This is the accessible text file for GAO report number GAO-07-30R 
entitled 'Rebuilding Iraq--Status of DOD's Reconstruction Program' 
which was released on December 15, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

December 15, 2006: 

Congressional Committees: 

Subject: Rebuilding Iraq--Status of DOD's Reconstruction Program: 

Of the $18.4 billion that Congress appropriated for Iraq relief and 
reconstruction in fiscal year 2004, the Department of Defense (DOD) 
received the largest share--$13.5 billion.[Footnote 1] As of September 
30, 2006, DOD had obligated[Footnote 2] about $13.1 billion and 
disbursed about $9.7 billion--$5.6 billion for construction, $3.6 
billion for nonconstruction (e.g., engineering, procurement, and the 
delivery of equipment), and about $480 million for related overhead 
costs. Among the many contracts DOD uses in Iraq, DOD has obligated 
about $3.7 billion for 12 large-scale, multiple-year design-build 
contracts for major construction projects. The design-build contracting 
approach makes one award for both the design and construction of a 
project, thus eliminating the need for a separate bidding process for 
the construction phase. 

To help Congress monitor the current progress and costs of DOD's 
reconstruction activities in Iraq, this report discusses (1) the status 
of the current construction work and targeted completion dates and (2) 
the support costs incurred by the design-build contractors in DOD's 
construction program. 

To identify the status of DOD's current construction work, we 
summarized DOD's work-in-place metrics provided by the Army Corps of 
Engineers' Gulf Region Division/Project and Contracting Office (GRD/ 
PCO) in Iraq.[Footnote 3] DOD uses this metric to compare the value of 
completed and planned work for its contractors, including the design- 
build contractors. This metric is a rudimentary measure of earned 
value, a measure of total value against individual contract amounts, 
including design and procurements made. The work does not necessarily 
have to be "in place" or constructed.[Footnote 4] To identify the 
support costs[Footnote 5] incurred by DOD's design-build contractors in 
Iraq, we analyzed the financial data provided by the Joint Contracting 
Command-Iraq/Afghanistan (JCC-I/A) for each design-build contractor. 
(See app. 1 for details on our scope and methodology.) As part of our 
work, we interviewed U.S. government personnel in the United States and 
Iraq and traveled to Iraq in November 2005 and March 2006 to meet with 
U.S. government officials overseeing DOD construction activities. We 
conducted our review from November 2005 to December 2006 in accordance 
with generally accepted government auditing standards. We prepared this 
report under the Comptroller General's authority to conduct evaluations 
on his own initiative for Congress. 

Results in Brief: 

While financial data show that DOD has obligated most (97 percent) of 
its $13.5 billion in fiscal year 2004 reconstruction funds, work-in- 
place data show that about 29 percent, or $2.3 billion, of DOD's 
construction program is incomplete, as of October 8, 2006. Continued 
congressional oversight of these activities will be needed since DOD 
estimates that this work will not be completed until mid-to late 2008. 
The incomplete work varies by sector, with 10 percent of planned 
construction remaining in the security and justice sector and 38 
percent remaining in the communications and transportation sector. 
Activities in the public works and water sector; the buildings, 
education, and health sector; and the transportation and communications 
sector will not be completed until mid-to late 2008. Although the 
United States has generally not met its goals for reconstruction 
activities in Iraq, DOD projects that its remaining construction 
projects will enable Iraq to increase its production of oil, 
electricity, and clean water and treated sewerage. As GAO's past work 
has shown, the challenging security environment, persistent attacks on 
U.S.-funded infrastructure projects, and sustainment challenges could 
make it difficult for DOD to achieve this progress.[Footnote 6] 

DOD's design-build contractors will incur estimated support costs of 
about $1.2 billion or about 33 percent of projected completion costs of 
$3.7 billion. The support costs include estimated security costs of 
about $359.6 million. In response to higher-than-anticipated support 
costs, DOD officials have pursued alternative contracting strategies. 
For example, DOD officials have contracted directly with Iraqi firms in 
the electricity and transportation sectors rather than relying 
exclusively on U.S. design-build contractors to complete the work. U.S. 
officials state that the transition to direct contracting with local 
Iraqi and international contractors could lead to cost reductions. Due 
to the lack of available information on the costs of direct contracts, 
we were not able to establish the extent to which support costs could 
be avoided at the time of our review. The direct contracting approach 
also has the potential of increasing Iraqi ownership of reconstruction 
efforts and employing more local Iraqis. 

