DATE: July 8, 1998 LETTER: 98-CU-13
TO: FEDERALLY INSURED CREDIT UNIONS
SUBJECT: Year 2000 Testing Guidance
The testing phase is the most important
phase of the Year 2000 process. Our May 12, 1998 Letter to Credit
Unions (98-CU-10) provided you with the Federal Financial Institution
Examination Council's (FFIEC) guidance on testing. In that letter,
we stated that experts estimate the testing phase will take more
than 50 percent of the time, cost, and personnel of Year 2000
preparations. The purpose of testing systems is to make sure
that they process transactions correctly before, during, and after
the transition from 1999 to 2000 and that the correct dates are
stored in the computer system. Thorough testing will help ensure
that Year 2000 efforts have been successful. All credit unions
are expected to be active in Year 2000 testing.
Many credit unions have stated that
the FFIEC testing guidance paper was too general in nature, and
that more information that is specifically geared to credit unions
is needed. The purpose of this letter is to give you a better
understanding of NCUA's expectations and the different ways you
can approach Year 2000 testing. Due to the wide variety of hardware,
software, and other equipment used in credit unions, we cannot
provide a step by step instruction for the testing process. However,
we can explain some key testing concepts so that you can better
communicate with your vendor(s) or service provider(s).
This letter covers the key questions
identified below. The letter is designed so that you can go directly
to the question where you need additional guidance and skip over
those sections that do not apply to your credit union.
Management is responsible for determining
the best testing approach for the credit union. In putting your
test approach in writing, you should include the types of specific
tests you'll use to make sure that your systems are Year 2000
ready. Part of the testing process is to compare the results
from your tests with the results you expected to get. While this
letter discusses several ways to test your systems and explains
several types of tests to be performed, the list doesn't include
everything. You should work with your vendors and organizations
where you exchange information electronically to develop the specific
ways you will test your systems.
WHAT ARE THE DIFFERENT WAYS
I CAN TEST MY SYSTEM?
There are numerous acceptable ways to
test your system, and since few credit unions have exactly the
same computer set-up, a particular approach may be all right for
some credit unions but not for others. You need to work with
your vendors, other credit unions that use your same system, and
any external organizations where you exchange information electronically
to develop the best approach for testing your individual credit
union's systems and hardware.
To start the testing process, management
should develop an overall approach for testing the credit union's
hardware and software. This big picture view should take place
even before the credit union has renovated software. After management
determines the overall testing approach, that approach should
be documented in a written testing plan. Credit unions should
include end-users, such as loan processors, tellers, etc., throughout
the testing process to make sure that the tests performed include
all of the routine activities of the credit union. Credit unions
should also work closely with their vendors to make sure that
the approach selected is valid for the system(s) being tested.
A credit union may discover that its vendor has already developed
generic test plans and procedures that the credit union may customize
for their own unique computer environment and testing needs.
The following is a list of acceptable
approaches for testing. We understand that there may be other
acceptable approaches or a combination of approaches which are
appropriate for credit unions; therefore, this list is not all
inclusive. If you want to use an approach that is not on this
list, feel free to contact your examiner to discuss the pros and
cons of that approach. Please keep in mind that our examiners
are not experts on every aspect of Y2K, and may need to seek additional
guidance from the regional office on your planned approach.
TESTING IN MY CREDIT UNION
Testing in your credit union involves
testing the software and hardware systems totally within your
credit union's computer environment. (NCUA considers this type
of testing to include those credit unions that chose to establish
a separate computer environment specifically for testing, including
identical hardware and software.) Since credit union management
has direct control over this type of testing process, testing
in your credit union is generally the most thorough and reliable
way to test for Year 2000 readiness. However, for this approach
to work, credit unions need to make sure that they have sufficient
resources available, such as credit union staff or volunteers,
or outside contractors. Also, credit unions may find it difficult
to get the information needed from their vendors to fully and
safely test their systems.
RISKS: This approach represents the lowest level of testing risk because the credit union's testing occurs in the real-world environment used in the credit union's normal operations. However, this type of testing has increased risks of error in preparing systems for testing. Under no circumstances should testing at your credit union take place using the live production environment. For those more complex credit unions that may have to take all ATM and audio response systems down or disable system security checks while testing, just a reminder that taking these systems down will make these safeguards inaccessible to the members during the test period increasing the risk of withdrawals beyond the available balances during that time. It is very important that the information on systems to be tested is backed up exactly according to procedures provided by the vendor so that the information can be safely restored after the tests are completed. Credit unions using this approach should have a history of being able to restore backed-up data. Credit unions must be cautious of inadvertently changing member information in the system during this type of testing. In addition, moving the date ahead on some systems may have unexpected consequences and should be discussed thoroughly with the vendor. Again, credit unions using this testing approach should be sure they have specific instructions from the vendor for data backup, data restore, and system date change procedures. Credit unions who do not follow those procedures exactly may have problems that will stop them from returning to normal operations after the testing has been performed.
