Departmental Manual

Effective Date: 9/26/84

Series: Environmental Quality

Part 516: National Environmental Policy Act of 1969

Chapter 4: Environmental Impact Statements

Originating Office: Office of Environmental Policy and Compliance

 

This chapter has been given a new release number.* No text changes were made.

516 DM 4

4.1 Purpose. This Chapter provides supplementary instructions for implementing those portions of the CEQ regulations pertaining to environmental impact statements (EIS).

4.2 Statutory Requirements (1502.3). NEPA requires that an EIS be prepared by the responsible Federal official. This official is normally the lowest-level official who has overall responsibility for formulating, reviewing, or proposing an action or, alternatively, has been delegated the authority or responsibility to develop, approve, or adopt a proposal or action. Preparation at this level will insure that the NEPA process will be incorporated into the planning process and that the EIS will accompany the proposal through existing review processes.

4.3 Timing (1502.5).

A. The feasibility analysis (go/no-go) stage, at which time an EIS is to be completed, is to be interpreted as the stage prior to the first point of major commitment to the proposal. For example, this would normally be at the authorization stage for proposals requiring Congressional authorization, the location or corridor stage for transportation, transmission, and communication projects, and the leasing stage for mineral resources proposals.

B. An EIS need not be commenced until an application is essentially complete; e.g., any required environmental information is submitted, any consultation required with other agencies has been conducted, and any required advance funding is paid by the applicant.

4.4 Page Limits (1502.7). Where the text of an EIS for a complex proposal or group of proposals appears to require more than the normally prescribed limit of 300 pages, bureaus will insure that the length of such statements is no greater than necessary to comply with NEPA, the CEQ regulations, and this Chapter.

4.5 Supplemental Statements (1502.9).

A. Supplements are only required if such changes in the proposed action or alternatives, new circumstances, or resultant significant effects are not adequately analyzed in the previously prepared EIS.

B. A bureau and/or the appropriate program Assistant Secretary will consult with the Office of Environmental Project Review and the Office of the Solicitor prior to proposing to CEQ to prepare a final supplement without preparing an intervening draft.

C. If, after a decision has been made based on a final EIS, a described proposal is further defined or modified and if its changed effects are minor or still within the scope of the earlier EIS, an EA and FONSI may be prepared for subsequent decisions rather than a supplement.

4.6 Format (1502.10).

A. Proposed departures from the standard format described in the CEQ regulations and this Chapter must be approved by the Office of Environmental Project Review.

B. The section listing the preparers of the EIS will also include other sources of information, including a bibliography or list of cited references, when appropriate.

C. The section listing the distribution of the EIS will also briefly describe the consultation and public involvement processes utilized in planning the proposal and in preparing the EIS, if this information is not discussed elsewhere in the document.

D. If CEQ's standard format is not used or if the EIS is combined with another planning or decisionmaking document, the section which analyzes the environmental consequences of the proposal and its alternatives will be clearly and separately identified and not interwoven into other portions of or spread throughout the document.

4.7 Cover Sheet (1502.11). The cover sheet will also indicate whether the EIS is intended to serve any other environmental review or consultation requirements pursuant to Section 1502.25.

4.8 Summary (1502.12). The emphasis in the summary should be on those considerations, controversies, and issues which significantly affect the quality of the human environment.

4.9 Purpose and Need (1502.13). This section may introduce a number of factors, including economic and technical considerations and Departmental or bureau statutory missions, which may be beyond the scope of the EIS. Care should be taken to insure an objective presentation and not a justification.

4.10 Alternatives Including the Proposed Action (1502.14).

A. As a general rule, the following guidance will apply:

(1) For internally initiated proposals; i.e., for those cases where the Department conducts or controls the planning process, both the draft and final EIS shall identify the bureaus' proposed action.

(2) For externally initiated proposals; i.e., for those cases where the Department is reacting to an application or similar request, the draft and final EIS shall identify the applicant's proposed action and the bureau's preferred alternative unless another law prohibits such an expression.

(3) Proposed departures from this guidance must be approved by the Office of Environmental Project Review and the Office of the Solicitor.

B. Mitigation measures are not necessarily independent of the proposed action and its alternatives and should be incorporated into and analyzed as a part of the proposal and appropriate alternatives. Where appropriate, major mitigation measures may be identified and analyzed as separate alternatives in and of themselves where the environmental consequences are distinct and significant enough to warrant separate evaluation.

4.11 Appendix (1502.18). If an EIS is intended to serve other environmental review or consultation requirements pursuant to Section 1502.25, any more detailed information needed to comply with these requirements may be included as an appendix.

4.12 Incorporation by Reference (1502.21). Citations of specific topics will include the pertinent page numbers. All literature references will be listed in the bibliography.

4.13 Incomplete or Unavailable Information (1502.22). The references to overall costs in this section are not limited to market costs, but include other costs to society such as social costs due to delay.

4.14 Methodology and Scientific Accuracy (1502.24). Conclusions about environmental effects will be preceded by an analysis that supports that conclusion unless explicit reference by footnote is made to other supporting documentation that is readily available to the public.

4.15 Environmental Review and Consultation Requirements (1502.25).

A. A list of related environmental review and consultation requirements is available from the Office of Environmental Project Review.

B. If the EIS is intended to serve as the vehicle to fully or partially comply with any of these requirements, the associated analyses, studies, or surveys will be identified as such and discussed in the text of the EIS and the cover sheet will so indicate. Any supporting analyses or reports will be referenced or included as an appendix and shall be sent to reviewing agencies as appropriate in accordance with applicable regulations or procedures.

4.16 Inviting Comments (1503.1).

A. Comments from State agencies will be requested through procedures established by the Governor pursuant to Executive Order 12372, and may be requested from local agencies through these procedures to the extent that they include the affected local jurisdictions. See 511 DM.

B. When the proposed action may affect the environment of an Indian reservation, comments will be requested from the Indian tribe through the tribal governing body, unless the tribal governing body has designated an alternate review process.

4.17 Response to Comments (1503.4).

A. Preparation of a final EIS need not be delayed in those cases where a Federal agency, from which comments are required to be obtained (1503.1(a)(1)), does not comment within the prescribed time period. Informal attempts will be made to determine the status of any such comments and every reasonable attempt should be made to include the comments and a response in the final EIS.

B. When other commentors are late, their comments should be included in the final EIS to the extent practicable.

C. For those EISs requiring the approval of the Assistant Secretary - Policy, Budget and Administration pursuant to 516 DM 6.3, bureaus will consult with the Office of Environmental Project Review when they propose to prepare an abbreviated final EIS (1503.4(c)).

4.18 Elimination of Duplication with State and Local Procedures (1506.2). Bureaus will incorporate in their appropriate program regulations provisions for the preparation of an EIS by a State agency to the extent authorized in Section 102(2)(D) of NEPA. Eligible programs are listed in Appendix I to this Chapter.

4.19 Combining Documents (1506.4). See 516 DM 4.6D.

4.20 Departmental Responsibility (1506.5). Following the responsible official's preparation or independent evaluation of and assumption of responsibility for an environmental document, an applicant may print it provided the applicant is bearing the cost of the document pursuant to other laws.

4.21 Public Involvement (1506.6). See 516 DM 1.6 and 301 DM 2.

4.22 Further Guidance (1506.7). The Office of Environmental Project Review may provide further guidance concerning NEPA pursuant to its organizational responsibilities (110 DM 22) and through supplemental directives (381 DM 4.5B).

4.23 Proposals for Legislation (1506.8). The Legislative Counsel, in consultation with the Office of Environmental Project Review, shall:

A. Identify in the annual submittal to OMB of the Department=s proposed legislative program any requirements for and the status of any environmental documents.

B. When required, insure that a legislative EIS is included as a part of the formal transmittal of a legislative proposal to the Congress.

4.24 Time Periods (1506.10).

A. The minimum review period for a draft EIS will be sixty (60) days from the date of transmittal to the Environmental Protection Agency.

B. For those ElSs requiring the approval of the Assistant Secretary - Policy, Budget and Administration pursuant to 516 DM 6.3, the Office of Environmental Project Review will be responsible for consulting with the Environmental Protection Agency and/or CEQ about any proposed reductions in time periods or any extensions of time periods proposed by those agencies.

----------------------------------------------------------------------------------------------------------------------

Chapter 4

Appendix 1

Programs of Grants to States in Which Agencies Having Statewide

Jurisdiction May Prepare EISs

1.1 Fish and Wildlife Service.

A. Anadromous Fish Conservation (=15.600).

B. Fish Restoration (=15.605).

C. Wildlife Restoration (=15.611).

D. Endangered Species Conservation (=15.612).

E. Marine Mammal Grant Program (=15.613).

1.2 Bureau of Land Management.

A. Wildlife Habitat Management Technical Assistance (=15.219).

1.3 National Park Service.

A. Historic Preservation Grants-in-Aid (=15.904).

B. Outdoor Recreation-Acquisition Development and Planning (=15.916).

1.4 Bureau of Reclamation.

A. National Water Research and Development Program (=15.505).

1.5 Office of Surface Mining.

A. Regulation of Surface Coal Mining and Surface Effects of Underground Coal Mining (=15.250).

B. Abandoned Mine Land Reclamation (AMLR) Program (=15.252).

1.6 Office of Territorial and International Affairs.

A. Economic and Political Development of the Territories and the Trust Territory of the Pacific Islands (=15.875).

Note.-Citations in parenthesis refer to the Catalog of Federal Domestic Assistance. Office of Management and Budget. 1983.

*