MISSION: STS-110 -- 13th ISS Flight (8A) - ITS S0 TRUSS, MOBILE TRANSPORTER

Vehicle Atlantis/OV-104
Target KSC Launch Date/Time April 4, 2002
Target KSC Landing Date/Time April 15, 2002
Mission Duration 11 days
Crew Bloomfield, Frick, Ross, Smith, Ochoa, Morin, Walheim
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

After completing an extensive modification period during its latest processing flow, Shuttle Atlantis rolled over to the Vehicle Assembly Building (VAB) this morning for space vehicle mate, as final preparations began for the launch of the STS-110 mission to the International Space Station (ISS), scheduled for April 4.

The transporter carrying Atlantis backed out of Bay 2 of the Orbiter Processing Facility at 9:50 a.m. - 10 minutes early - and Atlantis arrived in the VAB transfer aisle at 10:20 a.m. The orbiter will be lifted vertically into its VAB high bay tonight and will be mated to the twin Solid Rocket Boosters and the External Tank early Thursday. The Shuttle Interface Test, verifying the overall status of the STS-110 space vehicle, will be conducted over the weekend.

The STS-110 mission resumes ISS construction operations with the delivery of the first segment of the Integrated Truss Structure that will support solar panels providing additional power to the ISS. The STS-110 crew, commanded by Michael Bloomfield, will also install the first part of a Mobile Transporter that will provide a moveable base for the station's Canadian robotic arm.
 

The Kennedy Space Center (KSC) Newsroom offers an electronic subscription service for status reports, news releases and other notices issued from KSC. There are two possible ways to subscribe.  You may send a blank e-mail message to ksc-news_release-subscribe@kscnews.ksc.nasa.gov or follow the instructions on the Web site at http://kscnews.ksc.nasa.gov. The system will confirm the request via e-mail.

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

03/06/2002

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc.
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director