RELYING ON OTHER CREDIT UNIONS TO TEST MY SYSTEMS
For many credit unions, relying on other
credit unions to test systems through vendor user/customer groups
can be a viable option for Year 2000 testing and a resource throughout
the entire Year 2000 process. User group testing is a form of
proxy testing where your vendor or service provider tests the
system with a select number or sample of credit unions. Test
results are then shared with all similarly situated clients of
the vendor. If a credit union is going to use this testing approach,
it is very important that credit union officials review the user
group's sample of data to be tested, steps to perform the test
(also called a test script), and the expected results to ensure
they cover the products and services offered by their credit union.
For example, if a credit union offers share certificates or share
drafts to the membership, yet the test scripts for a particular
user group's testing do not contain any test plans or procedures
for these products, the credit union will need to test this section
of its system separately.
Credit unions planning to rely on user
group testing must make sure that their software, operating system,
and hardware are either identical, or function in a nearly identical
manner to the system(s) tested by the user group. Management
is responsible for determining if a credit union's systems are
similar enough to the test group for this approach to work. NCUA
will allow credit unions to rely, either in whole or in part,
on user group testing if, at a minimum, the following conditions
are met:
RISKS:
The risks involved with user group testing include:
|
TESTING AT YOUR DISASTER RECOVERY SITE
Some credit unions have access to remote
back-up locations as part of their routine disaster recovery plans.
These locations can be used to test for Year 2000 readiness.
Credit unions which plan to use these locations to test renovated
software must plan ahead to make sure that sufficient time and
resources are available at the disaster recovery site. As with
user group testing, credit unions must make sure its hardware,
software, and operating system are identical or function identically
to that provided at the disaster recovery site.
RISKS: The risks involved with disaster recovery site testing relate to the degree of similarity, or differences, between the disaster recovery site and the credit union's actual operations. In addition, duplicating and testing the credit union's external interfaces may not be practical or feasible which would require credit unions to supplement the disaster recovery site testing with some testing within the credit union. An additional risk is that some disaster recovery site vendors may not be able to schedule all of their customers at convenient testing times due to the volume of testing requests.
RELYING ON MY VENDOR TO TEST MY SYSTEMS
Vendor testing is another form of proxy
testing that is generally reserved for on-line/real time and batch
type systems where the primary hardware and software generally
are at the vendor's location. With these types of processing
systems, the vendor will most likely conduct the tests since credit
unions do not have sufficient access to the hardware and software
to perform adequate tests. Also, the risk of losing member information
is much greater when testing a live database, and may represent
an undue risk of loss. Therefore, NCUA will accept this type
of testing if the following conditions, at a minimum, are met:
RISKS: For some systems, vendor testing may be the most risky method for testing Year 2000 readiness primarily because credit unions do not maintain direct control over the testing process. Vendors may be more liberal in determining that test results are accurate due to an inherent lack of impartiality and oversight for the process.
WHAT ARE THE TYPES OF TESTS
THAT SHOULD BE PERFORMED ON MY SYSTEMS?
In this section, we list some of the
basic types of tests that should be performed on systems. Understanding
the basic terms involved may help clarify the testing process.
The listing will define five testing terms that your vendor or
examiner may use.The first three types of testing are normally
performed by the system developer.
UNIT (COMPONENT) TESTING:
This type of testing focuses on one particular program or module,
such as a loan initiation process or the general ledger module.
Vendors will perform some level of unit testing to assure that
the renovated program works.
INTEGRATION TESTING:
This type of testing involves checking several units (programs
or modules) together to make sure that they function together
as intended. Interfaces (or bridges) between programs or modules
within the system should be tested as part of the integration
testing to assure that they continue to share and interpret information
correctly. An example of this type of testing would be opening
an account, granting a loan, performing an ATM transaction, and
finally closing the account. In this example, many different
programs or components must work together properly to successfully
complete the test.
REGRESSION TESTING:
This testing type involves checking the programs to make sure
that Year 2000 fixes haven't created new problems in other areas
of the program. Vendors will usually be responsible for this
type of testing.
EXTERNAL INTERFACE TESTING:
Testing electronic information exchanges between organizations
(third parties) is an essential part of Year 2000 testing. Examples
of these interfaces include:
In many systems, standard third party
interfaces will be tested by the vendor. In these cases, credit
unions should review the proposed testing process to make sure
that the interface is adequately tested and compliant (using the
same due diligence process as discussed above under user group
and vendor testing). Management should contact vendors to receive
documentation on the data to be tested, the steps used in the
test, and the expected results. Credit unions will need to make
sure that the test data covers the transactions, products, and
services provided by the credit union. As an example, the vendor
may test the actual electronic exchange of information between
the organizations, but not test the actual posting and use of
the information in the credit union's system. Credit unions should
also discuss with vendors the actions taken to make sure that
the credit union's information is not changed if the external
party's exchange of information does not work.