The Department of Defense provided technical comments on our draft 
report that we incorporated, where appropriate. In its comments, 
Defense stated that it appreciated the balanced report that GAO has 
developed. Defense also clarified that the work-in-place measure used 
in our report is a rudimentary measure of earned value and measures 
total value against individual contract amounts, including design and 
procurements made. The measure does not only apply to work that is "in 
place" or constructed. 

Background: 

From May 2003 through June 2004, the Coalition Provisional Authority 
(CPA), led by the United States and the United Kingdom, was the United 
Nations-recognized authority responsible for the temporary governance 
of Iraq and for overseeing, directing, and coordinating the 
reconstruction effort. The CPA used a multitiered contracting approach 
for Iraq reconstruction activities. The CPA, through various military 
organizations, awarded 1 lead contract, 6 sector contracts, and 12 
design-build contracts in early 2004 (see fig. 1). Under this approach, 
the CPA used one lead contract to provide overall coordination and 
direction for the rebuilding program. Six sector contractors helped 
define sector priorities and project requirements, and assisted DOD in 
managing the 12 design-build contractors used to perform the on-the- 
ground construction work. 

Figure 1: DOD Construction Program Carried Out through a Multitiered 
Contracting Approach: 

[See PDF for Image] 

Source: GAO. 

[End of Figure] 

On June 28, 2004, the CPA transferred power to an interim sovereign 
Iraqi government, the CPA was dissolved, and Iraq's transitional period 
began. After the transfer, National Security Presidential Directive 36 
(NSPD 36) passed responsibility for the supervision and general 
direction of U.S. reconstruction assistance in Iraq to the Secretary of 
State. The directive also established a temporary organization within 
the department called the Iraq Reconstruction Management Office to 
facilitate the transition in Iraq. The Project and Contracting Office 
(PCO), a temporary organization in the Department of Defense, was 
tasked under NSPD 36 with providing acquisition and project management 
support. In late 2005, DOD merged PCO with the Army Corps of Engineer's 
Gulf Region Division, which now supervises DOD reconstruction 
activities in Iraq. 

DOD Has Made Some Progress, but Significant Reconstruction Work 
Remains: 

Although DOD has made some progress in restoring Iraq's essential 
services, it has not met program goals and estimates that it will not 
complete the remainder of its work until mid-to late 2008. While 
financial data show that DOD has obligated 97 percent of its $13.5 
billion fiscal year 2004 reconstruction funds, work-in-place data show 
that about 29 percent, or $2.3 billion, of DOD's planned construction 
activities valued at $8 billion are incomplete, as of October 8, 2006. 
This metric applies to DOD's Iraq construction activities using these 
funds and is not exclusive to design-build contractors. Work-in-place 
data are a measure of progress and compare completed to planned 
construction work. According to DOD, the remaining work will enable 
Iraq to increase the production of oil, electricity, clean water, and 
treated sewerage, among other outcomes. However, the challenging 
security environment, persistent attacks on U.S.-funded infrastructure 
projects, and sustainment challenges could make it difficult for DOD to 
achieve this progress. 

Of the $18.4 billion that Congress appropriated for Iraq relief and 
reconstruction in fiscal year 2004, DOD received the largest share-- 
$13.5 billion. As of September 30, 2006, DOD had obligated $13.1 
billion--97 percent. DOD obligated $8.2 billion of these funds on 
construction activities, including those of the design-build 
contractors; $4.4 billion on nonconstruction items (e.g., engineering, 
procurement, and delivery of equipment); and about $520 million in DOD- 
related overhead costs. 

One way DOD measures progress is to use work-in-place data for its 
construction contractors, including the design-build contractors. These 
data are reported by the GRD/PCO to the Secretary of the Army every two 
weeks. Work-in-place measures indicate that about 71 percent of all of 
DOD's planned work has been completed as of October 8, 2006, including 
90 percent in the security and justice sectors, 73 percent of the work 
in the oil sector, and 64 percent of the work in the electricity sector 
(see table 1). 

Table 1: Comparison of Planned and Completed Work by Sector Using All 
DOD Acquisition Strategies, as of October 8, 2006: 

Dollars in billions: 

Sector: Security and justice; 
Planned work: $1.46; 
Estimated work-in-place (completed work): $1.31; 
Completed work relative to planned work (percent): 90. 

