About the 35Express

The 35Express project extends approximately 30 miles, through eight cities and two counties, from US 380 in Denton County to I-635 in Dallas County. The Design-Build project is expected to relieve traffic congestion in one of the most heavily traveled corridors in the North Texas region.

Getting Around on the 35Express

Traffic alerts
  • Northbound Interstate 35E Entrance and Exit Ramps Between Post Oak Drive and Corinth Parkway to be Relocated
    Various lanes of northbound I-35E will be closed nightly from 9 p.m. until 6 a.m. Monday, Nov. 3 through Thursday, Nov. 6 to accommodate ramp relocations. This work is in preparation for an upcoming shift of northbound traffic between Corinth Parkway and Post Oak Drive.
  • Full Closure of Bogard Lane Between McGee Lane and the Southbound Interstate 35E Frontage Road Scheduled in Lewisville
    As work continues near FM 407, Bogard Lane will be closed between McGee Lane and the southbound Interstate 35E frontage road beginning 8 a.m., Monday, Oct. 27 through Saturday, Dec. 27.
  • Traffic Shift on North- And Southbound Interstate 35E Between Corinth Parkway and Loop 288 In Denton
    Traffic on north- and southbound I-35E between Corinth Parkway and Loop 288 will shift towards the inside median through Spring 2015. All lanes will remain open.
  • New Traffic Configuration at Belt Line Road
    East- and westbound Belt Line Road will be reduced to two lanes in each direction between Denton Drive and Hutton Drive through late 2014.
  • Long-term Closure of US 77/Dallas Drive Entrance Ramp to Southbound Interstate 35
    The US 77/Dallas Drive entrance ramp to southbound I-35E will be closed through Summer 2015. During the closure, 35Express crews will rehabilitate the ramp.
  • U-Turn Lane at Valwood Parkway and Interstate 35E Closed Through Late 2014
    The U-turn lane at Valwood Parkway from the northbound I-35E frontage road to the southbound I-35E frontage road will be closed through November 2014. Motorists will need to turn left from the signalized intersection to access the southbound I-35E frontage road.

Know Before You Go


Live Traffic Feed

Lane Closures

30-Day Outlook

 

Follow the project on social media and sign up for our e-newsletter and text alerts below.

Have a question or concern? Let us know here.