THIRD PARTY INTERFACE PROXY TESTING:
This type of testing involves vendor level testing for the electronic
funds transfer products and services provided through third parties.
In-house developed systems and service bureau system vendors
can test the interfaces to external processors (such as share
drafts, ATMs, ACH, POS, etc.) on behalf of the credit union, if
at a minimum the credit union makes sure that:
Credit unions which interface directly
with the Federal Reserve should become familiar with the Federal
Reserve's Century Date Change Bulletins. These bulletins can
be found on the Internet at http://www.frbsf.org/fiservices/cdc.
WHAT ARE NCUA'S EXPECTATIONS
FOR TESTING MY SYSTEM?
NCUA's expectations for testing remain
unchanged from our previous statements contained in NCUA Letters
to Credit Unions 97-CU-12 and 98-CU-4. NCUA expects credit union
officials to practice due diligence in making sure that their
systems are Year 2000 ready. This means that management and officials
must be aware of the status of their plans to fix the credit union's
systems. As stated earlier, testing is the most critical part
of making sure that a credit union's systems are ready for the
Year 2000. Management and officials should continue to receive
reports on the status of testing plans and results.
THIRD PARTY CERTIFICATIONS:
NCUA is unaware of any external party or company that certifies
whether a system, vendor, institution, or business is Year 2000
compliant. The legal liabilities associated with such a statement
are simply too great. Typically, those companies which provide
certification are stating that the approaches and procedures used
should result in Year 2000 readiness. Credit unions cannot rely
upon this type of certification for determining whether a system
or vendor is Year 2000 ready.
COMPONENT CERTIFICATION:
Some companies provide Year 2000 "certification" for
components they produce. This type of certification is not a
substitute for testing. As an example, a credit union may use
a network interface card which has been certified as compliant.
Management may decide not to perform unit testing for that particular
card; however, as they perform test of the entire system they
will test the network where that card resides.
REVIEW OF TEST STRATEGIES:
Our examiners will review testing documentation to make sure
credit unions are actively involved in the process. Credit unions
may not rely on vendor or third party statements of compliance
without comparing test results with expected results. We anticipate
that all credit unions will need to be involved in some level
of testing within the credit union itself due to the differences
in hardware, software, operating systems, and third party interfaces
from one credit union to the next.
Examiners will review the credit union's
overall Year 2000 test strategy, written plan, and the actual
performance of the steps contained in the plan. The goal of these
reviews will be to assess management's program toward achieving
Year 2000 readiness and the appropriateness of the testing approach
selected.
HOW SHOULD I DOCUMENT MY
EFFORTS AT TESTING?
TEST PLANS:
Developing a test plan is crucial to efficiently performing this
phase of Year 2000 preparation. The examiner will review the
credit union's test plan to assess management's awareness of the
testing issues and the appropriateness to their circumstances.
All credit unions should put testing plans in writing. The amount
and type of documentation for the test plan should be based on
the complexity of a credit union's systems, the testing approach
management selected, and the specific testing environment. The
purpose of a written plan is to provide guidance to the credit
union as it implements the testing process. The written plan
should consider the following key elements, where appropriate,
based on the complexity of systems and approach selected:
DUE DILIGENCE OF TEST RESULTS:
Management must document their due diligence efforts to make
sure that systems are Year 2000 ready. The reason for this documentation
is two-fold, first to assist the credit union in managing the
risks associated with the Year 2000 process. Second, the credit
union's documented efforts of due diligence are the credit union's
best defense if any Year 2000 litigation is brought against the
credit union.
The credit union should identify in
board minutes the following aspects of their Year 2000 plans:
SHOULD MY SUPERVISORY COMMITTEE
BE INVOLVED WITH TESTING?
NCUA expects supervisory committees
and/or internal auditors to provide a proper level of oversight
for the testing phase as discussed in NCUA Letter to Credit Unions
No. 97-CU-10. Some items to consider include:
WHAT ACTIONS SHOULD I TAKE
IF I'M GOING TO CHANGE TO A DIFFERENT SYSTEM?
NCUA recognizes that credit unions may
change data processors between now and the Year 2000 for a variety
of reasons. If a credit union plans to change or convert a mission
critical system, and that change will cause the credit union to
miss one of the dates contained in NCUA Letter to Credit Unions
No. 98-CU-4, NCUA's Year 2000 Contingency Plan, the credit union
must submit a letter detailing the credit union's conversion plans
to the NCUA Regional Director, with a copy to the State Supervisior.
In these circumstances, credit unions do not need to test the
old system for Year 2000 compliance. To help NCUA analyze the
credit union's due diligence in reviewing the conversion decision,
the letter must include the following information:
NCUA remains committed to working with
credit unions to help them prepare for the Year 2000. If you
have any questions, please contact your district examiner, regional
office, or state supervisory authority.