This is the accessible text file for GAO report number GAO-06-1132 
entitled 'Iraq Contract Costs: DOD Consideration of Defense Contract 
Audit Agency's Findings' which was released on September 25, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 

GAO: 

September 2006: 

Iraq Contract Costs: 

DOD Consideration of Defense Contract Audit Agency's Findings: 

Iraq Contract Costs: 

GAO-06-1132: 

GAO Highlights: 

Highlights of GAO-06-1132, a report to Congressional Committees 

Why GAO Did This Study: 

The government has hired private contractors to provide billions of 
dollars worth of goods and services to support U.S. efforts in Iraq. 
Faced with the uncertainty as to the full extent of rebuilding Iraq, 
the government authorized contractors to begin work before key terms 
and conditions were defined. This approach allows the government to 
initiate needed work quickly, but can result in additional costs and 
risks being imposed on the government. Helping to oversee their work is 
the Defense Contract Audit Agency (DCAA), which examined many Iraq 
contracts and identified costs they consider to be questioned or 
unsupported. 

The Conference Report on the National Defense Authorization Act for 
Fiscal Year 2006 directed GAO to report on audit findings regarding 
contracts in Iraq and Afghanistan. As agreed with the congressional 
defense committees, GAO focused on Iraq contract audit findings and 
determined (1) the costs identified by DCAA as questioned or 
unsupported; and (2) what actions DOD has taken to address DCAA audit 
findings, including the extent funds were withheld from contractors. To 
identify DOD actions in response to the audit findings, GAO selected 18 
audit reports representing about 50 percent of DCAA’s questioned and 
unsupported costs on Iraq contracts. 

GAO requested comments from DOD on a draft of this report, but none 
were provided. 

What GAO Found: 

Defense Contract Audit Agency audit reports issued between February 
2003 and February 2006 identified $2.1 billion in questioned costs and 
$1.4 billion in unsupported costs on Iraq contracts. DCAA defines 
questioned costs as costs that are unacceptable for negotiating 
reasonable contract prices, and unsupported costs as costs for which 
the contractor has not provided sufficient documentation. This 
information is provided to DOD for its negotiations with contractors. 
Based on information provided by DCAA, DOD contracting officials have 
taken actions to address $1.4 billion in questioned costs. As a result, 
DOD contracting officials negotiated contract cost reductions of $386 
million according to DCAA. Based on the information provided by DCAA, 
as of July 2006, the remaining $700 million in questioned costs is 
still in process. Because unsupported costs indicate a lack of 
contractor information that is needed to assess costs, DCAA cannot and 
does not render an opinion on those costs. Therefore, DCAA does not 
track the resolution of unsupported costs. 

For the 18 audit reports selected for this review, GAO found that DOD 
contracting officials took a variety of actions to address DCAA’s audit 
findings, including not allowing some contractor costs. In the contract 
documentation GAO reviewed, DOD contracting officials generally 
considered DCAA’s questioned and unsupported cost findings when 
negotiating with the contractor. GAO found DOD contracting officials 
were more likely to use DCAA’s advice when negotiations were timely and 
occurred before contractors had incurred substantial costs. For 
example, in three audit reports related to a logistics support task 
order negotiated prior to the onset of work, DCAA questioned $204 
million. According to DCAA’s calculations, $120 million of these 
questioned costs was removed from the contractor’s proposal as a result 
of its audit findings. In contrast, DOD officials were less likely to 
remove questioned costs from a contract proposal when the contractor 
had already incurred these costs. For example, in five audit reports 
comprising about $600 million of questioned costs reviewed, GAO found 
that the DOD contracting officials determined that the contractor 
should be paid for all but $38 million of the questioned costs, but 
reduced the base used to calculate the contractor’s fee by $205 
million. By reducing the base, the DOD contracting official reduced the 
contractor’s fee by approximately $6 million. In addition to 
identifying questioned and unsupported costs, DCAA has the option of 
withholding funds from the contractor and chose to withhold a total of 
$236 million for eight cases included in this review. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-1132]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact John Hutton at (202) 512-
4841 or huttonj@gao.gov. 