Sector: Electricity; 
Planned work: 3.00; 
Estimated work-in-place (completed work): 1.92; 
Completed work relative to planned work (percent): 64. 

Sector: Oil infrastructure; 
Planned work: 1.30; 
Estimated work-in-place (completed work): 0.95; 
Completed work relative to planned work (percent): 73. 

Sector: Public works and water; 
Planned work: 1.36; 
Estimated work-in-place (completed work): 0.93; 
Completed work relative to planned work (percent): 69. 

Sector: Buildings, education, and health; 
Planned work: 0.50; 
Estimated work-in-place (completed work): 0.36; 
Completed work relative to planned work (percent): 72. 

Sector: Transportation and communications; 
Planned work: 0.42; 
Estimated work-in-place (completed work): 0.26; 
Completed work relative to planned work (percent): 62. 

Total; 
Planned work: $8.04; 
Estimated work-in-place (completed work): $5.73; 
Completed work relative to planned work (percent): 71. 

Source: GRD/PCO. 

Note: This measure includes DOD construction activities using Iraq 
relief and reconstruction funds in these sectors and is not exclusive 
to design-build contractor activities. 

[End of table] 

DOD reports that it has increased electricity generation, oil 
production, and water treatment capacity, and built or renovated 
schools, hospitals, border forts, post offices, and railway stations. 
Table 2 shows by sector the planned completion dates and selected 
reconstruction goals for all DOD reconstruction activity, including the 
design-build and all other contracts. 

Table 2: DOD Reconstruction Goals, Achievements, and Remaining Work, 
Funded by Iraq Relief and Reconstruction Funds, as of October 2006: 

Sector (estimated completion date): Security and justice[A] (Dec. 
2007); 
Program product: Border posts; 
DOD goals: Program target: 252; 
DOD goals: Current achieved: 245; 
DOD goals: Remaining: 7. 

Sector (estimated completion date): Security and justice[A] (Dec. 
2007); 
Program product: Points of entry; 
DOD goals: Program target: 13; 
DOD goals: Current achieved: 9; 
DOD goals: Remaining: 4. 

Sector (estimated completion date): Security and justice[A] (Dec. 
2007); 
Program product: Military facilities; 
DOD goals: Program target: 204; 
DOD goals: Current achieved: 120; 
DOD goals: Remaining: 84. 

Sector (estimated completion date): Security and justice[A] (Dec. 
2007); 
Program product: Police facilities; 
DOD goals: Program target: 398; 
DOD goals: Current achieved: 348; 
DOD goals: Remaining: 50. 

Sector (estimated completion date): Security and justice[A] (Dec. 
2007); 
Program product: Fire facilities; 
DOD goals: Program target: 94; 
DOD goals: Current achieved: 86; 
DOD goals: Remaining: 8. 

Sector (estimated completion date): Security and justice[A] (Dec. 
2007); 
Program product: Prisons/courts; 
DOD goals: Program target: 46; 
DOD goals: Current achieved: 29; 
DOD goals: Remaining: 17. 

Sector (estimated completion date): Security and justice[A] (Dec. 
2007); 
Program product: Miscellaneous facilities; 
DOD goals: Program target: 58; 
DOD goals: Current achieved: 33; 
DOD goals: Remaining: 25. 

Sector (estimated completion date): Electricity (Dec. 2007); 
Program product: Contributed peak generation capacity (megawatts); 
DOD goals: Program target: 1,879; 
DOD goals: Current achieved: 1,420; 
DOD goals: Remaining: 459. 

Sector (estimated completion date): Electricity (Dec. 2007); 
Program product: Hours of power per day (U.S. goal); 
DOD goals: Program target: 10-12 Iraq and Baghdad; 
DOD goals: Current achieved: 10.8 Iraq and 5.1 Baghdad; 
DOD goals: Remaining: N/A. 

Sector (estimated completion date): Electricity (Dec. 2007); 
Program product: Transmission capacity (megawatts); 
DOD goals: Program target: 6,000; 
DOD goals: Current achieved: 5,500; 
DOD goals: Remaining: 500. 

Sector (estimated completion date): Electricity (Dec. 2007); 
Program product: Distribution substations; 
DOD goals: Program target: 89; 
DOD goals: Current achieved: 48; 
DOD goals: Remaining: 41. 

Sector (estimated completion date): Oil (April 2007); 
Program product: Crude oil capacity (million barrels per day); 
DOD goals: Program target: 3; 
DOD goals: Current achieved: 2.5; 
DOD goals: Remaining: 0.5. 

Sector (estimated completion date): Oil (April 2007); 
Program product: Natural gas production (million standard cubic feet 
per day); 
DOD goals: Program target: 800; 
DOD goals: Current achieved: 600; 
DOD goals: Remaining: 200. 

Sector (estimated completion date): Oil (April 2007); 
Program product: Liquefied petroleum gas (LPG) production capacity 
(tons per day); 
DOD goals: Program target: 3,000; 
DOD goals: Current achieved: 1,200; 
DOD goals: Remaining: 1,800. 

Sector (estimated completion date): Public works and water (July 2008); 
Program product: Potable water (delivery capacity added) (thousand 
cubic meters per day); 
DOD goals: Program target: 1,150; 
DOD goals: Current achieved: 419; 
DOD goals: Remaining: 731. 

Sector (estimated completion date): Public works and water (July 2008); 
Program product: Sewerage treatment capacity added (thousand cubic 
meters per day); 
DOD goals: Program target: 48;
DOD goals: Current achieved: 0; 
DOD goals: Remaining: 48. 

Sector (estimated completion date): Public works and water (July 2008); 
Program product: Repair dams, barrages, and canals (number repaired); 
DOD goals: Program target: 2; 
DOD goals: Current achieved: 1; 
DOD goals: Remaining: 1. 

Sector (estimated completion date): Public works and water (July 2008); 
Program product: Irrigates land (hectares); 
DOD goals: Program target: 387k; 
DOD goals: Current achieved: 31k; 
DOD goals: Remaining: 356k. 

Sector (estimated completion date): Buildings, education, and health 
(July 2008); 
Program product: Government building projects; 
DOD goals: Program target: 6; 
DOD goals: Current achieved: 5; 
DOD goals: Remaining: 1. 

Sector (estimated completion date): Buildings, education, and health 
(July 2008); 
Program product: Hospital projects/public health centers/other 
significant health projects; 
DOD goals: Program target: 25/142/2; 
DOD goals: Current achieved: 14/7/0; 
DOD goals: Remaining: 11/135/2. 

Sector (estimated completion date): Buildings, education, and health 
(July 2008); 
Program product: School built or renovated; 
DOD goals: Program target: 810; 
DOD goals: Current achieved: 806; 
DOD goals: Remaining: 4. 

Sector (estimated completion date): Transportation and communications 
(Dec. 2008); 
Program product: Railway station renovations; 
DOD goals: Program target: 99; 
DOD goals: Current achieved: 85; 
DOD goals: Remaining: 14. 

Sector (estimated completion date): Transportation and communications 
(Dec. 2008); 
Program product: Port projects/aviation projects; 
DOD goals: Program target: 7/19; 
DOD goals: Current achieved: 4/13; 
DOD goals: Remaining: 3/6. 

Sector (estimated completion date): Transportation and communications 
(Dec. 2008); 
Program product: Village roads and expressways (kilometers); 
DOD goals: Program target: 427; 
DOD goals: Current achieved: 239; 
DOD goals: Remaining: 188. 

Sector (estimated completion date): Transportation and communications 
(Dec. 2008); 
Program product: Advanced first responder network projects[B]; 
DOD goals: Program target: 3; 
DOD goals: Current achieved: 3; 
DOD goals: Remaining: 0. 

Sector (estimated completion date): Transportation and communications 
(Dec. 2008); 
Program product: Post offices/major communications institutions; 
DOD goals: Program target: 34/2; 
DOD goals: Current achieved: 31/1; 
DOD goals: Remaining: 3/1. 

Source: GRD/PCO. 

[A] Security and justice sector targets and achievements include 
projects completed by the Multi-National Security Transition Command-- 
Iraq. 

[B] For the purposes of analyzing work-in-place numbers, the Advanced 
First Responder Network was included in the communications sector. The 
network is also sometimes considered to be a part of the security and 
justice sector. 

[End of table] 

DOD estimates, however, that the remaining 29 percent of the planned 
work will not be completed until mid-to late 2008. According to DOD, 
this remaining work will enable Iraq to increase the production of oil, 
electricity, clean water, and treated sewerage by: 

* adding 459 megawatts of peak generation capacity, 500 megawatts of 
transmission capacity, and building 41 distribution substations in the 
electricity sector;[Footnote 7] 

* increasing crude oil production capacity by 0.5 million barrels per 
day and increasing petroleum gas production by 1,800 tons per day; and: 

* adding an additional 731,000 cubic meters of potable water delivery 
capacity per day, and 48,000 cubic meters of sewage treatment capacity 
per day, and 356,000 hectares of irrigated land. 

However, the metrics used to report progress make it difficult to 
determine the impact of the U.S. reconstruction effort. For example, we 
reported previously that in the water resources and sanitation sector, 
little was known about how U.S. efforts were improving the amount and 
quality of water reaching Iraqi households or their access to the 
sanitation services.[Footnote 8] Reported output measures overestimated 
the amount of potable water reaching Iraqi households because U.S. 
officials estimate that 60 percent of water treatment output is lost 
due to leakage, contamination, and illegal connections. 

The U.S. mission in Iraq reported in December 2005 that it had 
developed a set of metrics to better estimate the potential impact that 
U.S. water and sanitation reconstruction efforts were having on Iraqi 
households. However, it acknowledges that it is difficult to measure 
how much water the Iraqis actually receive or whether the water is 
potable. The mission report notes that, without such comprehensive 
data, mission efforts to accurately assess the impact of U.S. 
reconstruction efforts on water and sanitation services are limited. 

In addition, overall security conditions in Iraq have deteriorated 
since June 2003, as evidenced by attack trends, growing sectarian 
violence, and the growth and influence of militias. Enemy-initiated 
attacks against the coalition, its Iraqi partners, and infrastructure 
have continued to increase over time, complicating efforts to rebuild 
and restore essential services. Overall, attacks increased by 23 
percent from 2004 to 2005. After declining in the fall of 2005, the 
number of attacks rose to the highest level ever in July 2006 (see fig. 
2).[Footnote 9] 

Figure 2: Enemy-Initiated Attacks against the Coalition and Its Iraqi 
Partners, May 2003 through August 2006: 

[See PDF for Image] 

Sources: Multi-National Force-Iraq and DIA/J2. 

[End of Figure] 

In July 2006, the State Department reported to Congress that the recent 
upturn in violence had hindered efforts to engage fully with Iraqi 
partners and noted that a baseline of security was a prerequisite for 
moving forward on the political and economic tasks essential to 
achieving the conditions to withdraw U.S. forces. Unstable security 
conditions will make it more difficult for DOD to achieve its planned 
construction goals and targets. 

DOD's Design-Build Contractors in Iraq Will Incur Support Costs of 
about 33 Percent: 

Our analysis shows that DOD's design-build contractors will incur 
support costs of about $1.2 billion, or about 33 percent of projected 
completion costs of $3.7 billion. According to agency officials, the 
design-build contracting model used in Iraq entailed costs such as 
mobilizing, feeding, housing, and protecting an expatriate workforce. 
These officials further stated that these costs are typically incurred 
on most large-scale international construction projects but were higher 
due, in part, to the poor security environment and the difficulties in 
managing contract costs in Iraq. In response to higher-than-anticipated 
support costs, DOD officials have pursued alternative contracting 
strategies. For example, DOD officials have contracted directly with 
Iraqi firms in the electricity and transportation sectors rather than 
relying exclusively on U.S. design-build contractors to complete the 
work. 

DOD's design-build contractors will incur estimated support costs of 
about $1.2 billion, or about 33 percent of the projected completion 
costs of $3.7 billion (see table 3).[Footnote 10] These costs ranged 
from approximately 24 percent in the public works and water sector to 
about 67 percent in the transportation sector. In the transportation 
sector, the design-build contractor demobilized and left Iraq shortly 
after award of the contract in March 2004 because DOD and the 
contractor mutually agreed that the overall program costs were too 
high. As a result, the majority of design-build costs for the 
transportation sector accrued by the U.S. were support costs 
accumulated during the contractor's brief stay in-country. 

Table 3: Comparison of Design-Build Contractors' Support Costs by 
Sector, as of October 2006: 

Dollars in millions: 

Sector: Security/justice; 
Design-build contractors' estimated completion costs: $343.4; 
Support costs, including security costs: $97.8; 
Support costs as a percentage of estimated completion costs: 28.5%; 
Security costs only: $29.6; 
Security costs as a percentage of estimated completion costs: 8.6%. 

Sector: Electricity; 
Design-build contractors' estimated completion costs: 732.1; 
Support costs, including security costs: 259.9; 
Support costs as a percentage of estimated completion costs: 35.5; 
Security costs only: 105.4; 
Security costs as a percentage of estimated completion costs: 14.4. 

Sector: Oil infrastructure; 
Design-build contractors' estimated completion costs: 1,201.3; 
Support costs, including security costs: 467.4; 
Support costs as a percentage of estimated completion costs: 38.9; 
Security costs only: 113.8; 
Security costs as a percentage of estimated completion costs: 9.5. 

Sector: Water resources; 
Design-build contractors' estimated completion costs: 852.8; 
Support costs, including security costs: 207.8; 
Support costs as a percentage of estimated completion costs: 24.4; 
Security costs only: 59.2; 
Security costs as a percentage of estimated completion costs: 6.9. 

Sector: Building, health, and education; 
Design-build contractors' estimated completion costs: 369.2; 
Support costs, including security costs: 124.6; 
Support costs as a percentage of estimated completion costs: 33.7; 
Security costs only: 27.6; 
Security costs as a percentage of estimated completion costs: 7.5. 

Sector: Communications; 
Design-build contractors' estimated completion costs: 158.1; 
Support costs, including security costs: 46.6; 
Support costs as a percentage of estimated completion costs: 29.5; 
Security costs only: 20.6; 
Security costs as a percentage of estimated completion costs: 13.0. 

Sector: Transportation; 
Design-build contractors' estimated completion costs: 17.6; 
Support costs, including security costs: 11.8; 
Support costs as a percentage of estimated completion costs: 67.5; 
Security costs only: 3.4; 
Security costs as a percentage of estimated completion costs: 19.4. 

Total; 
Design-build contractors' estimated completion costs: $3,674.5; 
Support costs, including security costs: $1,215.9; 
Support costs as a percentage of estimated completion costs: 33.1%; 
Security costs only: $359.6; 
Security costs as a percentage of estimated completion costs: 9.8%. 

Sources: JCC-I/A and design-build contractors. 

Note: Support costs generally include transportation and mobilization, 
life support, management, administration, and security. 

[End of table] 

Officials in the electricity and oil sectors encountered challenges 
controlling support costs stemming from the level of contractors' 
reconstruction efforts. In the electricity sector, high cost estimates 
by one design-build contractor resulted in the termination of five task 
orders and the resolicitation of that work. After the task orders were 
canceled, the design-builder was slow to reduce overhead costs in 
accordance with the reduced workload, according to agency officials and 
documents. In the oil sector, DOD officials required the two design- 
build contractors to reorganize their management structure and improve 
their cost reporting as a result of concerns regarding high 
costs.[Footnote 11] 

DOD also estimates that, across all sectors, the design-build 
contractors will incur security costs of about $360 million, or about 
9.8 percent of estimated completion costs of $3.7 billion, during their 
reconstruction activities in Iraq. According to U.S. officials, the 
large number of project sites in remote locations and increased attacks 
on infrastructure have contributed to increased security costs. 

The security costs we identified are lower than those reported to 
Congress by the Department of State in January 2006. State reported in 
its January 2006 quarterly update to Congress that security remains a 
critical concern to the reconstruction effort in Iraq. State's analysis 
indicated that direct and indirect security costs represent 16 percent 
to 22 percent of the overall cost of major infrastructure construction 
projects in Iraq. According to the report, these costs included the 
reprogramming of Iraq Relief and Reconstruction Fund money to the 
security sector and to cover those costs stemming from schedule delays 
and increased maintenance costs. The estimated security costs we 
identified are unique to the design-build contractors and do not 
include other broader security costs included in State's analysis. 

In response to higher than anticipated support costs, DOD officials 
have contracted directly with Iraqi firms in the electricity and 
transportation, among other sectors, rather than relying exclusively on 
the design-build contractors to complete the work. For example, in the 
electricity sector, DOD directly contracted with Iraqi firms to reduce 
the costs of reconstruction efforts not requiring advanced technical 
and management expertise, such as erecting electrical distribution 
projects. DOD officials estimate that the department may achieve a cost 
savings of 20 percent to 50 percent in the electricity sector using 
direct contracting rather than design-build contractors. In the 
transportation sector, the design-build contractor demobilized and left 
Iraq shortly after award of the contract in March 2004 because DOD and 
the contractor mutually agreed that the overall program costs were too 
high. DOD then made greater use of Iraqi contractors who were 
experienced in building roads and bridges. However, due to the lack of 
available data on direct contracts awarded by DOD, we were unable to 
determine the level of actual cost avoidance achieved through these 
contracting efforts. 

Agency Comments: 

We provided a draft of this report to the Department of Defense, which 
provided technical comments that we incorporated, where appropriate. 
Defense stated that it appreciated the balanced report that GAO has 
developed. In its technical comments, the department also clarified 
that the work-in-place measure used in our report is a rudimentary 
measure of earned value and measures total value against individual 
contract amounts, including design and procurements made. The measure 
does not only apply to work that is "in place" or constructed as we 
stated in our draft report. 

Scope and Methodology: 

To determine the construction work completed to date and targeted 
completion dates for construction activities in Iraq, we reviewed 
documents and obtained data from the Department of Defense (DOD), 
including the Project and Contracting Office of the Gulf Region 
Division (GRD/PCO). Data for U.S. appropriated funds and work-in-place 
are as of September 30, 2006, and October 8, 2006, respectively. We 
also reviewed Special Inspector General for Iraq Reconstruction and 
other audit agency reports. Although we have not audited the funding 
and work-in-place data and are not expressing our opinion on them, we 
discussed the sources and limitations of the data with the appropriate 
officials and checked them, when possible, against other information 
sources. In March 2006, DOD standardized the use of its work-in-place 
measures to serve as an indicator of construction progress across all 
of Iraq's reconstruction sectors. We determined that the data were 
sufficiently reliable for broad comparisons in the aggregate using the 
category descriptions we have made. 

To determine the support costs incurred by the design-build contractors 
in DOD's construction program, we focused on design-build contractors' 
efforts in the Iraqi security and justice; electricity; oil; water; 
transportation and communications; and buildings, health and education 
sectors. These costs include transportation and mobilization, life 
support, management, administration, and security costs. We compared 
the design-build contractor's projected support costs to their 
estimated completion costs of $3.7 billion to estimate the level of 
support costs that will be incurred by DOD's design-build contractors 
in Iraq. We also used the Joint Contracting Command-Iraq/Afghanistan 
(JCC-I/A) data to compare the security costs (one component of support 
costs) to estimated completion costs to estimate the level of security 
costs that will be incurred by the design-build contractors. 
Specifically, we focused on the costs incurred by design-build 
contractors participating in the construction program and how sectors 
have adapted to meet these support costs. We obtained support costs 
information directly from the design-build contractors to ensure 
greater reliability of the support costs. We collected design-build 
cost data from the JCC-I/A, including summaries of support costs by 
sector. These data were based on design-build contractor cost reporting 
to JCC-I/A and GRD/PCO officials. Although we did not audit the cost 
data and are not expressing our opinion on them, we reviewed the data 
for discrepancies and checked them against other sources, when 
available. We determined that the data were sufficiently reliable to 
report in aggregate for each sector. 

We also reviewed contractor and agency reports and interviewed 
contractors and agency officials in Iraq and the United States. 
Specifically, we reviewed CPA, GRD/PCO, State, Army Corps of Engineers, 
and other reports. We also interviewed agency officials from GRD/PCO, 
Army Corps of Engineers, State, and State's Iraq Reconstruction 
Management Office in Washington, D.C., and Iraq. In addition, our 
analysis is based on our completed and ongoing reviews of efforts to 
rebuild Iraq, which we have undertaken since 2004, and reports of other 
inspector generals related to contract management, internal controls, 
and oversight of U.S. reconstruction activities. 

We conducted our review from November 2005 to December 2006 in 
accordance with generally accepted government auditing standards. In 
addition to interviews with U.S. officials via teleconference and 
videoconference, we traveled to Iraq in November 2005 and early April 
2006 to interview U.S. officials in Baghdad. In addition, when 
possible, we interviewed officials when these officials traveled to the 
United States. 

We are sending this report to interested congressional committees and 
to the Secretaries of State and Defense. We will also make copies 
available to others on request. In addition, the report will be 
available at no charge on the GAO Web site at [Hyperlink, 
http://www.gao.gov]. 

If you or your staff have any questions concerning this report, please 
contact me at (202) 512-8979 or christoffj@gao.gov. Contact points for 
our Offices of Congressional Relations and Public Affairs may be found 
on the last page of this report. Key contributors to this report 
include Stephen M. Lord, Assistant Director; Lynn Cothern; Tim 
DiNapoli; Micah McMillan; Mary Moutsos; and Adam Vodraska. 

Signed by: 

Joseph A. Christoff: 
Director, International Affairs and Trade: 

List of Congressional Committees: 

The Honorable John Warner: 
Chairman: 
The Honorable Carl Levin: 
Ranking Minority Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Richard G. Lugar: 
Chairman: 
The Honorable Joseph R. Biden, Jr. 
Ranking Minority Member: 
Committee on Foreign Relations: 
United States Senate: 

The Honorable Susan M. Collins: 
Chairman: 
The Honorable Joseph I. Lieberman: 
Ranking Minority Member: 
Committee on Homeland Security and Governmental Affairs: 
United States Senate: 

The Honorable Ted Stevens: 
Chairman: 
The Honorable Daniel K. Inouye: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
United States Senate: 

The Honorable Jerry Lewis: 
Chairman: 
The Honorable David R. Obey: 
Ranking Minority Member: 
Committee on Appropriations: 
House of Representatives: 

The Honorable C. W. Bill Young: 
Chairman: 
The Honorable John P. Murtha, Jr. 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

The Honorable Duncan L. Hunter: 
Chairman: 
The Honorable Ike Skelton: 
Ranking Minority Member: 
Committee on Armed Services: 
House of Representatives: 

The Honorable Henry J. Hyde: 
Chairman: 
The Honorable Tom Lantos: 
Ranking Minority Member: 
Committee on International Relations: 
House of Representatives: 

The Honorable Tom Davis: 
Chairman: 
The Honorable Henry A. Waxman: 
Ranking Minority Member: 
Committee on Government Reform: 
House of Representatives: 

The Honorable Christopher H. Shays: 
Chairman: 
The Honorable Dennis J. Kucinich: 
Ranking Minority Member: 
Subcommittee on National Security, Emerging Threats and International 
Relations: 
Committee on Government Reform: 
House of Representatives: 

(320402): 

FOOTNOTES 

[1] These funds were appropriated to the Iraq Relief and Reconstruction 
Fund in the Emergency Supplemental Appropriations Act for Defense and 
for the Reconstruction of Iraq and Afghanistan, 2004, P. L. 108-106. 

[2] An obligation is a definite commitment that creates a legal 
liability of the government for the payment of goods and services 
ordered or received. 

[3] DOD merged GRD and PCO in late 2005. 

[4] For the purposes of this report, DOD's planned work is defined as 
the total construction value of its projects and generally includes 
design, construction, award fee, security, life support, and 
administrative costs. 

[5] Support costs include transportation and mobilization, life 
support, management, administration, and security. 

[6] GAO, Stabilizing Iraq: An Assessment of the Security Situation, GAO-
06-1094T (Washington, D.C.: Sept. 11, 2006); and Rebuilding Iraq: 
Governance, Security, Reconstruction, and Financing Challenges, GAO- 06-
697T (Washington, D.C.: Apr. 25, 2006). 

[7] In providing technical comments on the report, DOD stated that over 
1,000 megawatts will be sustained by various projects in its generation 
program. 

[8] GAO, Rebuilding Iraq: U.S. Water and Sanitation Efforts Need 
Improved Measures for Assessing Impact and Sustained Resources for 
Maintaining Facilities, GAO-05-872 (Washington, D.C.: Sept. 7, 2005). 

[9] GAO, Stabilizing Iraq: An Assessment of the Security Situation, GAO-
06-1094T (Washington, D.C.: Sept. 11, 2006). The attack data we used 
provide the best overall assessment of Iraq's precarious security 
environment and the ensuing challenges in completing reconstruction 
projects. GAO has requested, but has yet to receive, unclassified 
attack data for September through November 2006. 

[10] In addition to these design-build contractor support costs, the 
PCO, lead contractor, and sector contractors incurred additional costs 
of $443 million for fiscal years 2004 through 2006 in managing the 
activities of the design-build contractors in Iraq. 

[11] To increase transparency over support costs, the oil sector 
developed four administrative task orders that allowed the design-build 
contractors to more easily report on transportation and mobilization, 
management and administration, security, and life support costs. 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts 
newly released reports, testimony, and correspondence on its Web site. 
To have GAO e-mail you a list of newly posted products every afternoon, 
go to www.gao.gov and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 441 G Street NW, Room LM 
Washington, D.C. 20548: 

To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202) 
512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S. 
Government Accountability Office, 441 G Street NW, Room 7125 
Washington, D.C. 20548: 

Public Affairs: 

Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800 
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, D.C. 20548: