news releases and other notices issued from KSC. There are two possible ways to subscribe.  You may send a blank e-mail message to ksc-news_release-subscribe@kscnews.ksc.nasa.gov or follow the instructions on the Web site at http://kscnews.ksc.nasa.gov. The system will confirm the request via e-mail.

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

11/05/2001

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc./
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director