[End of Section] 

Contents: 

Letter: 

Results In Brief: 

Background: 

DCAA Audit Reports Identified Billions of Dollars of Questioned and 
Unsupported Costs on Iraq Contracts: 

DOD Contracting Officials Have Taken a Range of Actions to Address 
Audit Findings: 

Appendix I: Scope and Methodology: 

Figures: 

Figure 1: Timeline of Key Contracting Events for Restore Iraqi Oil 
Contract, Task Order 5: 

Figure 2: Timeline of Key Contracting Events for Logistics Civil 
Augmentation Program III Contract, Task Order 89: 

Abbreviations: 

DCAA: Defense Contract Audit Agency: 
DESC: Defense Energy Support Center: 
DOD: Department of Defense: 
FAR: Federal Acquisition Regulation: 

United States Government Accountability Office: 
Washington, DC 20548: 

September 25, 2006: 

Congressional Committees: 

The United States is spending billions of dollars to achieve U.S. 
political, security, and economic goals in Iraq. Between fiscal years 
2003 and 2006, the U.S. government has allocated about $311 billion to 
support U.S. stabilization and reconstruction efforts in Iraq. The 
United States has relied heavily on private-sector contractors to 
provide the goods and services needed to support both the military and 
reconstruction efforts in Iraq. Faced with the uncertainty as to the 
full extent of rebuilding Iraq, the government authorized contractors 
to begin work before key terms and conditions were defined. This 
approach allows the government to initiate needed work quickly, but can 
result in additional costs and risks being imposed on the government. 
Given the dollar amounts involved, it is essential that these 
acquisitions be handled in an efficient, effective, and accountable 
manner to mitigate the government's risk. 

The Defense Contract Audit Agency (DCAA) provides services that can 
help DOD ensure accountability for its acquisitions. DCAA performs 
audits and provides financial advisory services in connection with 
negotiation, administration, and settlement of contracts and 
subcontracts. For example, DCAA has audited many Iraq contract 
proposals and contracts and has identified costs it considers to be 
questioned or unsupported. DCAA defines questioned costs as those costs 
considered to be not acceptable for negotiating a reasonable contract 
price, and unsupported costs as costs for which the contractor has not 
furnished sufficient documentation to support the cost proposed or 
claimed. 

The Conference Report on the National Defense Authorization Act for 
Fiscal Year 2006[Footnote 1] directed GAO to report on audit findings 
regarding contracts in Iraq and Afghanistan. As agreed with the 
congressional defense committees, we focused on Iraq contract audit 
findings and determined (1) the costs identified by DCAA as questioned 
or unsupported; and (2) what actions DOD has taken to address DCAA 
audit findings, including the extent to which funds were withheld from 
contractors. 

To determine the costs DCAA questioned or identified as unsupported, we 
analyzed information provided to us by DCAA on Iraq-related audit 
reports issued between February 2003 and February 2006. To identify 
actions taken by DOD to address audit findings and funds withheld, we 
selected 18 audit reports comprised of (1) the 10 reports with the 
highest dollar amounts of questioned and unsupported costs, and (2) 8 
other audit reports with questioned and unsupported costs above $5 
million. The questioned and unsupported costs for the 18 selected 
reports totaled $1.8 billion, or approximately 50 percent of all 
questioned and unsupported costs identified through DCAA's data on Iraq 
contracts. The selected audit reports represent work performed by four 
contractors. For each audit report, we obtained key documentation from 
DCAA and DOD, and interviewed DCAA auditors and DOD contracting 
officials. Appendix I provides details on our scope and methodology. We 
conducted our work from March 2006 through September 2006 in accordance 
with generally accepted government auditing standards. 

Results In Brief: 

Between February 2003 and February 2006, DCAA issued hundreds of audit 
reports that collectively identified $2.1 billion in questioned costs 
and $1.4 billion in unsupported costs on Iraq contracts, primarily 
through audits of contractor proposals. Based on information provided 
to us by DCAA, contracting officials had addressed $1.4 billion of 
DCAA's questioned costs. Of that amount, contracting officials reduced 
contract costs by about $386 million, according to information provided 
by DCAA.[Footnote 2] Based on the information provided by DCAA, as of 
July 2006, the remaining $700 million in questioned costs is still in 
process. Because unsupported costs indicate a lack of contractor 
information that is needed to assess costs, DCAA cannot and does not 
render an opinion on those costs. Therefore, DCAA does not track the 
resolution of unsupported costs. 

For the 18 audit reports selected for this review, we found that DOD 
contracting officials took a variety of actions in response to DCAA's 
audit findings, including not allowing some contractor costs. Based on 
contract documentation we reviewed, the DOD contracting officials 
generally considered DCAA's questioned and unsupported cost findings 
when negotiating with the contractor. We found that DOD contracting 
officials were more likely to use DCAA's advice when negotiations were 
timely and occurred before contractors had incurred substantial costs. 
For example, in 3 audit reports related to a logistics support task 
order negotiated prior to the onset of work, DCAA questioned $204 
million. According to DCAA's calculations, $120 million of these 
questioned costs was removed from the contractor's proposal as a result 
of its audit findings. In contrast, DOD officials were less likely to 
remove questioned costs from a contract proposal when the contractor 
had already incurred these costs. Of the 18 audits covered in our 
review, 11 audit reports corresponded to contract actions where more 
than 180 days had elapsed from the beginning of the period of 
performance to final negotiations. For example, in 5 audit reports 
comprising about $600 million of questioned costs reviewed, we found 
that the DOD contracting officials determined that the contractor 
should be paid for all but $38 million of the questioned costs, but 
reduced the base used to calculate the contractor's fee by $205 
million. By reducing the base, the DOD contracting official reduced the 
contractor's fee by approximately $6 million. In addition to 
identifying questioned and unsupported costs, DCAA can withhold funds 
from contractor payments,[Footnote 3] and chose to withhold a total of 
$236 million for 8 cases included in our review. Of the $236 million, 
the government decided to pay the contractors $148 million, not to pay 
$36 million, and $51 million has not been settled yet.[Footnote 4] 

We requested comments from DOD on a draft of this report, but none were 
provided. 

Background: 

The United States, along with its coalition partners and various 
international organizations and donors, has embarked on a significant 
effort to rebuild Iraq. The United States is spending billions of 
dollars to reconstruct Iraq while combating an insurgency that has 
targeted military and contractor personnel and the Iraqi people. The 
United States has relied heavily on private-sector contractors to 
provide the goods and services needed to support both the military and 
reconstruction efforts in Iraq. 

DCAA is responsible for providing contract audits for DOD, along with 
general accounting and financial advice to DOD acquisition officials 
negotiating government contracts. DCAA performs many types of audits 
for DOD, including audits of contractor proposals, audits of estimating 
and accounting systems, and incurred cost audits. Generally, the 
results of a DCAA audit are intended to assist contracting officials in 
negotiating reasonable contract prices. Normally, DCAA audits 
contractors' proposals and provides contracting officials advice on the 
reasonableness of contractor costs prior to negotiations. DCAA also 
conducts audits of cost-type contracts after they are negotiated to 
ensure costs incurred on these contracts are acceptable. Relying on 
cost information provided by the contractor and assessing whether the 
costs comply with government regulations, DCAA may identify certain 
costs as questioned or unsupported. DCAA defines questioned costs as 
costs considered to be not acceptable for negotiating a reasonable 
contract price, and unsupported costs as costs that lack sufficient 
supporting documentation. DCAA reports its findings to contracting 
officers for consideration in negotiating reasonable contract prices. 

DCAA audit reports represent one way DCAA can assist contracting 
officials as they negotiate government contracts. Also, contracting 
officials may invite DCAA to participate in contract negotiations to 
explain audit findings and recommendations, and may factor DCAA audit 
findings into evaluations of contract proposals. The Federal 
Acquisition Regulation (FAR) acknowledges that DCAA's role is advisory, 
and assigns the contracting officer responsibility for ensuring that 
the contractor's proposed price is fair and reasonable.[Footnote 5] 
While DCAA audit recommendations are nonbinding, DCAA's Contract Audit 
Manual states that contracting officials deviating from DCAA advice 
during negotiations should explain the reasons why they disagreed with 
DCAA. 

DOD Directive 5105.36 also enables DCAA to withhold payments by (1) 
suspending payment for specific incurred costs lacking documentation or 
(2) disapproving costs that do not conform with applicable regulations. 
DCAA can issue a Form 1 to a contractor notifying it that funds will be 
withheld, which initiates review of the challenged costs by the 
contracting officer. 

DCAA Audit Reports Identified Billions of Dollars of Questioned and 
Unsupported Costs on Iraq Contracts: 

Between February 2003 and February 2006, DCAA issued hundreds of audit 
reports that collectively identified $3.5 billion in questioned and 
unsupported costs on Iraq-related contracts, primarily through audits 
of contractor proposals. In some cases, DCAA was asked to audit 
multiple iterations of contractor proposals as these proposals were 
revised over a period of time. Based on information provided by DCAA, 
contracting officials have responded to audit findings that questioned 
$1.4 billion. As a result, contracting officials negotiated contract 
cost reductions of $386 million according to DCAA. DCAA does not render 
an opinion about costs it determines to be unsupported; therefore they 
do not track the resolution of unsupported costs. 

DCAA Identified Billions of Dollars in Questioned and Unsupported 
Costs: 

Between February 2003 and February 2006, DCAA tracked 349 audit reports 
that identified about $3.5 billion in questioned and unsupported costs 
on Iraq contracts. Of this total, DCAA classified $2.1 billion as 
questioned, and $1.4 billion as unsupported. DCAA identified these 
questioned and unsupported costs in audits related to 99 different 
contractors. Most of the questioned and unsupported costs were 
identified through audits of contractor proposals. Specifically, in 
DCAA's database, more than three-quarters of the audits with questioned 
and unsupported costs were classified as "forward pricing activity," 
which primarily involves auditing contractor proposals or parts of 
proposals. 

In some cases, DCAA reviewed multiple contractor proposals for the same 
work. DOD officials told us that contractors submitted multiple 
proposals because requirements changed or the proposal was considered 
inadequate for negotiations. For example, over a 6-month period, DCAA 
issued four audit reports on three different proposals for a task order 
related to an oil mission. Each audit superseded the prior one, and 
DCAA updates its information to reflect the most recent report. 

DCAA Tracks How Questioned Costs Are Addressed but Does Not Track 
Similar Information for Unsupported Costs: 

While DCAA tracks and records how questioned costs are addressed by the 
contracting official in negotiation, it does not track similar 
information about unsupported costs. Based on the data provided to us 
by DCAA, as of July 3, 2006, contracting officials had responded to 169 
of DCAA's 349 Iraq audit reports. DCAA considered the findings to be 
addressed because the contracting official had documented the result of 
negotiations with the contractor. 

Based on information provided by DCAA, for the $1.4 billion in 
questioned costs addressed by contracting officials, contracting 
officials sustained $386 million of the total questioned costs. DCAA 
defines sustained costs as the costs reduced through negotiations 
directly attributable to findings reported by the DCAA auditor for 
proposal audits. Based on the information provided by DCAA, as of July 
2006, the remaining $700 million in questioned costs is still in 
process. DCAA's information does not reflect what actions, if any, the 
contracting officials have taken to respond to these audit report 
findings. 

According to a DCAA official, DCAA does not track how unsupported costs 
are addressed. DCAA guidance implementing the FAR requires the 
contracting official to report on the disposition of questioned 
amounts, but not specifically on whether contractors provided 
sufficient documentation to eliminate unsupported costs.[Footnote 6] 
Because unsupported costs indicate a lack of contractor information 
that is needed to assess costs, DCAA cannot and does not render an 
opinion on those costs. Therefore, DCAA does not track the resolution 
of unsupported costs. 

DOD Contracting Officials Have Taken a Range of Actions to Address 
Audit Findings: 

For the 18 audit reports selected for this review, we found that DOD 
took a variety of actions in response to audit findings, including not 
allowing some contractor costs. Based on contract documentation we 
reviewed, the DOD contracting officials generally considered DCAA's 
questioned and unsupported cost findings when negotiating with the 
contractor. We found that DOD contracting officials were more likely to 
use DCAA's advice when negotiations were timely and occurred before 
contractors had incurred substantial costs. In contrast, DOD officials 
were less likely to remove questioned costs from a contract proposal 
when the contractor had already incurred these costs. In addition to 
identifying questioned and unsupported costs, DCAA can also withhold 
funds from the contractor, which it chose to do in eight of the cases 
included in our review. Other actions taken by the DOD contracting 
officials included inviting DCAA to attend meetings or negotiations 
with the contractor and conducting additional analyses to respond to 
audit findings. 

DOD Generally Considered DCAA Audit Findings When Negotiating with the 
Contractor: 

Our review of the government's documentation of contract negotiations 
for the selected audit reports showed that DOD generally considered 
DCAA audit findings.[Footnote 7] The majority, or 13 of the 15 
memorandums, identified how the contracting officials addressed DCAA 
audit findings.[Footnote 8] Most memorandums discussed questioned and 
unsupported costs identified by DCAA in areas such as labor, equipment, 
material, and subcontracts, but some lacked specific detail on how DCAA 
audit findings were addressed. However, in two cases we were unable to 
determine from the negotiation documentation how DCAA audit findings 
were used. 

DOD Contracting Officials Less Likely to Remove Questioned Costs 
Already Incurred by the Contractor: 

To address the more than $1 billion in questioned costs related to the 
audits selected, we found that the DOD contracting officials were less 
likely to remove questioned costs from a contractor proposal when the 
contractor had already incurred these costs. For example, in 5 audit 
reports comprising about $600 million of questioned costs reviewed, we 
found that the DOD contracting officials determined that the contractor 
should be paid for nearly all of the questioned costs (all but $38 
million), but reduced the base used to calculate the contractor's fee 
(by $205 million). By reducing the base, the DOD contracting official 
reduced the contractor's fee by approximately $6 million. 

Generally, when entering into a contract, the government and contractor 
reach agreement on the key aspects of the contract, including the scope 
and price of the work, before the work is authorized to start. However, 
the FAR enables the government to authorize the contractor to begin 
work before doing so in certain cases, such as when the government 
demands the work start immediately and it is not possible to negotiate 
a fully defined contract in sufficient time to meet the 
requirement.[Footnote 9] Our past work has shown that the use of 
undefinitized contract actions can pose risks to the government, such 
as potentially significant additional costs.[Footnote 10] Acquisition 
regulations generally require that the contracting official define the 
scope and costs of such contracts within 180 days of the contract's 
start date. According to contract officials, urgent conditions in Iraq 
led the government to initiate such contract actions without first 
specifying their scope of work and agreeing to the contract price. 

In many cases we reviewed, contractors completed some work and incurred 
substantial costs well before the government negotiated the contract 
price. Of the 18 audits covered in our review, 11 audit reports 
corresponded to contract actions where more than 180 days had elapsed 
from the beginning of the period of performance to final negotiations. 
For nine of these audits, the period of performance DOD initially 
authorized for each contract action concluded before final negotiations 
took place. 

For example, DCAA questioned $84 million in its audit of a task order 
proposal for an oil mission. In this case, the contractor did not 
submit a proposal until a year after the work was authorized, and DOD 
and the contractor did not negotiate the final terms of the task order 
until more than a year after the contractor had completed work (see 
fig. 1). The DOD contracting officer paid the contractor for all 
questioned costs but reduced the base used to calculate contractor 
profit by $45 million. As a result, the contractor was paid about $3 
million less in fees. In the final negotiation documentation, the DOD 
contracting official stated that payment of incurred costs is required 
for cost-type contracts, absent unusual circumstances.[Footnote 11] 
This same rationale was used in negotiations on several other task 
orders. 

Figure 1: Timeline of Key Contracting Events for Restore Iraqi Oil 
Contract, Task Order 5: 

[See PDF for image] 

Source: GAO analysis of DOD data. 

[End of figure] 

In contrast, in the few audit reports we reviewed where the government 
negotiated prior to starting work, we found that the portion of 
questioned costs removed from the proposal was substantial. For 
example, in 3 audit reports related to a logistics support task order, 
DCAA questioned $204 million. Since the government and the contractor 
negotiated the terms of this task order prior to the onset of work, the 
contractor had not incurred any costs at the time of negotiation (see 
fig. 2 for timeline). According to DCAA's calculations, $120 million of 
these questioned costs was removed from the contractor's proposal as a 
result of its audit findings. 

Figure 2: Timeline of Key Contracting Events for Logistics Civil 
Augmentation Program III Contract, Task Order 89: 

[See PDF for image] 

Source: GAO analysis of DOD data. 

[End of figure] 

DCAA Withheld Funds Related to Some Audit Reports We Reviewed: 

In addition to identifying questioned and unsupported costs, DCAA can 
withhold funds from contractors in certain situations.[Footnote 12] The 
cognizant administrative contracting officer may subsequently determine 
that the withheld costs should be approved for payment to the 
contractor. We found DCAA withheld $236 million from contractors 
related to 8 of the audits included in our review. Subsequently, as a 
result of either additional documentation provided by the contractor or 
the DOD administrative contracting officer determination, $148 million 
of the withheld funds was released to the contractor and the government 
did not pay $36 million to the contractor. The remaining $51 million 
has not been settled yet--a DOD contracting official is reviewing the 
available information to make a decision about whether or not these 
costs will be reimbursed.[Footnote 13] 

In the audit reports reviewed, the vast majority of funds withheld by 
DCAA ($171 million of the $236 million) related to dining facilities 
services provided at U.S. troop camps in Iraq.[Footnote 14] The 
contractor was directed by the Army to build, equip, and operate the 
dining facilities located at U.S. troop base camps in Iraq and to 
provide four meals a day to the camp populations. The population at 
each camp was specified in the Army's description of the work to be 
performed by the contractor. In addition, contractor and government 
representatives counted the number of troops served at each mealtime. 
However, the Army's description of the work did not specify whether the 
contractor should bill the government for the camp population 
identified in the work description or the actual head count for each 
meal. Generally, the government was billed based on the estimated base 
camp population, but DCAA stated that the billings should be based on 
the actual head count, which was lower than the estimated base camp 
population included in the work description. As a result, DCAA withheld 
funds by reducing payment for dining facilities costs on contractor 
billings by 19.35 percent. Ultimately, the DOD and the contractor 
negotiated a settlement where it was agreed that $36 million would not 
be paid to the contractor.[Footnote 15] 

In another example, DCAA withheld a payment to the contractor for its 
subcontractor's costs of $12 million related to electrical repair 
services. DCAA determined the cost to be unreasonable based on a 
comparison of price quotes from other subcontractors for similar 
electrical repair services. As a result of the action taken by DCAA to 
withhold payment, an Army Corps of Engineers contracting official 
reviewed contractor data. The contracting official determined the 
subcontractor's price was reasonable given the short contract time 
frames. A memo outlining the Army Corps of Engineers' rationale for 
paying the contractor for the subcontractor costs states, "Corps of 
Engineers representatives in Baghdad directed all of the contractors 
there to do whatever was necessary, regardless of cost, to meet 
schedule commitments." The $12 million withheld was released to the 
contractor. DCAA officials expressed concerns that the DOD contracting 
official had not sought their assistance when settling this issue with 
the contractor. 

DOD Took a Variety of Other Actions to Address DCAA Audit Findings: 

We found that DOD contracting officials took a variety of other actions 
to address DCAA audit findings. In many of the cases we reviewed, DCAA 
was invited to participate in meetings or negotiations with the 
contractor. For example, 

* To address the questioned costs identified in the task orders for the 
oil mission, the DOD contracting official convened a meeting to include 
the contractor representatives, DCAA officials, and Army Corps of 
Engineers officials. As a result of discussions in this meeting, a DCAA 
official told us that DCAA stopped questioning some costs such as the 
percentage paid to contractor employees for working in a dangerous area 
and price adjustments the contractor paid to its subcontractors for 
fuel from Turkey. In addition, the DOD contracting official asked DCAA 
to provide alternative negotiation positions, and in response DCAA 
developed memorandums outlining several options for each task order. 
Ultimately the DOD contracting official used a negotiation position 
presented in each memorandum to establish the government's negotiation 
position with the contractor. When asked if he was satisfied with the 
resolution of the questioned costs, a DCAA official involved in the 
process told us he thought the DOD contracting official did the best 
job he could. 

* In another example, DCAA attended negotiations between the contractor 
and the government for an electricity contract. DCAA's role at this 
meeting was to answer questions and to reiterate its opinion. 
Subsequent to negotiations, DCAA participated in additional meetings 
with the contractor and the Army Corps of Engineers to ensure that its 
concerns with the contractor purchasing system were addressed. DCAA 
officials told us that problems with the contractor purchasing system 
were related to the unsupported costs identified in the audit. DCAA 
officials involved in this process told us that they were generally 
satisfied with the actions taken by DOD and the contractor to resolve 
their audit findings. 

In some cases, DOD officials conducted additional analyses in response 
to DCAA's audit findings. For example, for the audit reports we 
reviewed related to the oil mission, DCAA questioned the cost of fuel 
and transportation based on a comparison between the price paid by the 
contractor and the price paid by the Defense Energy Support Center 
(DESC) when it took over the mission from the contractor in April 2004. 
In response, DOD collected additional information to update the fuel 
and transportation cost comparison. For example, although DESC 
negotiated prices based on trucks shipping fuel to Iraq three times per 
month, in practice the trucks were only able to make two trips per 
month, a fact that increased the cost of the mission to DESC. Overall, 
the additional analyses provided a rationale for the DOD contracting 
official to pay the contractor for some of DCAA's questioned costs. 

We requested comments from DOD on a draft of this report, but none were 
provided. 

We are sending copies of this report to the Secretary of Defense, 
appropriate congressional committees, and other interested parties. We 
will make copies of this report available on request. In addition, this 
report will be available at no charge on GAO's Web site at [Hyperlink, 
http://www.gao.gov]. 

If you have any questions concerning this report, please contact me at 
(202) 512-4841 or by e-mail at huttonj@gao.gov. Contact points for our 
Office of Congressional Relations and Public Affairs may be found on 
the last page of this report. Other major contributors to this report 
were Penny Berrier Augustine, Tim Bazzle, Greg Campbell, David E. 
Cooper, Tim DiNapoli, Julia Kennon, John Krump, Eric Lesonsky, Janet 
McKelvey, Guisseli Reyes-Turnell, Raffaele Roffo, and Jeffrey Rose. 

Signed by: 

John P. Hutton: 
Acting Director: 
Acquisition and Sourcing Management: 

List of Congressional Committees: 

The Honorable John Warner: 
Chairman: 
The Honorable Carl Levin: 
Ranking Minority Member: 
Committee on Armed Services: 
United States Senate: 

The Honorable Ted Stevens: 
Chairman: 
The Honorable Daniel K. Inouye: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
United States Senate: 

The Honorable Duncan L. Hunter: 
Chairman: 
The Honorable Ike Skelton: 
Ranking Minority Member: 
Committee on Armed Services: 
House of Representatives: 

The Honorable C. W. Bill Young: 
Chairman: 
The Honorable John P. Murtha: 
Ranking Minority Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

[End of section] 

Appendix I: Scope and Methodology: 

To determine the costs identified by the Defense Contract Audit Agency 
(DCAA) as questioned or unsupported, we analyzed data from DCAA's 
management information system on all DCAA Iraq-related audit reports 
with questioned or unsupported costs issued between February 2003 and 
February 2006. To develop an understanding and assess the reliability 
of the information included in the database, we held discussions with 
and obtained documentation from DCAA officials located in Fort Belvoir 
and we conducted electronic testing for obvious inconsistencies and 
completeness. During our review of the database we identified records 
for 20 audits, 1 percent of the database, which listed 2 different 
totals for questioned and/or unsupported costs. For these 20 audits, 
based on our conversation with a DCAA official, we selected the amount 
that reflected the most current total for questioned and/or unsupported 
costs. We determined the data used in our review to be sufficiently 
reliable for our purposes. 

To determine the actions taken by the Department of Defense (DOD) in 
response to DCAA audit findings, including the extent to which funds 
were withheld from contractors, we selected 18 audit reports comprised 
of (1) the 10 reports with the highest dollar amounts of questioned and 
unsupported costs and (2) a selection of 8 of the remaining audit 
reports with questioned and unsupported cost dollars above $5 
million.[Footnote 16] We excluded audit reports issued after November 
1, 2005 from the selection to ensure that DOD contracting officials had 
adequate time to resolve the audit findings. The questioned and 
unsupported costs for the 18 audits total approximately $1.8 billion, 
or about 50 percent of all questioned and unsupported costs identified 
through DCAA's database on Iraq contracts. These reports include (1) 11 
audits of 8 task order proposals to provide logistics support for U.S. 
troops, (2) 3 audits of task order proposals to provide fuel and fuel 
transportation, (3) 3 audits of task order proposals for electricity 
services, and (4) 1 audit of a proposal for contract management and 
administrative support functions. The 18 selected audit reports 
represent work performed by 4 contractors. For the selected audits, we 
held discussions with DCAA officials located in Fort Belvoir; 
Arlington, Texas; Lexington, Massachusetts; Seattle, Washington; Kent, 
Washington; and Iraq. We collected key documentation related to each 
audit report, such as DCAA's calculation of the resolution of 
questioned costs and dollars withheld (Form 1). For each audit, we also 
held discussions with DOD contracting officials located in Rock Island, 
Illinois; Dallas, Texas; Winchester, Virginia; and Iraq. We interviewed 
these officials to determine the actions taken by DOD to address DCAA's 
audit findings and obtained key documentation such as price negotiation 
memorandums. 

We conducted our review from March 2006 through September 2006 in 
accordance with generally accepted government auditing standards. 

FOOTNOTES 

[1] National Defense Authorization Act of 2006, H.R. Conf. Rep. No. 109-
360, p. 767(Dec. 18, 2005). 

[2] DCAA provided information that identified $453 million in reduced 
contract costs. Based on our review of 18 audit reports, we found 
DCAA's information on reduced contract costs included $67 million that 
was paid to the contractor but removed from the base used to calculate 
the contractor's fees. DCAA officials acknowledged these costs should 
not be included and that the $453 million does not represent a total 
reduction in contract costs. 

[3] Pursuant to the authority of DOD Directive 5105.36, DCAA can issue 
a Form 1. A Form 1 constitutes notice of costs suspended and/or 
disapproved incident to the audit of contractor costs incurred under a 
contract. Suspended costs are costs that have been determined to be 
inadequately supported or otherwise questionable, and not appropriate 
for reimbursement under contract terms at this time. Such costs may be 
determined reimbursable after the contractor provides the auditor 
additional documentation or explanation. Disapproved costs have been 
determined to be unallowable, that is, not reimbursable under the 
contract terms. 

[4] Monies withheld do not add to $236 million due to rounding. 

[5] Federal Acquisition Regulation (FAR) 1.602-2(c), Responsibilities, 
15.402(a) Pricing Policy (January 2006). 

[6] The FAR states when the contracting officer elects not to adopt 
significant audit or other specialist recommendations, the contracting 
officer should provide a rationale which supports the negotiation 
result in the price negotiation documentation. Federal Acquisition 
Regulation (FAR) 15.405(a), Price Negotiation (January 2006). 

[7] Documentation of contract negotiations includes price negotiation 
memorandums, business clearance memorandums, and definitization 
memorandums. For purposes of this report, we will refer to these 
documents collectively as "memorandums." 

[8] There were 15 memorandums related to the selected audit reports 
included in our review. Two of the memorandums addressed multiple audit 
reports. 

[9] FAR 16.603 Letter Contracts (January 2006). 

[10] GAO, Rebuilding Iraq: Fiscal Year 2003 Contract Award Procedures 
and Management Challenges, GAO-04-605 (Washington, D.C.: June 1, 2004). 

[11] The DOD contracting official indicates that because DCAA chose not 
to suspend or disallow the funds, DCAA and DOD agree that these unusual 
circumstances did not exist. However, DCAA officials do not agree with 
this characterization. 

[12] DCAA withholds funds from the contractor by issuing a Form 1. In 
general, DCAA has two options for withholding funds. DCAA can suspend 
reimbursement for costs that lack adequate support until the required 
data are received and a determination can be made about whether the 
cost is allowable. Or DCAA can disapprove costs that are not considered 
allowable. 

[13] Monies withheld do not add to $236 million due to rounding. 

[14] DCAA withheld a total of $212 million related to the dining 
facilities issue. However, only $171 million of this total relates to 
the audit reports included in our selection. 

[15] The total settlement amount was for $55 million, but only $36 
million relates to the audit reports we reviewed. 

[16] We initially selected 10 audit reports using our second criterion. 
During the course of our review, we learned that two of these audit 
reports were superseded by subsequent audits, and therefore actions 
taken were not documented. As a result, we removed these two audit 
reports from our review. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: